Amendment 0004.pdf
PDF 237 KB Posted
- Attached to
- IDIQ SB MACC, General Construction, MCI East AOR
- Solicitation number
- N4008521R1215
About this file
This solicitation requests proposals for an indefinite delivery/indefinite quantity multiple award construction contract to provide general construction services for facilities within the Marine Corps Installations East area of responsibility, including Camp Lejeune and Cherry Point. Services include design-build and design-bid-build construction projects ranging from $150,000 to $10 million. Proposals are due January 26, 2021 and must include both electronic and hard copy submissions. Evaluation will be based on technical qualifications, past performance, and price. Awards will be made to multiple small businesses. The scope of work includes renovation of building AS124 at Camp Lejeune involving roofing, siding, overhead door replacement, and interior renovations.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendent is to respond to Pre-Proposal Inquiries and extend the proposal due date. See SF30 Block 14 Continuation Page
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-Jan-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008521R1215
X 9B. DATED (SEE ITEM 11)
02-Dec-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-Jan-2021
CODE
NAVFACSYSCOM MID-ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008521R1215
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0004
The purpose of this amendment is to respond to Pre-Proposal Inquiries and extend the solicitation due date to 26 January 2021 at 2:00 PM EST.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 19-Jan-2021 02:00 PM to 26-Jan-
2021 02:00 PM.
(End of Summary of Changes)
SOLICITATION NO. N40085‐21‐R‐1215
PROJECT TITLE/LOCATION: MCI East AOR MACC
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
4 12/3/2020 SPECIFICA
TIONS
Is the contractor required to hire a Commissioning Agent? No 4
9 12/4/2020 A‐4 Please provide the requirements for the "Building Enumeration Sign" and any other signage required. See Specification Section 10‐44‐30 Room Signs for the requirements. Section 10‐44‐ 10 Building Enumeration is to be deleted from the project, the Base will provide building number signage.
10 12/4/2020 E‐Drawings Is Lightning Protection & grounding required on this building? Lightning protection system is not required.
11 12/4/2020 RFP Is construction materials testing required on this project? No material testing is required. 4 13 12/4/2020 A‐1 & P‐2 DEMO Is this building constructed on a concrete slab?
Building is on a concrete slab.
15 12/4/2020 E‐2 ‐ General Demolitio n Note 8;
E‐3
Please provide the name and contact information for the Electric Utility Company that serves this location. Will the Utility Company provide the new pole and transformers, or is that the contractor's responsibility? Will the Utility Company provide the disconnect/re‐connect for the electrical service?
It is the contractors responsibility to install all the scope for disconnect/connection, pole and transformer install.
16 12/4/2020 RFP The RFP says that Projects for the MACC have an estimated construction cost between $150,000.00 and $10,000,000.00.
Please provide further information of the anticipated cost range of task orders. What is the average project range?
No additional information about anticipated cost range of task orders is available at this time.
22 12/4/2020 M‐3 Detail 1 on drawing M‐3 shows flue and intake pipe for the gas unit heater. However the drawing or the specifications proivided do not indicate the material specifications for the piping. Please provide material specifications, etc for the required piping for the flue and intake.
The vent pipe should be galvanized steel or other suitable corrosion resistant material per manufacturers requirements.
Follow the National Fuel Gas Code for minimum thickness of vent material. The minimum thickness for connectors varies depending on the pipe diameter. Do not vent unit with PVC or other forms of plastic venting material.
23 12/4/2020 A‐2 New work note #2 on drawing A‐2 states to provide Chain Link Fencing to close in yard. No specifications or drawing details have been provided for the type of fencing required. Futher, the drawings do not include sufficient information to determine the quantity of fencing required or if any gates or other items/accessories would be required. Please provide drawing details, dimensions, and speicifications for the Chain Link Fencing so fair and balanced pricing can be provided and the same scope can be priced by all.
Match existing fence 7' height. Replace 30' of fence from building corner to existing gate at Southeast and Southwest corners of AS124.
REFERENCE
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Posted on Amend No.
July 2011
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
24 12/4/2020 A‐2 New work note #4 on drawing A‐2 states to provide Aluminum Hanger Rod Canopy. Canopy detail 3/A2 canopy notes provides some specifics but is incomplete. No info/material specification is provided on hanger rod, soffit, whether a downspout is required, whether color is to be priced from standard or custom colors, etc. Please provide specifications and or missing details so fair, balanced and competitive pricing can be provided by all.
