Attachment A- Part 2 - 01 33 10.05 20_REV.pdf
PDF 58 KB Posted
- Solicitation number
- N4008524R2608
About this file
This document is a section from the specifications for a federal contract opportunity to perform exterior renovation work on Building W143 at Naval Station Norfolk, Virginia. The key details are:
The specification outlines the requirements for contractor-originated design documents and design submittals, including design drawings, specifications, basis of design, and record documents. It specifies the design quality control and approval processes, with the contractor responsible for reviewing and certifying the design submittals and the government as the approving authority. The contractor must prepare design documents, including BIM submittals, in accordance with the referenced UFC and UFGS requirements. Specific requirements are provided for the design drawings, specifications, and basis of design. The contractor must also prepare record documents, including record drawings, DD Form 1354, and record model. The specification also addresses design changes, variations, and the order of precedence between the contract components.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXTERIOR RENOVATION OF BLDG W143 1709051
SECTION 01 33 10.05 20
DESIGN SUBMITTAL PROCEDURES
05/ 17, CHG 6: 03/ 23
PART 1 GENERAL
1.1 SUMMARY
This section includes requirements for Contractor-originated design documents and design submittals.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. DEPARTMENT OF DEFENSE (DOD)
FC 1-300-09N (2014; with Change 6, 2021) Navy and Marine Corps Design
UFC 1-200-01 (2022) DoD Building Code
UFC 1-300-08 (2009; with Change 2, 2011) Criteria for Transfer and Acceptance of DoD Real Property
1.3 GENERAL DESIGN REQUIREMENTS
Contractor-originated design documents must provide a project design that complies with the Request For Proposal (RFP), FC 1-300-09N , UFC 1-200-01 , the Core UFCs, and other UFC's listed above.
1.4 SUBMITTALS
Submit design submittals, including shop drawings used as design drawings, to the Government for approval. The use of a "G" following a submittal indicates that a Government approval action is required. Submit the following in accordance with this section and Section 01 33 00.05 20
CONSTRUCTION SUBMITTAL PROCEDURES.
SD-01 Preconstruction Submittals
Consolidated RFP Documents; G
Submittal Register; G
SD-05 Design Data
Design Drawings; G
Specifications; G
Basis of Design; G
Design Submittals; G
SECTION 01 33 10.05 20 Page 1
BIM Project Execution Plan (PxP); G
Design Model; G
SD-11 Closeout Submittals
Record Documents; G
DD Form 1354; G
Final Record Model; G
1.5 DESIGN QUALITY CONTROL
1.5.1 Contractor Reviewing and Certifying Authority
The QC organization is responsible for reviewing and certifying that design submittals are in compliance with the contract requirements.
1.5.2 Government Approving Authority
The Contracting Officer is the approving authority for design submittals.
1.5.3 Designer of Record Certifying Authority
The Designer of Record (DOR), as registered and defined in FC 1-300-09N , is the design certifying authority. The DOR accepts responsibility for design of work in each respective design discipline, by stamping and approving final construction drawings submitted to the Government approval authority.
1.5.4 Contractor Construction Actions
Purchase of material and equipment, fabrication and construction of any elements may proceed upon Government signed approval of the final design submission. Final submission to include sealed, signed and certified documents by the DOR, Design Quality Control (DQC) Manager, and Quality Control (QC) Managers.
1.5.5 Contractor's Responsibilities
a. Designate a lead licensed architect or engineer to be in responsible charge to coordinate the design effort of the entire project. This lead architect or engineer must coordinate all design segments of the project to assure consistency of design between design disciplines.
b. With the Designer of Record, verify site information provided in the RFP. In addition, provide additional field investigations and verification of existing site conditions as may be required to support the development of design and construction of the project.
c. Indicate on the transmittal form accompanying submittal which design submittals are being submitted as shop drawings.
d. Advise Contracting Officer of variations, as required by paragraph
DESIGN CHANGE AND VARIATIONS.
e. Provide an updated, cumulative submittal register with each design
SECTION 01 33 10.05 20 Page 2 package that identifies the design and construction submittals required by that design package and previous submittals.
f. Refer to Section 01 78 24.00 20 FACILITY DATA WORKBOOK (FDW) for Contractor's eOMSI responsibilities.
