This document is an amendment to a solicitation for dredging services at Naval Station Norfolk in Virginia. The amendment provides additional details on the scope of work, which includes new dredging of Pier 11 South Berth Expansion Area and maintenance dredging of Piers 5 North and 6 North. A portion of the Pier 11 area contains sediment contaminated with petroleum, oil and lubricants that must be dredged and disposed of at an upland facility. Additional requirements include placement of dredged sandy capping material and armor stone layers. The amendment implements COVID-19 safety protocols for federal contractors, provides revisions to general requirements and the design, and answers pre-bid inquiries. Bids are due by November 1, 2021 electronically and November 4, 2021 for hard copies. The solicitation is for a firm-fixed-price construction contract awarded to the lowest priced responsible bidder.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQR5884892 1663506
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
N4008521B0056 PIER 11 SOUTH EXPANSION DREDGING AND 5 NORTH AND 6 NORTH MAINTENANCE DREDGING, NSN, NORFOLK, VA
SEE SF 30 BLOCK 14 CONTINUATION PAGE
1. CONTRACT ID CODE PAGE OF PAGES
J 1 14
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 25-Oct-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4008521B0056
X 9B. DATED (SEE ITEM 11)
30-Sep-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
25-Oct-2021
CODE
NAVFACSYSCOM MID-ATLANTIC
PWD NORFOLK
FACILITIES ENGINEERING & ACQ DIV
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3624
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008521B0056
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0002
The purpose of this amendment is to:
1. Implement the Requirements of Executive Order 14042, Ensuring Adequate COVID Safety Protocols for
Federal Contractors
2. Provide Revisions to General Requirements
3. Provide Design Revision 01
4. Provide Responses to Pre-Bid Inquiries (PBIs)
All PBIs are hereby answered. All other terms and conditions remain unchanged.
1. Implement the Requirements of Executive Order 14042, Ensuring Adequate COVID Safety Protocols for
Federal Contractors
Pursuant to Executive Order 14042, Ensuring Adequate COVID Safety Protocols for Federal Contractors, dated September 9, 2021, the following clause is hereby added to Solicitation Number N4008521B0056 and shall be included in Award hereafter:
252.223-7999 ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS
(DEVIATION 2021-O0009)
Class Deviation 2021-O0009 implements the requirements of Executive Order 14042 to ensure that contractors comply with all guidance for contractor and subcontractor workplace locations published by the Safer Federal Workforce Task Force. This Class Deviation remains in effect until incorporated into the FAR or until otherwise rescinded.
See Attachment 9 – CD 2021-O0009
See Attachment 10 – Guidance for Federal Contractors and Subcontractors
For additional information, including frequently asked questions:
https://www.saferfederalworkforce.gov/contractors/
2. Provide Revisions to General Requirements
Changes are provided in Amendment 0002 herein and are indicated in red font.
3. Provide Design Revision 01
See Attachment 12 - Design Revision 01.
4. Provide Responses to (PBIs) #4-19
PBI
Reference
Question
Page Section Paragraph Government Response Posted on Amend
No
Can the XYZ point file be provided for the most recent survey conducted of the project site?
Yes. Please see Attachment 11 -nsn_cond_20x_Nov2019_mllw provided in Amendment 0002
5 11 01 14 00 1.1
This section states that the dredge plans are to show progressive positioning of hydraulic dredge, crane barge, etc. If clamshell bucket is an allowable form of dredging, can this be accounted for in the language?
Clamshell dredging is permitted. 0002
6 15 Appendix
A
p. 15
Please confirm if the jobsite is adjacent to any protected species habitats that would enact environmental dredging time of year restrictions as notated in the Appendix A permits. Per the Permit documents, it states "Any authorized dredging located adjacent to certain resources (including shellfish beds, submerged aquatic vegetation, and anadromous fish use areas) will require a time of year restriction (TOYR), unless determined unnecessary through additional agency coordination. The TOYR indicates the time of any given year that the authorized dredging cannot be performed in order to protect these resources. The TOYR for these resources are as follows:
• Shellfish beds: March 1 through September
• Submerged Aquatic Vegetation: March 1 through October 31
• Anadromous Fish Use Areas: February 15 through June 30
No Time Of Year Restrictions are anticipated to be required under the project permits.