The requirements for the Hanger Rod Canopy are on Detail 3/A2/A2. Color shall be selected by Base Architect from a standard color chart.
25 12/4/2020 A‐1 Work note #5 on A‐1 states to remove interior and exterior dust collection piping, store, and reinstall. To ensure adequate pricing is included, additional information is necessary. i.e. piping material type and size, mounting height, mounting type and surface. Please provide the requested info so fair and balanced pricing can be provided and the same scope can be priced by all.
The dust collection system piping shown on both the Existing and Renovated Floor Plans shall be removed, stored and reinstalled. See attached pictures for any needed reference.
26 12/4/2020 A‐3, A‐7, A‐10 The door schedule on A‐3 does not include any information, at a minimum door size, for OHRD's #1 & #2. Drawing A‐7 detail 1/A2/A7 shows rough opening framing at 12' wide x 13' height. Drawing A‐10 detail 1/A2/A10 indicates height of finished opening at 14' and support framing above that. This 14' and framing above directly conflicts with the "z" girt framing at 13' height on drawing A‐7 detail 1/A2/A7. Please provide a door schedule and or dimensions of the OHRD's required and revise and provide exact framing details and material specifications of framing components for both support and rough openings to be used in these locations. Without the requested information accurate pricing cannot be determined.
Details 1/A2/A7 ‐ move the new wall girt up to 14'‐0". Both OHRDs (Over Head Rolling Door) shall be 12'‐0" wide by 14'‐ 0" tall.
30 12/7/2020 A7 and A10 Detail 1 ‐ A2/A7 shows an opening of 12x13 for the new overhead door. A10 Detail 1 ‐ A2/A10 states the height of the new overhead door is 14". Which is correct?
See PPI #26 4
33 12/9/2020 A2
NUMBERE
D NOTE
#2
PLEASE PROVIDE SPECIFICATION FOR THE CHAIN LINK FENCE. HOW TALL SHOULD FENCING BE? ARE ANY GATES TO BE
PROVIDED?
See PPI #23 4
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
34 12/9/2020 A‐1 General note 2 Upon visual inspection, the southern wall of room E103 is furred out and finished with gypsum board. Neither the sections on sheet A‐7 nor the floor plan on A‐1 have this wall furred out. General Note 2 calls for all gypsum board and plywood walls to be removed.
Are all the walls in rooms E101, E102, E103, E104, E105, E106, E107, E108, and E109 furred out where there exists exterior/previously exterior CMU walls?
There is not furring on the interior face of the exterior block (except for a very small spot for an Electrical Panel in area E103).
Interior walls are wood stud with gypsum board and/or plywood finish (except E110 and E111 are block with no furring). The existing gypsum board and plywood wall finish is to be removed per the plans and replaced with new ‐ see Finish Schedules.
36 12/9/2020 5 1.3.1 Please provide the installations that are part of the East Area of Responsibility other than Camp Lejeune and Cherry Point. The work will be primarily in MCB Camp Lejeune, MCAS Cherry Point, and MCAS New River, but work in other areas may still occur under this MACC
37 12/9/2020 Specifications page 717‐745 of 1005
The Submittal Register provided within the Solicitation Specifications does not look to be specific for the Seed Project Scope of Work.
Please confirm that the aforementioned document is not project specific and that it will be edited appropriately.
The submittal register is created by the specification software package according the specified materials.
38 12/9/2020 02 84 16 Specification Section 02 84 16 ‐ Handling of Lighting Ballasts and Lamps Containing PCBs and Mercury is considered to be broad, over‐ reaching and contradictory for the Scope of Work being engaged in and the facility in which the Work is being performed. Please confirm that Spec Section 02 84 16 is able to be and shall be disregarded in whole.
Please see the attached revised spec section 02 84 16 concerning hazardous materials.
39 12/9/2020 detail B on drawing C‐
This vegetation plan states that after grading activities and the contruction of swales all areas are to be seeded. However, there are no grading activities to be performed or swales to be constructed. The existing grassy areas around the existing compressor shed to be reconstructed and what appears to be like a grassy areas 5' off the east and west ends of the building will most likely only need to be raked and seeded. We do not find any indications on the drawings to change grades, regrade or construction swales. Please advise if the above mentioned areas are the only areas to be seeded per the vegetation plan.
Yes, Those areas and any disturbed by Contractor operations.
