Attachment_F_PPI_Spreasheet - MIG GOV_Government Responses.pdf
PDF 11 KB Posted
- Attached to
- REPLACE CIRCUIT E BETWEEN SWITCH 2 & 3 AND INSTALL FOUR-WAY SWITCH, NASO, VIRGINIA BEACH, VA
- Solicitation number
- N4008524R2775
About this file
This document appears to be a set of questions and answers related to a federal contract opportunity to REPLACE CIRCUIT E BETWEEN SWITCH 2 & 3 AND INSTALL FOUR-WAY SWITCH, NASO, VIRGINIA BEACH, VA under Solicitation #N4008524R2775.
The key details are:
- All personnel driving vehicles beyond the flightline and on the airfield will require Airfield Driving Training and Certification, provided at no-cost by NASO AirOps. Non-drivers are not required to have this certification.
- The air show dates are 9/16/24-9/23/24, during which the job site will be shut down.
- A SWPPP is not required as this is a linear project with areas of impact less than 1 acre.
- Due to long lead times for the required 35KV SF6 switch (72 weeks) and cable (24-28 weeks), the contractor requested an extension to the 270-day project completion timeline, which was addressed in an amendment.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page Section Para. Dwg #
MIG GOV
07/24/24
There was mention at the site visit about the need for an Airfield Driving
Certification in order to drive on site. How would we attain that certification and will all subcontractors also need to have that cert?
All personnel driving vehicles beyond the flightline and on the airfield will be required to have Airfield Driving Training and
Certification. This is approximately a two hour class provided at no-cost by NASO
AirOps. Non-drivers are not required to have airfield driving certification.
MIG GOV
07/24/24
What are the dates of the air show and when the job site will be shut down during this time?
9/16/24-9/23/24
MIG GOV
07/24/24 Will a SWPPP be required for this project?
No as this is a linear project with many smaller areas of impact; none of which are greater than 1 acre.
MIG GOV
07/24/24
Time to complete for this project was given as 270 days. Current leads times for the required 35KV SF6 switch is 72 weeks and for the cable is 24-28 weeks.
We request an extension of the time to complete on this project based on these lead times.
See amendment to the Specifications and
General Conditions provided by the Contract
Specialist
Project Title: REPLACE CIRCUIT E BETWEEN SWITCH 2 & 3
AND INSTALL FOUR-WAY SWITCH, NASO, VIRGINIA BEACH,
VA
Solicitation / RFP#: N4008524R2775 - PPI Cut Off Date: 24 JULY 2024
Amend No.
GOVERNMENT RESPONSE
PPI No.
Offeror
Date
Submitted
REFERENCE
QUESTION
File details come from the government source that posted it. Updated .