Contractor shall the bid the project accordingly.
7 2 Attachment
5- Final Plan 1-4
V-002 - Dredging and Design Notes
Will there be an opening within the port security barriers (PSB) during dredging to allow for 24hour transit of tugs and scows and to the disposal site if contractor elects to dredge via clamshell?
Plans V-002
1. NAVAL STATION NORFOLK HAS
IMPLEMENTED .ADDITIONAL SECURITY
t.1EASURES AL.ONG THE WATERFRONT.
ACCESS TO THE WORK AREAS FROM THE
WATER IS RESTRICTED. A PORT SECURITY
BARRIER {PSB) SYSTEM HAS BEEN DEPLOYED
WHICH APPROXIMATES THE RESTRICTED AREA
IN THE WATERS SURROUNDING NAVAL
STATION NORFOLK. THE CONTRACTOR SHAf.1
NOTIFY AND REQUEST PORT OPERATIONS TO
t.10VE AND REPLACE THIS LINE EACH TIME THE
CONTRACTOR REQUIRES ACCESS TO THE
RESTRICTED AREA. THE CONTRACTOR MUST
NOTIFY PORT OPERATIONS AT 444-1121 AT
LEAST FM: (5) BUSINESS DAYS IN ADVANCE OF
ANY MOVEMENT OF THE PSB REGARDLESS OF
THE TIME OF DESIRED OPENING (WEEKENDS,
WORKING/NON-WORKING HOURS ETC .•. ) FOR
LONG TERt.1 PSB OPENING REQUESTS {>1
HOUR) FOR APPROACH DREDGING AND
RELOCATION OF DREDGING EQUIPMENT AND
PIPELINES, NOTIFY PORT OPS A MINIMUM OF
SEVEN DAYS IN ADVANCE. CONTRACTOR
SHOULD EXPECT TO RECEIVE ffROVAL. 24
HOURS PRIOR TO EACH DESIRED OPENING
DATE (VETTING TAKES PLACE THE DAY
BEFORE ENTRY). Af.1 CONTRACTORS ON BOARD THE 'vrSSEL ARE REQUIRED TO HAVE
VALID DBIDS CARDS FOR ENTRY TO NAVAL
STATION NORFOLK.
PSB openings are only allowable during regular business hours unless in event of an emergency.
The contractor must coordinate all PSB openings with Port Operations as indicated on the plans and specs.
8 17 01 57 19 3.4.1
Specification Section 01 57 19, Page 17, Section 3.4.1, Preconstruction Air Permits.
This section requires us to submit for an air permit at least 6 months prior to bringing equipment on the site. This requirement cannot be achieved given the project is only 180 days in duration. Please clarify.
See Attachment 12 - Design Revision 01 provided in Amendment 0002.
Is there a requirement to have a Marine Mammal Watch person stationed on the project?
Marine mammal watch person(s) are not anticipated to be required under the project permits.
Contractor shall the bid the project accordingly.
V-
Plan Sheet V-003, Sections A thru F shows the 36” thick sand layer on the cut slope.
This slope is at a 2:1. The natural angle of repose for the sand will make the sand want to create a 3:1 slope. Is it acceptable to have the finished slope at a 3:1?
Contractor shall bid pursuant to plan design using a 2:1 slope.
V-
Plan Sheet V-003, Sections A thru F show dividing lines between the POL material and the material to be hydraulically dredged and placed into Cranney Island. The POL material will need to be dredged first as the layer sits on top of the Non-POL material.
How will the contractor know when to stop dredging the POL material and switch to the Hydraulic method? Will NAVFAC be testing periodic mechanical buckets of material as they are dredged?