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
40 12/9/2020 detail B on drawing C‐ the permanent vegetation section of this vegetation plan states that all areas not covered with buildings, pavements, or other impermeable sufraces shall be sodded as the final/permanent vegetation. With the proceeding requirement of the establishment of a full stand of grass 4" tall with 95% coverage why would you then cover that with sod? If sod is to be required please provide an estimated quantity of sod required to be used as a basis of bid so everyone will be bidding the same scope and fair and reasonsable pricing can be provided.
Seed is temporary method of stabilization. Sod is the required permanent vegetation.
41 12/9/2020 drawings C‐1, C‐2, C‐3
In review of the civil drawings, a "project limits of contruction" boundry is not shown or even listed in the civil legend. Please confirm that the project limits boundry is determined by the limits of the asphalt replacement as identified by keynote 1 on C‐2, the area between the building and the existing asphalt drive shown on the "plan" north and west sides of building AS124, and 5' out from the face of building AS124 on the "plan" east and south of building AS124. Otherwise provide a civil drawing that shows the actual boundry line for the project limits of construction.
The limits of disturbance in this instance is the limits of work.
45 12/10/2020 A‐1 General note 2
Upon visual inspection, the southern wall of room E103 is furred out and finished with gypsum board. Neither the sections on sheet A‐7 nor the floor plan on A‐1 have this wall furred out. General Note 2 calls for all gypsum board and plywood walls to be removed.
Are all the walls in rooms E101, E102, E103, E104, E105, E106, E107, E108, and E109 furred out where there exists exterior/previously exterior CMU walls?
See PPI #34 4
46 12/10/2020 A‐4 Note 7 and 2/A‐ 4/A‐7 detail
Please confirm that an exposed‐fastener wall panel is acceptable. Yes 4
47 12/10/2020 A‐7 {detail 1/A‐2/A‐
7}
Are the horizontal "Z" Girts to be replaced on one end wall only, or are they to be replaced on both end walls? Both ends of the building 4
48 12/10/2020 RFP Is a Total Building Commissioning agent required to be hired by the contractor No 4 49 12/10/2020 RFP Please provide a list of Special Inspections and Materials Testing that will be required. See PPI #11 4 51 12/11/2020 316 07 52 00 2.4 The last subparagraph in paragraph 2.4 states that roof coatings need to be the product of the roof membrane manufacturer while in the subparagraphs above it states the coatings are to be made by Arkema. Arkema does not manufacture modified bitumen roofing systems. What roofing manufacturers are acceptable given the requirement for the Arkema coatings?
Delete "Aquatec" from the specification 4
52 12/11/2020 none No site laydown, parking, and occupancy plan was provided. Additionally the siding and roofing replacement will create a need for fencing for safety to separate the work area from non contractor personnel. Can the site laydown and termporary occupancy plan be provided?
Coordinate with Construction Manager 4
53 12/11/2020 427 09 29 00 3.4 This paragraph calls for level 5 gypsum wallboard finish. Given the use of the spaces in this building should the level of finish be adjusted to Level 3 or 4?
In this building level 4 gypsum board finish is aceptable
54 12/11/2020 M2 ec Sect 23.73.33 ParaWhat material is to used for the flue and intake pipe for the gas unit heaters? See PPI #22 4
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
55 12/11/2020 Am. 002, Pg 13 Amendment 2 indiciates "Hard copy proposals shall be received no later than two (2) business days after the electronic proposal due date." With express mail carriers issuing warnings about delays in shipping that could outlast the holiday season, please consider allowing for 5‐7 days for Hard Copy proposals to arrive as long as they are postmarked within 1 day of the electronic proposal due date.
The requirement will remain that the hard copy proposals are received 2 business days after the electronic proposal due date, however, the electronic proposal will be used to determine timeliness of the proposal
57 12/11/2020 Civil Please clarify that the existing steam pit is to be completely removed, backfilled with select material and paved over with 2” of asphalt.
See note on Renovated Plan on Sheet A‐2 4
63 12/14/2020 H‐1 AS124 Drawing H‐1 ‐ Hazardous Materials Plan ‐ These demo plans reflect Lead Based Paint & Asbestos containing material. Should we expect any other hazardous material for instance piep insulaiton or piping? Or are all the materials listed on H‐1 the only Hazardous material we should price?
At Plan 2/H1/H1 change circled note to "4". Contractors are also responsible for reviewing ACM & LBP Report.