1.5.6 QC Organization Responsibilities
a. The QC Manager must certify design submittals for compliance with the contract documents. The DOR stamp on drawings indicates approval from the DOR.
b. QC organization must certify submittals forwarded by the Designer of Record (DOR) to the Contracting Officer with the following certifying statement:
"I hereby certify that the (equipment) (material) (article) shown and marked in this submittal is that proposed to be incorporated with Contract Number (insert contract number here), is in compliance with the contract documents, and is submitted for Government approval.
Certified by Design Quality Control (DQC) Manager _____________________, Date _______ Certified by QC Manager________________________________, Date ______"
c. Sign certifying statement. The persons signing certifying statements must be the QC organization members designated in the approved QC plan. The signatures must be in original ink. Stamped signatures are not acceptable.
d. Update submittal register as submittal actions occur and maintain the submittal register at project site until final approval of all work by Contracting Officer.
e. Retain a copy of approved submittals at project site.
1.5.7 Government Responsibilities
The Government will:
a. Note date on which submittal was received from QC manager, on each submittal.
b. Perform a quality assurance (QA) review of submittals. Government will notify Contractor when comments for that design package are posted and ready for Contractor evaluation and resolution.
c. Upon submittal of final design package and resolution of comments by the Contractor, the Government will sign final design package, when approved, and return electronic copy of signed design documents to the Contractor.
1.5.7.1 Actions Possible
Submittals will be returned with one of the following notations:
a. Submittals may be marked "approved." Submittals marked "approved" indicate a quality assurance (QA) review has been performed.
SECTION 01 33 10.05 20 Page 3
Government review or approval of any portion of the proposal or final design does not relieve the Contractor from responsibility for meeting the contract requirements or for any error that may exist, because under the Quality Control (QC) requirements of this contract, the Contractor is responsible for ensuring information contained within each submittal accurately conforms with the requirements of the contract documents. Furthermore, Government review or approval of a submittal is not to be construed as a complete check.
b. Submittals marked "not reviewed" indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and certified by Contractor, or is not complete. Submittal will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
c. Submittals marked "revise and resubmit" or "disapproved" indicate submittal is incomplete or does not comply with design concept or requirements of the contract documents and must be resubmitted with appropriate changes. If work has been started on the unacceptable portion of the design submittal, the Contractor must propose corrective action. No further work is allowed to proceed until the issue is resolved in a manner satisfactory to the Government.
1.6 DESIGN DOCUMENTS
Provide design documents that include basis of design, design drawings, and design specifications, reports, and submittal register in accordance with FC 1-300-09N , Navy and Marine Corps Design Procedures.
The Contractor is required to make product, material, and system selections during the project design and indicate these choices on the design documents. Accomplish this by submitting design drawings and specifications that include proprietary submittal information such as manufacturers name, product names, model numbers, product data, manufactures information, provided optional features, appropriate connections, fabrication, layout, and product specific drawings.
Adherence to RFP submittal requirements and provision of DOR approved construction submittal information on the design submittals - eliminates the need for follow-on traditional construction submittals after the final design is approved.
The Contractor is required to submit proprietary information to describe the construction submittal information in the design documents for all products, materials, and systems submittals listed below:
a. All building enclosure components.
Refer to Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES for requirements pertaining to Contractor proposed design changes or variations.
1.7 DESIGN DRAWINGS
Prepare, organize, and present design drawings in accordance with the requirements of FC 1-300-09N , Navy and Marine Corps Design Procedures.
Submit all CAD files for the final drawings on CD-ROM or DVD disks in the
SECTION 01 33 10.05 20 Page 4 appropriate AutoCAD or REVIT format. Drawing files must be full files, uncompressed and unzipped.
1.7.1 Design Drawings Used as Shop Drawings
Design drawings may be prepared more like shop drawings to minimize construction submittals after final design is approved. If the Contractor chooses or is required to include the construction submittal information on the design documents, indicate proprietary information on the design drawings as necessary to describe the products, materials, or systems that are to be used on the project. Construction submittal information included directly in the design drawings must be approved by the DOR. All design documents must be professionally signed in accordance with FC 1-300-09N , Navy and Marine Corps Design Procedures.
1.7.2 Drawing Format For Design Drawings Used as Shop Drawings
The Contractor-originated drawings will be used as the basis for the record drawings. Shop drawings included as design documents must comply with the same drawing requirements such as drawing form, sheet size, layering, lettering, and title block used in design drawings.