The project plans, (sheet V-101) shows the POL material areas and corresponding required dredging depths. When the contractor achieves the minimum dredging depths, as shown on the plan, the POL material removal shall be considered completed. The GOV will perform a bathymetric survey in order to verify that minimum contract depths have been achieved.
12 3 35 31 19 2.1.1
Specification Section 35 31 19, Page 3, 2.1.1 states that the contractor is to submit the source of the clean medium grain sand and testing reports. We are not furnishing the sand on the project. It is being mined onsite.
Is the contractor required to test the mined sand for compliance with ASTM C33?
See Attachment 12 - Design Revision 01 provided in Amendment 0002. Sand shall be mined from on-site as shown on plans.
13 2 01 11 00 1.3
Specification Section 01 11 00, Page 2, 1.3 states NTP is to be issued within 90 days or less from the contract award date. When do you anticipate contract award?
The Government intends to award in November 2021
14 3 01 30 00 1.6
Specification Section 01 30 00, Page 3, 1.6 states that the contractor is to mobilize within 60 Calendar days from contract award. If the government takes the full 90 days in question 7 above this section is contradictory to question 7 above.
See Attachment 12 - Design Revision 01 provided in Amendment 0002.
Are there any time of year restrictions for the dredging work?
No Time Of Year Restrictions are anticipated to be required under the project permits.
Contractor shall the bid the project accordingly.
16 2 35 20 23 1.9
Specification Section 35 20 23, Page 2, 1.9 Charges states the government will pay charges imposed by USACE for disposal of dredge material into Craney Island. This section is in conflict with the bid item descriptions for CLINs 0001AB, 0002AA, and 0003AA which states the contractor is required to pay the USACE the tipping/disposal fee. Please clarify.
See Attachment 12 - Design Revision 01 provided in Amendment 0002.
17 2 01 11 00 1.4
CLIN 0001AJ is an item for Downtime with a quantity of 24 hours. Specification Section 01 11 00, Page 2, 1.4 Work Scheduling states that the contractor shall allow for a maximum of 200 hours where construction activity is prohibitive. Will the payment for downtime start after the 200 hours of incidental downtime is exhausted?
See Attachment 12 - Design Revision 01 provided in Amendment 0002. Any downtime impacts due to Government Operations is to be paid to the Contractor via CLIN
0001AJ
18 11 01 11 00 1.1.1 Non-POL Contaminated Material from the Berth Expansion Area may be dredged via
Material placed into the CDMMA Rehandling Basin via conventional clamshell bucket, transported via sealed scow/barge and deposited into the CDMMA Rehandling Basin or pumped via hydraulic unloader to an upland cell of the Craney Island Dredge Material Management Area (CDMMA) or dredged via hydraulic cutterhead dredge and pumped directly upland cell of CDMMA.
Please confirm if dredged material disposed in the CIDMMA Rehandling Basin via dump scow must be then pumped into the CIDMMA Upland Site by the same contractor. Please confirm the current capacity of the CIDMMA Rehandling Basin if rehandling the dredged material via hydraulic unloader into the CIDMMA Upland Site is not required.
bottom dumping scow is not required to be subsequently pumped to an upland cell by the contractor. However, the contractor shall bear in mind that material placed into the rehandling basin is subject to a considerably higher disposal toll charged by the Army Corps of Engineers. As stated in the bid schedule, the contractor shall be responsible for paying all CDMMA disposal tolls.
19 Plans Sheet V-201
Plans Sheet V-201 POL Contaminated Dredged Material Management and Side- Slope Capping Narrative Can the POL contaminated material be dredged via clamshell and hydraulicly unloaded at the CIDMMA?
The material would then be dried and mixed ion place at a contained CIDMMA upland cell and then be rehandled to a landfill.
No. Bid the project pursuant to the disposal options specified in the bidding documents.
SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS
The following have been modified:
GENERAL REQUIREMENTS
Description: PIER 11S BERTH EXPANSION NEW DREDGING AND PIER 5N AND 6N MAINTENANCE
DREDGING
Installation; (SA) & Location/UIC: N62688 NAVSTA NORFOLK VA (MAIN BASE)
NORFOLK, VIRGINIA
Description of Proposed Construction
Scope of Work for FY22 Pier 11S Berth Expansion New Dredging and Pier 5N and 6N Maintenance Dredging at Norfolk Naval Station, Norfolk, VA
The work includes New Dredging of Pier 11 South Berth Expansion Area and Maintenance Dredging of the outer berths of Piers 5 North and 6 North. Maintenance Dredging of the outer berths of Piers 5 North and 6 North and Non-POL Contaminated Material from the Berth Expansion Area may be dredged via conventional clamshell bucket, transported via sealed scow/barge and deposited into the CDMMA Rehandling Basin or pumped via hydraulic unloader to an upland cell of the Craney Island Dredge Material Management Area (CDMMA) or dredged via hydraulic cutterhead dredge and pumped directly upland cell of CDMMA. Location of deposition within Craney Island Project Site is subject to change and should be coordinated with the Army Corps of Engineers before dredging begins. A portion of the Pier 11S Berth Expansion area contains sediment contaminated with Petroleum, Oil and Lubricant (POL) material as shown on the plans.
The POL contaminated material shall be dredged via conventional clamshell bucket and disposed at an upland facilty as specified herein and on plans.
Dredging from on-site location and placement of sandy material to be used as side-slope capping (as shown on plans) shall be done via conventional clamshell bucket.
Additional work as shown on the plans and specification shall be performed, including but not limited to, placement of sandy capping material dredged on-site (as shown on plan) and rip-rap armor stone layers along southern and eastern side slopes of Berth Expansion Area to cap disturbed POL contaminated material remaining in place and removal and disposal of debris remaining after the past demolition of steel sheet piling cofferdam break water and timber breakwater structures. Remaining debris may include steel sheet piling stubs and timber piling stubs, concrete rubble and rip-rap stone.
Section 00 10 00 – Solicitation
STATEMENT OF WORK
INVITATION FOR BID
FY22 PIER 11S BERTH EXPANSION NEW DREDGING AND PIER 5N AND 6N MAINTENANCE
DREDGING AT NAVAL STATION NORFOLK, NORFOLK, VA
The following (8) documents have been uploaded to www.sam.gov as separate attachments:
Attachment 1 – Appendix A_Permits Attachment 2 – Appendix B_Summary_DredgeSamplingResults Attachment 3 – Appendix C_On-Base Material Staging_Mixing_Offloading_Area Attachment 4 - Pier11South_Specs Attachment 5 - NSN P11S Berth Expansion And Maint Dredge_Final_Plan Attachment 6 - Price Bid Worksheet (Bid Schedule) Attachment 7 – Pre-Bid Inquiries (PBI) Form Attachment 8 - Subcontracting Plan
Section 00 21 13 – Instructions To Bidders
THE FOLLOWING DOCUMENTS SHALL BE SUBMITTED WITH THE BID:
Standard Form 1442, Solicitation, Offer and Award (Submit SECTION 001000 – Lump sum pricing for CLIN 0001 AA-AJ (Base Price), CLIN 0002 (Option Item 0001) and CLIN 0003 (Option Item 2).
Please be sure to fill out the lump sum pricing for the Base Bid (CLIN 0001AA-AJ), CLIN 0002 (Option Item 0001) and CLIN 0003 (Option Item 2) on the SF1442. The SF1442 and bid schedule shall be submitted.
Acknowledgements of any Amendments issued.
Bid Bond Guarantee (FAR 52.228-1(c)) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.
RESPONSIBILITY DETERMINATION INFORMATION - In order to be eligible for award, the bidder must be determined responsible in accordance with FAR Part 9, specifically 9.104-1, General Standards. The apparent successful low bidder will be required to provide the following information within 3 days of the bid opening:
- Description of Contractor’s facilities and equipment.