67 12/15/2020 Page 9 of
00 21 16em 4, factor **The referenced location outlines the number of completed projects to be submitted in support of a viable Solicitation response, including the Size and Scope/Complexity requirements to be met. Our company meets these requirements. This section also includes requirements that are considered restrictive to our company and would not allow us, by the strict interpretation of the RFP, to submit a response or be considered for a seat on this MACC.
**Specifically, Factor 1 states, “Offerors shall have acted as the prime contractor on all submitted projects. Offeror’s experience performing as subcontractor will not be considered, nor will experience of companies proposed to work as subcontractors on the awarded contract,” and “…the Offeror’s experience as a subcontractor will not be considered.”
**As an SBA recognized Mentor that has ushered multiple entities through the SBA 8(a) program, our firm’s responsibilities for efforts performed under this umbrella should be given latitude. While, Joint Ventures without shared experience are able to provide individual company experience for consideration, it is reasonable that a Mentor’s experience within a JV should equally be allowed to be submitted. Unfortunately, the legal parameters of Mentor/Protégé Program, and subsequent Joint Venture agreements, requires that the Mentor be issued Subcontract status (under the umbrella of the Joint Venture). In short, while our capabilities, past experience and bonding capacity have allowed several small businesses to become independent thriving General Contractors, to the benefit of the Government, the experiences gained by these JV entities are not being allowed to be capitalized on; to the detriment of the Mentor firm.
**Please confirm that, as described above, companies experiencing these extenuating circumstances may provide Past Performance gained as a Mentor under an SBA recognized Joint Venture umbrella.
Bid per the RFP. 4
81 12/16/2020 A‐1/A‐2 Please clarify if new chain link fence is required. There is no spec section for this. Sheet A‐1 Note 2 states ” Remove Chain Link Fence back from Building as required to Complete Work.” Sheet A‐2 Note 2 states “Provide new chain link fence to close in yard at the appropriate time.”
See PPI #23 4
82 12/17/2020 A‐2; M‐2 A‐2 Numbered Note 5‐6; M‐ 2 Demo
Keyed Note
Will the government be disconnecting and reconnecting the dust collection system from the governement owned equipment?
See note 6 on Sheet A‐1. Government shall remove existing equipment and reinstall. The Government will disconnect and reconnect the equipment to the dust collection system
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
83 12/17/2020 E‐8 Note 1
Telecomunic ations Riser;
Note 5 Data/Recept acle Mounting Detail
Confirm that the conduits and boxes will be installed by the electrical contractor with pull strings installed. The conduits and boxes and pull strings must be provided and installed as part of this project and be included in the bid.
86 12/17/2020 SPEC 27 10
00 2.4.2.4 Table 1
Please, confirm that the cabling in part of the UNSECURED network should be green in color. There is no reference as to which network it is for, but 27 10 00 2.4.2.1 Table 1 (Page 15) references Unclassified Network cable colo is green.
Yes, green sheathed horizontal cabling for unsecured network cabling
91 12/17/2020 7 of 15 Amen.
4.a.1.1 Amendment 002, Paragraph 4.a.1.1 indicates that the offeror shall provide the latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or signed by an authorized officer of the organization. If an offeror's 2020 fiscal year ends on December 31, 2020, can the Offeror submit certified complete fiscal year financial statements for FY2017, FY2018 and FY2019 with their price proposal since the electronic proposal submission date for the Solicitation is 1/4/2021? If financial information for FY2020 will be required, will a corporate Balance Sheet signed by a Corporate Officer of the Offeror be acceptable?
FY2018, FY2019, and FY2020 data is required.
95 12/17/2020 77 of 1005 01 45
1.5.2.1 Spec Section 01 45 10, Paragraph 1.5.2.1 indicates for the Contractor to provide a Master Electrician licensed in North Carolina to serve as an Electrical Inspector Crew Supervisor with 10 years minimum experience. This type of Electrical License does not exist in the State of North Carolina. Can this requirement be removed from the project by Amendment provided that the electrical work is performed by an Electrical Contractor with an Unlimited North Carolina Electrical License?
Yes, electrical work can be performed by an Electrical Contractor with an Unlimited North Carolina Electrical License
97 12/17/2020 99 of 1005 01 57
3.5.3.2 Spec Section 01 57 19, Paragraph 3.5.3.2 indicates for the Contractor to provide seeding as specified in Spec Section 02 82 30.