1.7.3 Identification of Design Drawings Used as Shop Drawings
The Contractor's transmittal letter and submittal register must indicate which design drawings are being submitted as shop drawings.
1.7.4 Naval Facilities (NAVFAC) Engineering Command Drawing Numbers
Number the final Contractor-originated design drawings consecutively with NAVFAC drawing numbers. Determine the total number of sheets required for the complete set of drawings before requesting the NAVFAC drawing numbers from the Contracting Officer.
1.7.5 Seals and Signatures on Documents
All final Contractor-originated design drawings must be signed, dated, and bear the seal of the registered architect or the registered engineer of the respective discipline in accordance with FC 1-300-09N . This seal must be the seal of the Designer of Record for that drawing, and who is professionally registered for work in that discipline. A principal or authorized licensed or certified employee must electronically sign and date final drawings and cover sheet, in accordance with FC 1-300-09N . The design drawing coversheets must be sealed and signed by the lead licensed architect or engineer of the project design team. Indicate the Contractor's company name and address on the drawing coversheets of each design submittal. Application of the electronic seal and signature accepts responsibility for the work shown thereon.
1.7.6 Units of Measure
Utilize English Inch-Pound units of measure on the design documents.
1.8 BUILDING INFORMATION MANAGEMENT/MODELING (BIM)
Include BIM submittals as required by and complying with FC 1-300-09N :
a. BIM Project Execution Plan (PxP)
SECTION 01 33 10.05 20 Page 5
b. Design Model
c. Record Model (With Record Documents)
1.9 SPECIFICATIONS
Provide a Contractor-originated design specification that in conjunction with the drawings, demonstrates compliance with requirements of the RFP.
The specified products, materials, systems, and equipment that are approved by the DOR; submitted to the Government by the Contractor; and reviewed by the Contracting Officer must be used to construct the project. UFGS sections contained in RFP Part 2 become a part of the Contractor-originated Division 01 specification without modification.
Specification Sections contained in RFP Part 5 become a part of the Contractor-originated specification without modification.
1.9.1 Specifications Components and Format
The Contractor must prepare design specifications that include a UFGS specification for each product, material, or system on the project. If the Contractor chooses or is required above to combine design and construction submittal information on the design documents, provide a UFGS specification and also proprietary information such as catalog cuts and manufacturers data that demonstrates compliance with the RFP. Organize the specifications using Construction Specification Institute (CSI)
MasterFormat TM unless the Contracting Officer requires a UniFormat organization. Navy's use of system specifications takes precedence over CSI MasterFormat component breakdown and related component specifications. Provide project specifications to include the following:
a. Provide the specification cover sheet with the professional seal and signature of the lead licensed architect or engineer of the project design team. Indicate the Contractor's company name and address on the specification coversheet.
b. Table of contents for entire specification.
c. Individual UFGS specification sections for each product, material, and system required by the RFP. Edit UFGS sections in accordance with RFP Part 4, PTS Section Z-10, Design Submittals.
d. If proprietary information is provided or required, include a coversheets for the product, material, or system information that is being proprietarily specified. This information is to follow the related UFGS specification.
e. If proprietary information is provided or required, include highlighted and annotated Catalog Cuts, Manufacturer's Product Data, Tests, Certificates, Manufactures information and letters for each product, material, or system that is being proprietary specified.
f. Coordinated submittal register for all products, materials and systems with each design submittal. Provide a cumulative register that identifies the design and construction submittals required by each design package along with previous design submittals. The DOR must assist in developing the submittal register by determining which submittal items are required to be approved by the DOR. Complete all fields in the final submittal register in order to obtain Government approval of the final design.
SECTION 01 33 10.05 20 Page 6
1.9.2 Specifications Section Source Priority
Choose UFGS sections that describe the products, materials, and systems that are used on the project. Use current UFGS sections that are available on the Whole Building Design Guide website (available at this website:
https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs ) and give priority to the Unified Tri-Service UFGS sections (no spec number suffix) and UFGS that are prepared by NAVFAC (.00 20 suffix). Only use a UFGS section prepared by another DoD Component (.00 10, and .00 30 suffix), if an applicable NAVFAC prepared specification section does not exist. Do not use Army (.00 10 suffix) and NASA (.00 40 suffix) specifications from Division 22 through Division 28. If no applicable UFGS technical specification exists to meet your project requirements, consult with the NAVFAC Component for guidance and create a new UFGS specification in accordance with UFC 1-300-02, Unified Facilities Guide Specifications (UFGS) Format Standard.
