This document is an Amendment 0001 to Solicitation N4008524R2670 for the P-1068 SOF Renovate Operations Building project at NAS Oceana in Virginia Beach, VA. The amendment provides responses to pre-proposal inquiries, including confirming that access to the roof and second floor will be available during the site visit on August 8, 2024. It also attaches the site visit log from August 8, 2024 and provides the B355 record drawings from 1989. The solicitation is restricted to MACC holders under the Design-Build (DB)/Design-Bid-Build (DBB), Indefinite-Delivery/Indefinite Quantity (IDIQ), Multiple Award Construction Contract (MACC) for general construction in the Hampton Roads area of responsibility. The proposal due date and other key solicitation details have not changed.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
12 AUG 2024
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than item 6) CODE
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
See Item 6
8. NAME AND ADDRESS OF CONT RACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
N40085-24-R-2670
X 9B. DATED (SEE ITEM 11)
23 JUL 2024
10A. MOD. OF CONT RACT /ORDER NO.
10B. DAT ED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENT S OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15 and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT
TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNT ING AND APPROPRIAT ION DAT A (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICAT IONS OF CONT RACTS/ORDERS.
IT MODIFIES THE CONT RACT /ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONT RACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONT RACT /ORDER IS MODIFIED TO REFLECT THE ADMINIST RAT IVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORT ANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
N40085-24-R-2670 - P-1068 SOF Renovate Operations Building, NAS Oceana, Virginia Beach, VA
See SF30 block 14 continuation page
Contract POC: Karen Richardson, karen.y.richardson3.civ@us.navy.mil
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONT RACTING OFFICER (Type or print)
TEL: EMAIL:
15B. CONT RACT OR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNIT ED STATES OF AMERICA
BY ______________________________________________
(Signature of Contracting Officer)
16C. DATE SIGNED
12 Aug 2024
EXCEPTION TO SF 30
STANDARD FORM 30 (Rev.
APPROVED BY OIRM 11-84 Prescribed by GSA
FAR (48 CFR)
N40085-24-R-2670
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following have been added by full text:
AMENDMENT 0001
This amendment is issued to incorporate the following:
1. Provide PPI Responses
2. Provide Site Visit Log from 08 August 2024 (attached separately)
3. Provide B355 Record Drawings 1989 (attached separately)
1. Provide PPI Responses
PPI# Page Section Paragraph Question Answer 3 Solicitation:
N/A Site Visit Reference the Site Visit scheduled for Thursday, 08 August 2024. Will photographing the areas of work be allowed?
No
AE105
(Base Bid) & AE103 (Bid Option Item No. 3)
N/A N/A
Reference Roof Plan Sheets for the Base Bid (AE105) and Bid Option Item No. 3 (AE103). Can access to the roof be made available at the Site Visit on August 8, 2024?
Roof was accessible during site visit on August 8, 6 4
Pre- Proposal Inquiries (PPIs)
Solicitation
Reference the Pre-Proposal Inquiries requirements identified in the Solicitation, which includes submission shall be no later than 2:00 PM local time ten (10) days prior to proposal due date.
Are the "days" referenced work week days or calendar days? If not calendar days, please consider an extension to the cut-off day to allow for composition of questions arising as a result of the Site Visit on August 8, 2024.
It's 10 calendar days
N40085-24-R-2670
PD101 (Base Bid)
N/A N/A
Plan Sheet PD101 indicates demolition work which appears to require access to the second floor area. The Base Bid documents do not appear to included any second floor drawings or reference to second floor access. Please confirm access to the second floor will be available should Bid Option Item No. 3 not be awarded.
Second floor will be available
2. Provide Site Visit Log from 08 August 2024. (attached separately)
3. Provide B355 Record Drawings 1989 (attached separately)
(End of Summary Changes)