However, Drawing C‐3 indicates all disturbed areas that are not covered by impermeable surfaces shall be sodded. Which requirement is correct?
See PPI #40 4
98 12/17/2020 283 ‐ 301 of 1005
07 42
All We have been infomed by our Metal Wall Panel subcontractor that the only wall panel supplier that can meet the specifcation requirements for the project and will be considered as acceptable at MCAS New River is the The Garland Company, Inc. Is the The Garland Company, Inc's Wall Panel System the basis of design the for the project? If not, can the acceptable wall panel manufacterers for the project be provided by Amendment?
The metal wall panels shall be steel concealed fastener with a 20 year warranty.
99 12/17/2020 302 ‐ 329 of 1005
07 52
All We have been infomed by our roofing subcontractor that the only MODIFIED BITUMINOUS MEMBRANE ROOFING supplier that can meet the specifcation requirements for the project and will be considered as acceptable at MCAS New River is the The Garland Company, Inc. Is the The Garland Company, Inc's MODIFIED BITUMINOUS MEMBRANE ROOFING system the basis of design the for the project? If not, can the acceptable MODIFIED BITUMINOUS MEMBRANE ROOFING manufacterers for the project be provided by Amendment?
The Base has developed and vetted this roof specification. The Base provided this roof specification.
100 12/17/2020 341 ‐ 360 of 1005
07 61 15.00
All We have been informed by our roofing subcontractor that the only ALUMINUM STANDING SEAM ROOFING supplier that can meet the specification requirements for the project and will be considered as acceptable at MCAS New River is the The Garland Company, Inc. Is the The Garland Company, Inc's ALUMINUM STANDING SEAM ROOFING system the basis of design the for the project? If not, can the acceptable ALUMINUM STANDING SEAM ROOFING manufacturers for the project be provided by Amendment?
The Base has developed and vetted this roof specification. The Base provided this roof specification.
105 A‐10 1 The detail shows the existing block wall to have turn down footing placed below with rebar placed vertically every 24” the entire height of the wall. The wall must be removed and rebuilt.
This is an addition to the building for the air compressor
108 12/17/2020 E‐2 ‐ Demolitio n Note 8
Is the Electric Power Utility on‐base "privitized"? The Base Electrical Utility is Government owned.
109 12/17/2020 Electrical Drawings
Does this building have an existing Lightning Protection/Grounding System? Is a new Lightning Protection/Grounding System required?
Lightning Protection system is not required. The contractor must install a grounding system per the details on Plan E‐4.
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
110 12/17/2020 Site Visit Will the exterior equipment and other items, including the dust collection system supporting steel, and steel bollards, require re‐painting?
paint the pipe bollards, no work to dust collector.
112 12/17/2020 Site Visit Please provide a requirement for filling holes in existing CMU masonry before painting, and if possible, provide a $ allowance for masonry patching.
Fill openings to be closed with CMU to match the existing wall. Misc. utility holes to be abandoned shall be filled with mortar.
116 12/21/2020 5 PPI
#115
Since January 18, 2021, is a federal holiday. How far in advance can the link for electric submission be requested? How long will the link be available for useage; 24 hours, 48 hours, 72 hours, 1 week?
DoD Safe links expire after 14 days. If a link has not been requested, it must be requested as soon as possible.
117 12/21/2020 Section 07 61 15.00 20 – Alumin um Standin g Seam Roofing
The specifications call for a 0.040” thick aluminum standing seam roof panel, 2 3/8” x 16” T‐Lock seams, Kynar painted. This is typically used on architectural type Roofing from a manufacture like Peterson or Fabral, and is very expensive. We would like the opportunity to submit specs. for a Varco Pruden – SSR II, 22 gauge – galvanized Roof panel, with a Kynar painted and warranted finish, that is standing seam with seams at 16” oc, as it meets your warranty requirements. Using a well established metal building manufacturer like Varco Pruden for the Standing Seam Roofing is the most cost effective way to retrofit and recover the existing Warehouse. Most times, aluminum standing seam roofing is not made to span 5’ OC Roof purlins and is installed on top of plywood decking and/or rigid decking.
The Base has developed and vetted this roof specification. The Base provided this roof specification.
118 12/21/2020 Section 07 42 13 – Metal Wall Panels
The specifications call for a 22 gauge, Kynar painted wall panel to be used on the Warehouse. We would like submit a Varco Pruden Panel Rib Wall Panel, in 24 gauge Kynar painted finish, as this is the standard for metal buildings, and would meet your performance requirements. We can get it in 22 gauge, but it is more expensive.