1.9.3 Identification of Manufacturer's Product Data Used with Specifications
Provide complete and legible catalog cut sheets, product data, installation instructions, operation and maintenance instructions, warranty, and certifications for products and equipment for which final material and equipment choices have been made. Indicate, by prominent notation, each product that is being submitted including optional manufacturer's features, and indicate where the product data shows compliance with the RFP.
Coordinate with Section 01 78 24.00 20 FACILITY DATA WORKBOOK (FDW) for Contractor's eOMSI responsibilities.
1.9.4 Specification Software
Submit the final specification source files in SpecsIntact.
1.10 BASIS OF DESIGN
Prepare, organize, and present basis of design in accordance with the requirements of FC 1-300-09N . The basis of design must be a presentation of facts at the Concept Design Workshop to demonstrate the concept of the project is fully understood and the design is based on sound engineering principles. Provide design analyses for each discipline and include the following:
a. Basis of design that includes:
(1) An introductory description of the project concepts that addresses the salient points of the design;
(2) An orderly and comprehensive documentation of criteria and rationale for system selection; and
(3) The identification of any necessary licenses and permits that are anticipated to be required as a part of the design or construction process. The "Permits Record of Decision" (PROD) form provided must be used for recording permits.
SECTION 01 33 10.05 20 Page 7
b. Code and criteria search must identify all applicable codes and criteria and highlight specific requirements within these codes and criteria for critical issues in the facility design.
c. Calculations as specified and as needed to support this design.
d. Provide a written/graphic descriptions for each unique wall assembly used as part of exterior enclosure barriers.
e. Fall Protection Analysis
f. Draft and Interim DD Form 1354 that document the real property assets of the project. Refer to RECORD DOCUMENTS paragraphs in this section for requirements.
g. eOMSI Facility Data Workbook (FDW)
h. BIM PxP
1.10.1 Basis of Design Format
The basis of design for each design discipline must include a cover page indicating the project title and locations, contract number, table of contents, tabbed separations for quick reference, and bound in separate volumes for each design discipline.
1.10.2 Design Calculations
Place the signature and seal of the designer responsible for the work on the cover page of the calculations for the respective design discipline.
1.10.3 Fall Protection Analysis
Eliminate fall hazards in the facility or if not feasible provide control measures to protect personnel conducting maintenance work after completion of the project. Identify fall hazards in the Basis of Design with the Design Development and Prefinal submittals. The analysis must describe how fall hazards are considered, eliminated, prevented or controlled to prevent maintenance personnel from exposure to fall hazards while performing work at heights. Refer to RFP Part 2, Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS for fall hazard protection requirements.
1.11 RECORD DOCUMENTS
1.11.1 Record Drawings
The as-built modifications must be accomplished by electronic drafting methods on the Contractor-originated DWG design drawings to create a complete set of record drawings.
a. For each record drawing, provide CAD drawing identical to signed Contractor-originated PDF drawing, that incorporates modifications to the as-built conditions. In addition, copy initials and dates from the Contracting Officer approved .PDF documents to the title block of the record CAD.DWG drawings. The RFP reference or definitive drawings are not required for inclusion in the record set of drawings.
b. After all as-built conditions are recorded on the CAD.DWG files, produce a PDF file of each individual record drawing in conformance
SECTION 01 33 10.05 20 Page 8 with FC 1-300-09N . Electronic signatures are not required on record drawings.
c. Provide a searchable electronic copy of the photo documentation used in the QC Daily Reports. Refer to Section 01 45 00.05 20 DESIGN AND
CONSTRUCTION QUALITY CONTROL.
1.11.2 Source Documents
Provide the specifications, basis of design, reports, surveys, record model, calculations, and any other contracted documents on the CD-ROM or DVD disk with the record drawings.
