Attachment H - Price Proposal Form.docx

DOCX document 39 KB Posted

Attached to
BQ-455 Renovations and Repairs, Naval Submarine Base New London
Solicitation number
N4008523R2530
Issued by

About this file

This document contains a price proposal form for a construction project at Naval Submarine Base New London. The form includes line items for the base price of permanent party repairs to Building BQ455, with separate entries for site work inside and outside of the 5-foot line. Additional line items cover replacing windows and wallboard throughout the building. Optional line items include expanding the kitchen, upgrading bathroom wall tile, adding rigid sheet wall protection below corridors, substituting wood cabinets, and installing new electrical systems from the transformer to the switchboard. The Navy seeks these renovations and repairs through solicitation N4008523R2530 to improve facilities at Naval Submarine Base New London. Pricing is requested for the base scope of work as well as optional upgrades.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

[Type here]

Line Item
Description
Quantity
Unit
Unit Price
Sub-Total
Total Price
0001
BASE PRICE: Total Price for the entire work for Permanent Party Repairs BQ455 - Project

Number: 1632260 in accordance with the drawings and specifications, complete, but excluding work provided in another Priced line Item.

1
EA
0001A
Subtotal of Base Price for the entire work for BQ455 complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item
1
EA
0001B
Subtotal of Base Price for the entire project sitework outside the facility 5-foot line, complete in accordance with the drawings and specifications, but excluding work described in another line Item.
1
EA
0001C
Unit Price for replacing exterior windows at all locations, with exception to storefront at the building main entry.
360
EA
____
________
0001D
Unit Price for replacing all gypsum wallboard throughout entire building. Steel studs will remain and be sprayed for mold remediation.
23565
SF
____
________
0001E
Subtotal of Base Price for Design of the replacement of all windows, complete, but excluding work provided in another line item.
1
EA

The quantities in CLINS 0001F thru CLIN 0001I are for estimated work above and beyond those indicated in the contract drawings for CLINs 0001A thru 0001E. These items will only be performed at the direction of the Contracting Officer. The contractor will only receive payment for quantities actually performed and a deductive modification will be executed for quantities not performed.

0001F
Unit Price for providing Rock Excavation and Disposal complete in accordance with the drawings and specifications, but excluding work provided in another line item.
2500
CF
____
________
0001G
Unit Price for removal and disposal of asbestos containing pipe insulation complete in accordance with the drawings and specifications, but excluding work provided in another line item..
4000
SF
____
________
0001H
Unit Price for removal and disposal of asbestos containing floor tile complete in accordance with the drawings and specifications, but excluding work provided in another line item.
4000
SF
____
________
0001I
Unit Price for fire proofing existing penetrations complete in accordance with the drawings and specifications, but excluding work provided in another line item.
300
EA
____
________
0002
Option Item No. 1: Price for providing all work in connection with providing a larger kitchen area; reference Contract Dwg. A-420 including all related construction activities, complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.
1
EA
0003
Option Item No. 2: Price for providing Full Height Wall Tile at bathroom walls in lieu of Partial Height Wall Tile, complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.
1
EA
0004
Option Item No. 3: Price for providing Rigid Sheet Wall protection below corridor wall guards in lieu of Knockdown Finish, complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.
1
EA
0005
Option Item No. 4: Price for providing Wood Cabinets throughout Project in lieu of Plastic Laminate Cabinets, complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.
1
EA
0006
Option Item No. 5: Price for providing New Electrical conduits and Feeder Cables from Transformer to New

Switchboard complete, complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.

1
EA