See answer #98. 22 gauge required 4
119 12/21/2020 Section 07 22 00 – Metal Roof and Wall
This Spec. Section is very unclear as to what Blanket Insulation and its Vapor Barrier to use. The Plans on Drwg. A‐9 indicate “Metal 6” Building Insulation R = 19” for the Roof and Walls Of the Warehouse. Typically, a vapor barrier like white vinyl is used facing the interior. Please clarify the insulation specs. required.
See the attached Metal Building Specification Amendment
120 12/21/2020 Drawing H‐
Regarding Drawing H‐1: Regarding Drawing H‐1: The proximity of the ceiling beam to the ACM‐containing single‐ply roof is unclear.
Please clarify the site condition so Contractor may determine if the ceiling beam should be abated.
See Detail 1/A1/A7 ‐ Ceiling Beam is seperated from the single ply roof
121 12/21/2020 page 412, Attachmen t F, AS124, Specs
SET #05
janitor, electrical, communicat ions
Please clarify if Data/Comm Room R107 is considered a secure space requiring security door hardware (not currently shown on hardware schedule)?
Regular lockset ‐ not secured area 4
123 12/21/2020 Solicitation No.
N4008521 R1215
5.Please clarify if completed Representa ons and Cer fica ons are to be submi ed with our proposal and where they should be placed in our proposal response.
Reps and Certs are to be submitted with your price proposal.
124 12/21/2020 page 13 of Solicitation
No.
N4008521 R1215
Factor 4 ‐ Past Performanc e, (i)
Will the Government accept previously completed Past Performance Questionnaires if they are submitted as part of the proposal (not incorporated by reference) and in the format provided in the solicitation?
Yes 4
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
125 12/21/2020 5
1.3.2
Task orders under the MACC will be design‐bid‐build. The original pre‐soicitation states design‐build / design‐bid‐build. Please confirm that theere are no design services required. Thanks
Confirmed. 4
126 12/21/2020 page 13 of Amendme nt 0002 of Solicitation
No.
N4008521 R1215
5.2.3
Please clarify if the Government is accepting electronic proposal submissions in lieu of or in addition to hard copy proposals. Will the Government accept an electronic‐only proposal submission with no hard copy?
Both an electronic copy and hard copy are required.
129 12/22/2020 A‐12 Per drawing A‐2, note 12, what is the existing CMU reinforcement for this wall that we are to grout solid? How tall is the existing wall and will additional rebar be required to be installed or just grout fill the wall? If additional rebar is required, please provide size and spacing requirements.
No original plans available for this building. It is unclear if the existing CMU walls are reinforced or filled with grout.
Contractor shall assume their is no reinforcing steel or grout fill in the existing CMU walls
130 12/22/2020 A‐3 There is no OHD shown per the door schedule on drawing A‐3. What size should these doors be? And are the manual or electrically operated?
See PPI #26 Manual Doors 4
131 12/22/2020 H‐1 Will the contractor use the existing hazerdous material testing noted on drawing H‐1 for abatement activities or will the contractor have to provide their own survey and report?
Use H‐1 and the ACM & LBP Report provided for this project
132 12/22/2020 4 01 45
1.5.2.1
Will the contractor be required to provide the electrical and telecommunications specialist stated in the this section? If so, will this have to be an employee of the contractor or can this be a third party specialist?
Yes, they can sub‐contract the telecom out. There are a few different local telecom contractors who work on a regular basis aboard CLNC and are already very familiar with our specs and standards
133 12/22/2020 8 of 59 Sect. 4
Regarding the requirement to "submit evidence of availability of working/operating capital, which will be used for the performance of the resultant contract", please clarify what is the expected "evidence" if not inicluded with the financial statements.
Bid per the RFP. 4
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
134 12/22/2020 A3
Finish Schedule
The finish schedule indicates that the exposed structure is to be painted. It appears that the finish schedule is also indicating that the warehouse walls be painted. According to the wall sections, the warehouse walls will be exposed blsnket6 insulation. Please clarify the requirement.