1.11.3 DD Form 1354
Prepare a Draft and Interim DD Form 1354, TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY, in accordance with UFC 1-300-08 . Coordinate the identification of quantities of appropriate asset construction categories with the Contracting Officer and the RPAO.
a. The Government will provide the Initial Draft DD Form 1354, Transfer and Acceptance of Military Real Property filled in with the appropriate Real Property Unique Identifiers (RPUID) and related construction Category Codes to summarize the designed real property assets that apply to this contract. Modify and include any necessary changes to the DD Form 1354 when meeting with the Contracting Officer and the Real Property Accounting Officer during the Pre Construction Meeting and the Project Closeout Meetings. The Contractor must provide the Interim DD Form 1354 that uses the appropriate division of the RPUIDs/ Category Codes to represent the final constructed facility and include all associated cost.
(1) Coordinate the Contractor's Price and Payment structure with the structure of the RPUIDs/ Category Codes.
(2) Divide detailed asset breakdown into the RPUIDs and related construction Category Codes and populate associated costs which represent all aspects of the work. Where assets diverge into multiple RPUID/Category Codes, divide the asset and provide the proportion of the assets in each RPUID/ Category Code. Assets and related RPUID/ Category Codes may be modified by the Contracting Officer as necessary during course of the work.
(3) Coordinate identification and proportion of these assets with the Government Real Property Accounting Officer.
(4) Cost data accumulated under this section are required in the preparation of DD Form 1354.
b. After award of the contract but prior to commencement of any work, meet with the Contracting Officer to discuss and develop a clear understanding relative to the administration of the Draft and Interim DD Form 1354 Submittal.
c. Draft DD Form 1354. DOR must determine quantities of applicable real property assets broken out by construction categories and submit a "Draft DD Form 1354" for Government approval as a part of the Basis of Design included with the Prefinal Design submittal. "Draft DD Form 1354" must include all quantities and units of measure, but does not
SECTION 01 33 10.05 20 Page 9 require cost breakdown. The Real Property Accountable Officer (RPAO) will provide the first draft of the DD1354 to the contractor with RPUIDs and CCNS on it.
d. Interim DD Form 1354. Coordinate with the DOR and update the Draft DD Form 1354 submission to include any additional assets, improvements, or alterations that occurred during construction. Use the Draft DD Form 1354 and the Section 01 20 00 PRICE AND PAYMENT PROCEDURES to identify costs. Submit Interim DD Form 1354 to the Government for approval 30 days prior to the Beneficial Occupancy Date (BOD). If modifications to the Interim DD Form 1354 are required by the Government, the corrected version must be submitted prior to the BOD.
Coordinate with Section 01 20 00 PRICE AND PAYMENT PROCEDURES for construction categories and associated category codes. The Contractor's Schedule of Prices must allocate the total cost of construction to the appropriate category codes.
When documenting demolition work, the DD Form 1354 must list the quantitative data associated with this work as a negative value to show the cost should be deleted from the Navy asset data store. Coordinate with the Installation Real Property POC to assist in determining the negative value for demolition work.
There are two ways to account for the demolition portion of the project and to document the reduction of real property: (1) attach an Authorization for Demolition form 18 (Service-specific) to the DD Form 1354 to document category codes and quantities of demolished real property. These should be listed separately from constructed/transferred item numbers; or, (2) indicate, as additional DD Form 1354 item numbers, all demolished real property facility numbers and category codes using negative numbers (shown in parenthesis) for units of measure, and in block 18 indicate N/A for costs. Disposal cost within the footprint of the project is added into total construction cost of new facility prompting the demolition.
1.11.4 Record Model
Provide Record Model in accordance with FC 1-300-09N .
1.12 REQUEST FOR INFORMATION
Submit copies of all completed Request for Information (RFI) correspondences to the Contracting Officer within 5 working days of the RFI completion.
PART 2 PRODUCTS
2.1 CONSOLIDATED RFP DOCUMENTS
Within four weeks after contract award, provide three electronic and hard copies of consolidated RFP documents incorporating the Contractor's Proposal and all RFP amendments and revisions that are contained in the contract award. Identify the changes to the RFP with the "Red-lining" or "Track Changes" feature of SpecsIntact or MS Word to highlight the pre-award modifications to the contract. Identify the amendment source at each addition and deletion by annotation, such as footnote or reference in parenthesis.
SECTION 01 33 10.05 20 Page 10
2.2 DESIGN SUBMITTALS
Complete the Contractor-originated design submittals as defined by this contract, and coordinate with the approved design network analysis schedule.