- One (1) Signed Bank Reference demonstrating adequate financial resources. If offeror’s firm has a line of credit – provide information on how many figures offeror can borrow against the line of credit (i.e. medium 6 figures – exact line of credit is not required).
- The latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or signed by an authorized officer of the organization. Submit evidence of availability of working/operating capital, which will be used for the performance of the resultant contract. For Joint Venture arrangements, submit the latest three complete fiscal year financial statements for each company in the Joint Venture and discuss the financial responsibilities among the companies. The Government may also utilize Dun & Bradstreet reports to evaluate the financial capacity of the Offeror.
- Other work presently under contract and their period of performance.
This information forms the basis of your firm’s responsibility determination should your firm be the apparent low bidder. Packages will not be returned, but shall be destroyed by the Contracting Officer. No certificate of destruction will be issued.
The offeror’s bid must include all data and information required and must be submitted in accordance with these instructions.
1. SUMMARY
The following paragraphs are supplemental instructions /information for Bidder to be used in conjunction with the Instruction to Bidders, Section 00100 clauses.
2. POINT OF CONTACT
All questions concerning this solicitation shall be addressed in writing to Kate Arnold at email address:
kathryn.l.arnold3.civ@us.navy.mil; Tel # (757) 341-0554.
3. CHANGES TO SOLICITATION
All changes will be issued via Amendment and posted on the Contract Opportunities (FBO) website: https:// sam.gov. It is the contractor’s responsibility to monitor for any changes or updates.
ALL PRE-BID INQUIRIES (PBI) MUST BE SUBMITTED NO LATER THAN 10 DAYS PRIOR TO BID
OPENING DATE. PBIs submitted after the cut-off date may not receive a response. All inquiries must be emailed to kathryn.l.arnold3.civ@us.navy.mil and submitted on the PBI Form (provided as an attachment herein). Please include the solicitation number and contract title in the subject line of the Email when submitting your PBIs. All plans, specifications and amendments will be posted to the sam.gov website.
4. MINIMUM INSURANCE REQUIREMENTS:
a. The contractor shall procure and maintain during the entire period of performance under this contract the following minimum insurance coverage (also refer to FAR 52.228-5):
1. Comprehensive General Liability: $500,000 per occurrence.
2. Automobile Liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage.
3. Workmen’s Compensation: As required by Federal and State workers’ compensation and occupational disease laws.
4. Employer’s Liability Coverage: $100,000 except in states where workers compensation may not be written by private carriers.
5. Others as required by State of Virginia.
b. Prior to commencement of work, the contractor shall furnish to the Contracting Officer a certificate or written statement of the above required insurance. The policies evidencing required insurance shall contain an endorsement to the effect that cancellation or any material change in the policies adversely affecting the interests of the Government in such insurance shall not be effective for such period as may be prescribed by laws of the state in which this contract, N40085-21-B-0056 is to be performed, and in no event less than thirty (30) days after written notice thereof to the Contracting Officer.
c. The Contractor agrees to insert the substance of this clause, including this paragraph (c), in all subcontracts hereunder.
Cancellation Language: The cancellation language must state, "Any cancellation or any change in the limits of liability shall not be effective (1) for such period as the laws of the state in which this contract is to be performed prescribe or (2) until 30 days after the insurer gives written notice to the Contracting Officer, whichever period is longer.” Wording such as "will endeavor to mail notice" or “failure to mail such notice shall impose no obligation or liability" does not comply with the contract requirements and therefore are not acceptable.
5. SITE VISIT
Refer to FAR 52.236-27 for Site Visit.
A site visit is not scheduled at this time. If bidders desire a site visit, please request it in writing to Dean Gregory at dean.s.gregory2.civ@us.navy.mil AND Kate Arnold at kathryn.l.arnold3.civ@us.navy.mil on the provided PBI form.