Paint steel structure 4
135 12/23/2020 283 ‐ 301 of 1005 and 341 ‐ 360 of
07 42 13 & 07 15.00
All
The required roof and wall repair work for the project consists of removal & replacement of wall girts, metal wall panels, metal roof panels, trims, and gutters & downspouts on existing Butler‐Style Pre‐Engineered Metal Building Frames. The apparent sole‐sourced Garland/Emedco Roof & Wall System required by the Project Specifications for use on the project is designed for use on existing Non‐ Pre‐Engineered Metal Building Retrofits. Can Spec Sections 07 42 13 & 07 61 15.00 be removed from the Project Specifications and replaced with Spec Section 13 34 19 (Metal Building Systems) by Amendment so that Pre‐Engineered Metal Building Suppliers can be considered acceptable for use on this project?
The Base has developed and vetted this roof specification. The Base provided this roof specification.
136 12/23/2020 10 of 21 A‐3 The Finish and Color Schedules referenced on Drawing A‐3 indicates they are for Building AS4141. Can revised Finish and Color Schedules be provided by Amendment?
The existing & renovated finish schedules and interior color schedule are for AS124.
137 12.23.20 4 of 4 Amend ment 3
We ask the bid date be postponed an additional two days. The bid date was revised to January 19th. This date falls one day after a federal holiday. This contract is very important to us. To ensure timely delivery of our proposal, we usually have it delivered the day before to account for mishaps. With the Government offices closed January 18th timely delivery of our proposals is compromised.
Please extend the proposal due date an additional two days.
See Amendment 0004 4
138 Duplicate question Duplicate question 4
139 12/28/2020 A‐2 What is the length and height of the new chain link fence? See PPI #23 4 140 12/28/2020 N/A N/A
N/A
The answer to PPI #69 states offerors may use smaller than 12 pt font TNR for headers, footers, tables, and graphics. For Headers, is it acceptable to use LARGER than size 12 TNR? We currently are using Size 20 in header sections to clearly mark each section at a glance.
This is acceptable. 4
141 12/28/2020 11 Factor 3 ‐ Safety
(i) Solicitation Submittal Requiremen ts
Under (i) Solicitation Submittal Requirements, we are required to submit information on our DART Rate and TCR Rate for the prime contractor/offeror for the calendar years 2015‐2019. Do we need to provide OSHA 300 and OSHA 300A cards for calendar years 2015‐ 2019 to substantiate the rates provided?
No. 4
142 12/28/2020 Will the job site electrical poll remain in place or will it be relocated? No. Pole is to be removed in entirety per Plan E‐3, Demo Note 4. Pole must be replaced with new per Plan E‐3, Detail 2.
143 12/28/2020 Are all CMU walls to remain and if so, during the demo process, if the walls start to fail. Will the government accept a change order for new CMU walls.
Yes the existing CMU walls are to remain. 4
146 12/29/2020 A‐1
General note 2
Upon visual inspection, the southern wall of room E103 is furred out and finished with gypsum board. Neither the sections on sheet A‐7 nor the floor plan on A‐1 have this wall furred out. General Note 2 calls for all gypsum board and plywood walls to be removed.
Are all the walls in rooms E101, E102, E103, E104, E105, E106, E107, E108, and E109 furred out where there exists exterior/previously exterior CMU walls?
See PPI #34 4
148 1/4/2021 A‐2 Note 12 Note 12 on sheet A‐2 states to grout the existing CMU wall solid. What is the spacing of the existing grouted cells in the existing wall or is the existing wall completely un‐grouted?
No original plans available for this building. It is unclear if the existing CMU walls are reinforced or filled with grout.
Contractor shall assume their is no reinforcing steel or grout fill in the existing CMU walls
149 1/4/2021 A‐4 Numbe red Note 9
Numbered note 9 on A‐4 indicates to provide Over Head Rolling Door. This door is not indicated on the Door Schedule. 1/A‐2|A‐7 shows an opening 12x13 but Section 1/A‐2|A10 shows top of Jamb 14'‐0" AFF. Please provide dimensions for the two new overhead doors.
See PPI #26 4
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
151 1/5/2021 A‐3 The renovated finish schedule on sheet A3 shows rooms labelled as CMU walls for finish but also gypsum wall board and plywood on the same lines. Is the intent that CMU remains exposed where shown or is it that plywood or gypsum wallboard are to be laminated onto the CMU?
See PPI #34 4
152 1/5/2021 A‐3 The renovated finish schedule calls for sealing the concrete floors. There are no specifications on this sealer. What is required for the sealer?