2.2.1 Design Submittal Packages
The Government prefers to review for Quality Assurance (QA) as few submittal packages as possible. Site and Building Design Submittal Packages are required, however Critical Path Design Submittals are acceptable if they are substantiated as having an impact to the critical path in the Government approved Network Analysis Schedule. A Critical Path submittal must include all design analyses, drawings, specifications and product data required to fully describe the project element for Government review.
Examples of project elements that may be submitted as Critical Path Design Submittal Packages are: Master Plan Design, Demolition Design, Foundation Design, Structural Design, Building Enclosure Design, Remaining Work Design, Furniture/Equipment Design, long lead items, or any other construction activity or project element that can be organized into a submittal package that can be reviewed and approved by the Government without being contingent upon subsequent design submittals.
2.2.1.1 Site Design
The Site Design typically includes the following components:
a. Master Site Plan
2.2.1.2 Building Design
The Building Design typically includes the following components:
a. Building Enclosures
b. Remaining Work
2.2.2 Required Design Submittals
Provide the following Design Submittal packages. Provide comprehensive, multi-discipline design packages that include design documentation for project elements, fully developed to the design stage indicated, and in accordance with FC 1-300-09N , except where specified otherwise.
a. Concept Design presented at Concept Design Workshop
b. Prefinal (100 percent) Design - Government Progress QA. 14 calendar day Government review time.
c. Final Design - Government QA. 14 calendar day Government review time for submittals requiring Government approval prior to construction.
2.2.3 Critical Path Design Submittals
Provide Critical Path Design Submittals that include design documents for the project elements involved. Include and provide full documentation that would normally have been provided in earlier submittal stages, such
SECTION 01 33 10.05 20 Page 11 as Design Development Phase.
a. 100 percent (Prefinal) Design - Government Progress QA. 14 calendar day Government review time.
b. Final Design - Government QA. 14 calendar day Government review time for submittals requiring Government approval prior to construction.
2.2.4 Review Copies of Design Submittal Packages
a. Provide bound copies of each design submittal package for review to the following reviewers. Addresses for mailing will be furnished at the PAK meeting.
(1) 8 paper copies to the NAVFAC component and 1 electronic copies of the Final submittals.
(2) 4 paper copies to the Activity claimant.
b. Provide the same quantities of copies for resubmittals, as required for each design submittal.
2.2.5 Design Submittal Review Schedule
Use the time frames for Government submittal review identified in the RFP. For construction scheduling purposes add additional time to the identified minimum review time periods to allow for the following scheduling conditions:
(1) Submittals received after noon will be logged in on the following business day.
(2) Federal holidays, including the period between Christmas and New Year's Day, will be considered non-working days for Government personnel in reviewing design submittals and attending design related meetings.
(3) Postpone delivery if Government personnel to receive the submittal are unavailable. Assure in advance of the submittal delivery it can be received.
(4) Postpone delivery when heightened security restricts access to the Base. Coordinate heightened security requirements in advance with the CM.
(5) Period of review for a resubmittal is the same as the initial submittal. Review time for resubmittals caused by non-conformance, do not result in a change in contract duration or cost.
2.2.6 Distribution of Approved Final Design Drawings and Specification to Government Representatives
Submit within 14 calendar days of receiving the Government Approved Final Design Documents, which includes any Critical Path Final Design Document Packages, electronic and hardcopy(s) of these final documents to Government representatives for use during the construction of the project. If Critical Path Submittal Packages are used, provide coversheets and index to identify each sheet and how this Critical Path
SECTION 01 33 10.05 20 Page 12
Submittal Package fits into the overall project. Provide the number and type of copies of the final design documents to the following Government representative:
a. Two electronic and two hard copys to the Project Manager.
b. Three hard copys to the Contracting Officer.
c. Four hard copys to the Client.
2.3 IDENTIFICATION OF DESIGN SUBMITTALS
Provide a title sheet to clearly identify each submittal, the completion status, and the date. The title sheet must use the standard format indicated in the FC 1-300-09N for title sheets. The title sheet must be unique to a particular design submittal. Submit the project title sheet with design status and date for the design submittals.
2.3.1 Critical Path Submittal Title Sheet
Identify Critical Path submittals as such and include a title sheet indicating the type of critical path submittal, the level of completion of the individual drawings, and which drawings are approved for construction.