6. CONTRACTOR EVALUATION PERFORMANCE REPORTING (CPAR)
The contractor is required to provide the government with the name, phone number and e-mail address of the “Contractor’s Representative” that will be responsible for receipt and review of draft performance evaluations prepared by the government. It is the contractor’s responsibility to keep this contact information current. Prime Contractor should become familiar with the CPAR Program requirements at https://cpars.csd.disa.mil.
7. EMPLOYMENT ELIGIBILITY VERIFICATION
If contractor is not enrolled at time of award, then the Contractor shall enroll within 30 days. Refer to FAR Clause 52.222-54 for further instructions.
8. WAWF INVOICE PROCESSING
This contractor will utilize electronic invoice processing. Refer to DFAR Clauses 252.232-7006 and 252.232-7003 for further information.
9. DEPLOYMENT OF SUBCONTRACT REPORTING REQUIREMENTS
A requirement has been implemented regarding the Federal Funding Accountability and Transparency Act. Refer to FAR Clause 52.204-10 for reporting instructions by the Prime Contractor.
10. DELIVERY OF BID
Bid Submission shall be labeled “BID SUBMISSION FOR IFB N4008521B0056, ATTN: KATE ARNOLD; DO
NOT OPEN IN MAIL ROOM”.
BID DUE DATE:
BIDS SHALL BE RECEIVED ON OR BEFORE Monday, November 1, 2021 at 2:00 p.m. Eastern Daylight Time electronically. Send to: Kate Arnold via DoD SAFE (Instructions provided below). A hard copy of the Bid shall be forwarded separately by mail and shall be received on or before Thursday, November 4, 2021 12:00 p.m. Eastern Daylight Time.
The electronic and hard copy bids shall be identical. Furthermore, if there is a discrepancy between the two bid documents submitted, the electronic bid shall govern. Failure to submit an electronic bid by the specified date and time shall render the bid LATE and therefore, unacceptable. It will not be considered further.
Electronic Copy due: Monday, November 1, 2021 2:00 p.m EDT.
Hard Copy due: Thursday, November 4, 2021 12:00 p.m. EDT.
LATE BIDS WILL NOT BE CONSIDERED.
Due to COVID 19 restrictions, a public bid opening will not be held. Additionally, bid packages shall be sent through DOD Safe file in accordance with instructions below.
Electronic Bid Delivery Information via DOD Safe Site:
Contractors shall send their Electronic Bid submission to Kate Arnold through the DOD Safe Site (safe.apps.mil).
Only DoD SAFE is authorized for the submission of the electronic original bid in response to this solicitation.
Further guidance is provided below for submission of hard copy submissions.
The contractor shall send the contract specialist, Kate Arnold at kathryn.l.arnold3.civ@us.navy.mil, the email address of the offeror’s point of contact who will be receiving the Drop-Off invitation to upload bids to the DOD Safe Site no later than Wednesday, October 27, 2021 by 1400, unless that date and time are changed via Solicitation Amendment.
The Contract Specialist, Kate Arnold, will “Request a Drop-Off” through DoD SAFE utilizing the provided offeror’s point of contact email address. The recipient will receive an automated email containing the information for the request and instructions for uploading. Requests from DoD SAFE will be sent on Thursday, October 28, 2021. If you do not receive an email containing drop off instructions on that date, please contact the Contract Specialist. Only the identified POC will be able to drop-off bids or bid revisions in DOD SAFE. Failure to provide accurate POC information will preclude the Offeror from using DoD SAFE. Note: only two email addresses may be provided per Offeror.
To submit the bid, the Offeror will utilize the link provided in the automated email to take you to DoD SAFE at https://safe.apps.mil. The system will allow for inclusion of a short note to the Recipient and then the Offeror will click to add files or drag and drop them. Click “Drop-Off Files” to send the files to the recipient. You should receive a notification on the site “Drop-Off Completed” “Your files have been sent successfully.” Please keep this for your records. The file(s) are uploaded and an email will be sent to the recipient notifying them of the “drop-off”.
