This amendment to a solicitation provides updated details for a site visit and modifies the deadline for pre-proposal inquiries. The solicitation is for design-build structural repairs to Bridge 2 at Portsmouth Naval Shipyard in Kittery, Maine. Offerors are invited to attend an in-person site visit on June 6, 2023 at 1:00 PM where they can inspect the project site. Those needing base access must complete security paperwork and schedule an appointment with the Pass and ID office in advance of the visit. The deadline for submitting written pre-proposal inquiries is modified from 14 days to 12 days prior to the revised proposal due date. The Navy Facilities Engineering Command Mid-Atlantic is the contracting agency.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

N40085-23-R-2622 DESIGN-BID-BUILD, BRIDGE 2 STRUCTURAL REPAIRS, PORTSMOUTH NAVAL SHIPYARD, KITTERY, MAINE

This Amendment is issued to provide site visit details and to update Instructions to Offerors section 4.3 PRE-PROPOSAL INQUIRIES (PPIs).

See Continuation Page(s).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-May-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008523R2622

X 9B. DATED (SEE ITEM 11)

22-May-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-May-2023

CODE

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008523R2622

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0001

This Amendment is issued to incorporate the following:

1. Update Instructions to Offerors section 4.1 PRE-PROPOSAL CONFERENCE AND SITE VISIT (changes denoted in red below) and FAR 52.236-27 to include site visit details.

2. Update Instructions to Offerors section 4.3 PRE-PROPOSAL INQUIRIES (PPIs) (changes denoted in red below).

INSTRUCTIONS TO OFFERORS

4.1 PRE-PROPOSAL CONFERENCE AND SITE VISIT

From:

SITE VISIT DETAILS WILL BE DETERMINED VIA AMENDMENT.

To:

Date: Tuesday, June 6, 2023 @ 1300 EDT

Site Visit POC: Ian Bodwell, (207) 752-4112, ian.l.bodwell.civ@us.navy.mil

Meeting Location: For Offerors who already have base access, please meet at the southern end of Bridge 2 at Portsmouth Naval Shipyard. For those Offerors needing to be escorted, please arrive at the pass office (B384 at the end of Walker Street) 30 minutes prior to the time of the site visit.

Additional Site Visit Instructions for N4008523R2622 – Bridge 2 Structural Steel Recoating and Repairs:

This site visit is not located inside the CIA, Required Steps for Visitors:

1) For those who require access/badging, return completed “DBIDS Access Request Form” (Attachment K) to james.a.godwin41.civ@us.navy.mil.

a. All completed “DBIDS Access Request Form” must be submitted by 30 May 2023 to enable sufficient processing time.

b. A completed 5500 DBIDS Form (Attachment K) for each company. If there are multiple subcontracting companies, a 5500 form is required for each company. If there are multiple individuals coming from a company, only one 5500 is required, however please include the attendee list on page two with the following information:

i. Full first name, last name, middle initial

ii. Company name

iii. State of Residence

iv. US Citizenship (Y or N?)

2) Each person must schedule an appointment with the Pass & ID office by using the “QLESS” app (https://www.qless.com/L).

3) Each person must complete SF 5512 form (Attachment L) and hand carry this form, along with 2 forms of approved photo ID, with them to their scheduled appointment at the pass office.

a. Anyone expecting to be badged should have either a VALID US passport (not expired) and a regular license, OR, a license, accompanied with a social security card or birth certificate.

b. Do NOT email the 5512 form as it has personal identification information.

NOTE: IF THE SITE VISIT DATE NEEDS TO BE CHANGED IT WILL BE ANNOUNCED VIA RFP

AMENDMENT.

Additional information:

1) PPE is recommended for the site visit (i.e. hard hat, hearing protection, etc.)

2) Reminder: Contractors with base access can meet the site visit team at the southern end of Bridge 2 at 1300 EDT.

However please submit the names of those attending the site visit to assist with coordination.

In Summary, Prime contractors must identify the contractors without base access who will attend the site visit and immediately book an appointment at Pass & ID as well as submit the respective DBIDS request form by the suspense date. Contractors must ensure attendees have completed SECNAV 5512s brought with them to their Pass & ID appointment date.

Lastly please submit to james.a.godwin41.civ@us.navy.mil a list of all attendees NO LATER THAN 30 May, 2023.

4.3 PRE-PROPOSAL INQUIRIES (PPIs):

From:

All inquiries must be submitted in writing and received by the Contract Specialist no later than fourteen (14) days prior to the proposal due date in order to permit adequate time to reply to the inquiry. There is no guarantee that PPI’s submitted after the cut-off date will be answered before the solicitation closes. Submit all questions to James Godwin at james.a.godwin41.civ@us.navy.mil. Use of the PPI Log template is required. The PPI Log Template (Attachment A) can be found on PIEE or the Contract Opportunities website (Sam.gov) under the Attachments section.

To:

All inquiries must be submitted in writing and received by the Contract Specialist no later than twelve (12) days prior to the proposal due date in order to permit adequate time to reply to the inquiry. There is no guarantee that PPI’s submitted after the cut-off date will be answered before the solicitation closes. Submit all questions to James Godwin at james.a.godwin41.civ@us.navy.mil. Use of the PPI Log template is required. The PPI Log Template (Attachment A) can be found on PIEE or the Contract Opportunities website (Sam.gov) under the Attachments section.

SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS

The following have been modified:

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Date: Tuesday, June 6, 2023 @ 1300 EDT

Site Visit POC: Ian Bodwell, (207) 752-4112, ian.l.bodwell.civ@us.navy.mil

Meeting Location: For Offerors who already have base access, please meet at the southern end of Bridge 2 at Portsmouth Naval Shipyard. For those Offerors needing to be escorted, please arrive at the pass office (B384 at the end of Walker Street) 30 minutes prior to the time of the site visit.

(End of provision)

(End of Summary of Changes)