See the attached Concrete Finishing Sealer Specification Amendment
153 1/5/2021 A‐3 07 42 13 & 07 61 15
Section 07 42 13 calls for steel wall panels and section 07 61 15 calls for aluminum roof panels. Should the roof and wall panels be similar materials?
Roof Panels are Aluminum and Wall Panels are Steel. Also See PPI #98
154 1/5/2021 RFP Page
5.2.4
In light of the health concerns regarding COVID‐19 and Government/Company recommendations of having non‐essential personnel work from home, we respectfully request that the Government eliminate the requirement of providing hard copies and CDs. In order to produce hard copies and CDs, we would need our employees to travel to the office to prepare/package the proposal submission, as well as travel to hand deliver the proposal [or travel to shipping center to send the proposal] as currently permitted by the solicitation. We request that the Government allow us to submit the proposal files via email or DoD SAFE in lieu of the current proposal submission options. This will allow the Government to receive the proposal in the safest manner and maintain public health.
Both an electronic copy and hard copy are required.
155 1/5/2021 Amendme nt 0004
General Require ments
Pre‐ Proposal Inquiries (PPIs)
The amendment states to "submit in accordance with Section 00 21 13 ‐ Bidding Schedule Instructions to Bidders of the SF1332, Instruction to Offerors, 5.3 Pre‐Proposal Inquiries (PPIs)." This section is not in the documents provided. Confirm that the correct section is 00 21 16 per the original RFP or provide section 00 21 16.
Confirmed. 4
156 1/5/2021 M‐2 There is a unit heater located in room R109 that is exhausting directly into the new compressor shed R117. Confirm that this is the desired exhaust location or revise location of exhaust to a non‐obstructed exterior wall with adequate clearances.
Route the unit heater GUH08 intake and exhaust through R111 Tool Storage and then turn out through the exterior wall adjacent to R117 Compressor
157 1/5/2021 A‐9 Details 2 & 3
Are only the newly laid CMU wall portions being grouted? The new CMU on the North, East, and West are to be filled with grout. The new and existing CMU on the South wall shall be filled with grout.
158 1/5/2021 A‐9 Details 2 & 3
Is the existing CMU wall adjacent to the warehouse space already fully grouted? See PPI #129 4
160 1/5/2021 A‐1 General Note 2 states "Remove gypsum board and plywood wall and ceiling finishes completed ‐ see finish schedule." The finish schedule indicates gypsum board walls and/or plywood ceilings in rooms E101‐E109 & E112‐E115. This is in conflict with numbered note 7, which states "Remove sections of wood stud and gypsum bard wall indicated by the hatch."
Verify the scope of drywall and plywood demo and replace.
See PPI #34. Numbered Note 7 on Sheet A‐1 is refering to removing the intire wall indicated by hatch on plan. See Renovated Plan on Sheet A‐2 for new conditions.
161 1/5/2021 A‐3 The note on the eisting finish schedule for building AS4141 states to "Remove existing aplied finishes throughout the building…" Confirm that the concrete floors identified in the schedule are not to be demolished and rather are to be cleaned and sealed per the renovated finish schedule for building AS4141.
Concrete floors remain 4
162 1/5/2021 A‐2 General Note 1 states "Provide over head rolling doors (OHRD). See renovated floor plan for new doors." The doors are not identified on the door schedule located on sheet A‐3. Provide revised renovated door schedule identifying the opening sizes, frame type, etc.
Details 1/A2/A7 ‐ move the new wall girt up to 14'‐0". Both OHRDs (Over Head Rolling Door) shall be 12'‐0" wide by 14'‐ 0" tall. OHRD's detailed on 1/A2/A10.
163 1/5/2021 A‐10 Confirm that the existing structure can support the load of the new overhead coiling doors. Provide (2) additional 6", 10 gauge members at each end of building for anchoring the Over Head Rolling Doors.
164 1/5/2021 Has a Limited Source Justification (FAR 6.302‐1(c), 6.303) been prepared for any materials identified under this solicitation? If so, identify which systems to which they apply and provide all related documentation, including any required Approval (FAR 6.304) or Certification (FAR 6.303(b)(12)).
No. 4
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
165 1/5/2021 Confirm that the Government will allow proposers a minimum of seven (7) days to respond to the RFP starting from the date that the
Government responds to 100% of the RFIs received.
The Government will give the proposers as much time as possible, however, this cannot be guaranteed.
| AMD 04 |
| Amd 04 PPIs |