2.3.2 Construction Document Validation
All CAD design documents used to construct the facility must bear a visible and legible AutoCAD generated plotstamp in the lower right-hand margin of each drawing. The plotstamp information on the jobsite construction documents must match the plotstamp information contained on the following development stages of the design documents:
a. The Final Critical Path Submittal or the Final Design Submittal professionally signed by the DOR and submitted for Government approval.
b. The Final Critical Path Submittal or the Final Design Submittal drawings that have been approved by the Government. This development stage may be combined with "c." below, if issued at the same time.
c. The Final Critical Path or Final Design drawings that have been included in the contract by modification.
d. The Final Critical Path or Final Design drawings which include subsequent revisions to the design documents that have been included in the contract by modifications.
Issue new drawings for construction which bear the current plotstamp once a new development stage of the design documents has been accomplished.
Design documents which do not bear a plotstamp that matches the corresponding plotstamp exhibited on the design documents described above, are not allowed to be used for the construction of the project. The plotstamp must bear the date and time of the plot, at a minimum. Maintain a plotstamp record at the jobsite that lists the applicable plotstamp information for each drawing through each stage of development described above.
SECTION 01 33 10.05 20 Page 13
PART 3 EXECUTION
3.1 CONTRACTOR'S RESOLUTION OF COMMENTS
Provide written responses to all written comments by the Government.
Resubmittal of an unacceptable design submittal must be a complete package that includes all the required, specified components of that design submittal. When required by the Government, Contractor resubmittal of design package, due to nonconformance to the contract, is not a delay in the contract.
3.2 DESIGN CHANGE AND VARIATIONS
A design change is when the design is revised from what was reviewed by the Government during any phase of the design process prior to Government approval of the Final Design. A variation is any portion of the design that differs from the requirements of the solicitation, accepted proposal, or final design after Government approval of the Final Design. Design changes and variations require Government approval and only variations that are advantageous to the Government will be considered. Refer to Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES for further explanation and requirements of design change and variation. Discuss design changes and variations with the Contracting Officer before submission to address functional and quality requirements are met and minimize rejections and resubmittals. When contemplating a design change or variation that results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
The Contractor must immediately notify the Government of all potential design changes and variations via a Request for Information (RFI) which must be clearly marked as "DESIGN CHANGE" or "VARIATION" to the Contracting Officer. Design changes or variations that the Contractor asserts will require a contract modification to adjust the cost/price or schedule are not allowed to be incorporated in the design during any phase of the design process without prior documented approval from the Contracting Officer. Contractors will not receive compensation for any unauthorized design changes or variations which have been included in the Government approved Final Design. Include the following information in the design change and variation RFIs:
a. Indicate the RFP Parts, sections, and paragraphs affected by this design change or variation,
b. The scope of work of the design change or variation,
c. The reason for the proposed change,
d. Explanations of how the variation is advantageous to the Government.
e. Indicate which upcoming design submittal will be affected by the subject design change,
f. Explanation of contract cost/price and schedule impacts or provide an affirmative statement indicating that the design change or variation will not have an impact on the contract cost/price or schedule.
g. Coordination measures proposed to incorporate the design change or variation into the construction.
SECTION 01 33 10.05 20 Page 14
h. Upon request by the Contracting Officer, submit a cost proposal prepared using the UniFormat Work Breakdown Structure for all design changes and variations that have cost or schedule impacts. Submit a proposal that provides cost breakdown of each UniFormat system or subsystem that is applicable to the design change or variation.
Utilize the units of measure indicated in the UniFormat Structure at the NAVFAC DB RFP website, https://www.wbdg.org/ffc/navy-navfac/design-build-request-proposal .
3.3 THE CONTRACT AND ORDER OF PRECEDENCE
3.3.1 Contract Components
The contract consists of the solicitation, the approved proposal, and the final design.
3.3.2 Order of Precedence
In the event of conflict or inconsistency between any of the below described portions of the conformed contract, precedence must be given in the following order:
a. Any portions of the proposal or final design that exceed the requirements of the solicitation.
(1) Any portion of the proposal that exceeds the final design.
(2) Any portion of the final design that exceeds the proposal.
(3) Where portions within either the proposal or the final design conflict, the portion that most exceeds the requirements of the solicitation has precedence.
b. The requirements of the solicitation, in descending order of precedence:
(1) Standard Form 1442, Price Schedule, and Davis Bacon Wage Rates.
