This document appears to be a Questions and Answers (Q&A) document related to a federal contract opportunity for the project "REPLACE CIRCUIT E BETWEEN SWITCH 2 & 3 AND INSTALL FOUR-WAY SWITCH, NASO, VIRGINIA BEACH, VA" with Solicitation Number N4008524R2775. The scope of work includes replacing circuit E between MW switches 2 and 3, providing a new MW switch to feed the tacan and par, and providing a diesel backup generator to the par, a diesel generator replacement to the tacan and a pad mount distribution transformer replacement at the tacan. The solicitation has a cut-off date of 24 July 2024, and is only open to contractors on the MACC. The document provides a government response to a question about whether a sweeper truck will be required, stating that the contractor is responsible for FOD control within the limits of construction and haul routes at all times.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page Section Para. Dwg #
MIG GOV
07/25/24
Will a sweeper truck be required at all times during the construction?
Contractor is responsible for FOD control within limits of construction and haul routes at all times. Contractor shall remove all FOD that may appear on operational airfield pavements due to contractor operations.
Means and methods are at the discretion of the contractor.
Project Title: REPLACE CIRCUIT E BETWEEN SWITCH 2 & 3
AND INSTALL FOUR-WAY SWITCH, NASO, VIRGINIA BEACH,
VA
Solicitation / RFP#: N4008524R2775 - PPI Cut Off Date: 24 JULY 2024
Amend No.
GOVERNMENT RESPONSE
PPI No.
Offeror
Date
Submitted
REFERENCE
QUESTION
File details come from the government source that posted it. Updated .