This supplemental scope of work document provides additional details for the battery area upgrades project at Building 3235 of the Public Works Center - Crane Detachment. The contractor shall include a laptop computer with all required software and cables for connecting to the PLC controller, as well as be prepared to potentially move work surfaces and cabinets within cubicles to complete the work. Special requirements include obtaining proper permits for transporting natural gas equipment onto site and using the designated outdoor laydown area. The project must be completed within 591 calendar days, with a maximum duration of 21 weeks to upgrade areas 2 and 3 simultaneously. The contractor must protect personnel and the environment from contamination, properly dispose of contaminated equipment and ductwork, avoid dragging out work unnecessarily, not abandon any items on site, verify explosives have been cleared from the facility, and notify the government project manager after field work is finished to schedule radon testing.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PUBLIC WORKS CENTER - CRANE DETACHMENT
Supplemental Scope Items for Bldg 3235 Battery Area Upgrades Revision “0” dated 01-13-23
The contractor shall include the following scope items into the project scope.
1. A laptop computer is required for connection to the PLC controller with all software. Include pelican case, software, and cables.
2. Cubicles are not planned to be moved completely, however the work surfaces and cabinets may need to be moved. If the work surfaces inside of the cubicles need to be moved to accomplish work, this shall be the responsibility of the contractor.
3. Note the requirements in the specs that the natural gas fired MAU’s and the scrubber is not allowed to be transported onto government property until authorized by the NSA Crane Air permit manager after they have secured the proper air permit(s).
4. The outdoor material laydown area for the contractor is the parking lot near the existing scrubbers. Protect materials.
5. The contractor shall complete the project within 591 calendar days after award. There are phasing requirements shown on sheet G-003 of the drawings. The contractor shall minimize the the amount of time that zones 2 and 3 are under construction with the maximum allowable field duration for the zone 2 and 3 areas to be under construction to be 21 calendar weeks.
6. There are special requirements to protect personnel and the environment from the contamination in areas of the bldg – ref specs.
7. There are special requirement for the demolition of contaminated equipment and ductwork – ref specs.
8. The contractor shall not drag out (or use as “filler” work) any portion of the installation longer than necessary which would impact the occupants (e.g. do not drag out the controls installation in the offices as this has an impact to the occupants, or do not drag out a particular lab renovation.
9. Contractor shall not abandon items in place
10. The contractor shall request and receive verification from the government that all explosives have been removed from the facility prior to the construction.
11. For clarification this project is design-bid-build
12. The contractor is required to send an email to the government project manager upon completion of the field work so the government can schedule Radon testing in the facility.
13. Spec correction: 01 14 00 part 1.5.4 remove the following underlined statement “and 7 a.m. to
11:00 p.m. on Saturday”. Saturday work may only be allowed with special permission from contracting officer.