(2) Part 1 - Contract Clauses.
(3) Part 2 - General Requirements.
(4) Part 3 - Project Program Requirements.
(5) Part 6 - Attachments (excluding Concept Drawings).
(6) Part 5 - Prescriptive Specifications exclusive of performance specifications.
(7) Part 4 - Performance Specifications exclusive of prescriptive specifications.
(8) Part 6 - Attachments (Concept Drawings).
c. Within Part 3 - Project Program Requirements Section 5.0 ROOM REQUIREMENTS provides detailed requirements on a room by room basis that further defines requirements that are in addition to the
SECTION 01 33 10.05 20 Page 15
ENGINEERING SYSTEMS REQUIREMENTS SECTION.
3.3.2.1 Government Review or Approval
Government review or approval of any portion of the proposal or final design does not relieve the Contractor from responsibility for errors or omissions with respect thereto.
-- End of Section --
SECTION 01 33 10.05 20 Page 16
| 01 33 10.05 20 - DESIGN SUBMITTAL PROCEDURES |
| PART 1 GENERAL |
| 1.1 SUMMARY |
| 1.2 REFERENCES |
| 1.3 GENERAL DESIGN REQUIREMENTS |
| 1.4 SUBMITTALS |
| 1.5 DESIGN QUALITY CONTROL |
| 1.5.1 Contractor Reviewing and Certifying Authority |
| 1.5.2 Government Approving Authority |
| 1.5.3 Designer of Record Certifying Authority |
| 1.5.4 Contractor Construction Actions |
| 1.5.5 Contractor's Responsibilities |
| 1.5.6 QC Organization Responsibilities |
| 1.5.7 Government Responsibilities |
| 1.5.7.1 Actions Possible |
| 1.6 DESIGN DOCUMENTS |
| 1.7 DESIGN DRAWINGS |
| 1.7.1 Design Drawings Used as Shop Drawings |
| 1.7.2 Drawing Format For Design Drawings Used as Shop Drawings |
| 1.7.3 Identification of Design Drawings Used as Shop Drawings |
| 1.7.4 Naval Facilities NAVFAC Engineering Command Drawing Numbers |
| 1.7.5 Seals and Signatures on Documents |
| 1.7.6 Units of Measure |
| 1.8 BUILDING INFORMATION MANAGEMENTMODELING BIM |
| 1.9 SPECIFICATIONS |
| 1.9.1 Specifications Components and Format |
| 1.9.2 Specifications Section Source Priority |
| 1.9.3 Identification of Manufacturer's Product Data Used with |
| 1.9.4 Specification Software |
| 1.10 BASIS OF DESIGN |
| 1.10.1 Basis of Design Format |
| 1.10.2 Design Calculations |
| 1.10.3 Fall Protection Analysis |
| 1.11 RECORD DOCUMENTS |
| 1.11.1 Record Drawings |
| 1.11.2 Source Documents |
| 1.11.3 DD Form 1354 |
| 1.11.4 Record Model |
1.12 REQUEST FOR INFORMATION
| PART 2 PRODUCTS |
| 2.1 CONSOLIDATED RFP DOCUMENTS |
| 2.2 DESIGN SUBMITTALS |
| 2.2.1 Design Submittal Packages |
| 2.2.1.1 Site Design |
| 2.2.1.2 Building Design |
| 2.2.2 Required Design Submittals |
| 2.2.3 Critical Path Design Submittals |
| 2.2.4 Review Copies of Design Submittal Packages |
| 2.2.5 Design Submittal Review Schedule |
| 2.2.6 Distribution of Approved Final Design Drawings and Specification to |
| 2.3 IDENTIFICATION OF DESIGN SUBMITTALS |
| 2.3.1 Critical Path Submittal Title Sheet |
| 2.3.2 Construction Document Validation |
| PART 3 EXECUTION |
| 3.1 CONTRACTOR'S RESOLUTION OF COMMENTS |
| 3.2 DESIGN CHANGE AND VARIATIONS |
| 3.3 THE CONTRACT AND ORDER OF PRECEDENCE |
| 3.3.1 Contract Components |
| 3.3.2 Order of Precedence |
| 3.3.2.1 Government Review or Approval |