[Additional details can be viewed in the DoD SAFE User Guide available at https://safe.apps.mil]. Note that the submission of any bid must be completed no later than the due date and time, unless the date and time are changed via Solicitation Amendment, using the link sent by the contract specialist via DOD Safe. The DoD SAFE system will record the date and time of package submittal. The date and time of package submittal recorded in DoD SAFE shall govern the timeliness of any bid submission.
Offerors shall allow adequate time to upload files which may be slower for non-DoD users and to avoid other technical difficulties that may be encountered. Offerors are also responsible for submitting files in the format specified and consistent with requirements stated elsewhere in this solicitation. Files that cannot be opened, or are otherwise missing the required content are the responsibility of offerors. The maximum file size of a package is 8 GB. Up to 25 packages may be uploaded per link.
It is the sole responsibility of the Offeror to obtain the IFB files, along with any amendments, from Opportunities (www.sam.gov).
Mailed Hard Copies
In addition, one (1) original and one (1) copy of the hard copy bid shall be delivered by mail on the date and time listed below, respectively, unless those dates are changed via Solicitation Amendment.
Bid Submission shall be labeled “BID SUBMISSION FOR IFB N4008521B0056, ATTN: KATE ARNOLD; DO
NOT OPEN IN MAIL ROOM”.
Hard copy bids shall be be mailed as follows:
Naval Facilities Engineering Command, Mid-Atlantic Public Works Department Norfolk Facilities Engineering and Acquisition Division Building A81, 2nd Floor 9742 Maryland Ave Norfolk, VA 23511-2609 Attn: Kate Arnold, AQ
The Government is not responsible for any delays experienced by the commercial carrier. Bid delivered by commercial carrier will be treated as Hand-carried bids for purposes of determining lateness. Bidders shall advise such carriers of the delivery instructions and the Government shall not be responsible for any delays experienced by the commercial carrier.
11. PRICE
A. Price Submission:
1. PRICE BINDER: Offeror shall submit one (1) original, marked “Original”, and one (1) copy, with the following:
Cover page with Solicitation Number, Solicitation Title, Prime
Contractor Name, Address, Phone Number, Fax Number, DUNS, Cage Code, Point of Contact, phone number, and email address Price Bid Worksheet (Attachment 6) Acknowledgement of Amendment(s) (as applicable) Copy of Representation and Certifications from SAM Bid Bond Completed copy of Provision 52.204-24
B. Basis of Evaluation:
1. The Government will evaluate price based on the lump sum price. The Government will evaluate price based on the total price proposal including the base price and all options. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
a. Comparison of proposed prices received in response to the RFP.
b. Comparison of proposed prices with the Independent Government Cost Estimate (IGCE).
c. Comparison of Proposed prices with available historical information.
d. Comparison of market survey results.
12. EVALUATION
1. The Govermnent reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the contract and to award the contract to the offeror submitting the lowest price acceptable proposal.
2. The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). The government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range.
3. From all proposals deemed eligible for award, the lowest price will be chosen.
13. WHOLE DOLLAR PRICING
Bids will be rounded down to the nearest whole dollar for evaluation and subsequent award purposes. If after rounding takes place there are multiple identical low bidders, FAR 14.408-6 shall apply.
14. PAYMENT INSTRUCTIONS
Updated payment instructions can be found under PGI 204.7108(b)(2) at the following link:
https://www.acq.osd.mil/dpap/dars/pgi/pgi_htm/current/PGI204_71.htm#payment_instructions Procurement Method: This acquisition will be advertised utilizing FAR Part 14 – Sealed Bidding resulting in a Firm Fixed Price (FFP), contract for construction services.
NAICS: The NAICS code for this procurement is 237990_except and the size standard is $30.0M
Magnitude of Construction: More than $10,000,000
Contractor Performance Information: Contractor’s performance will be evaluated using the respective contractor performance evaluation report entry system located on the website http://www.cpars.gov/. Prior to commencement of work the contractor is required to provide the government with the name, phone number and e-mail address of the “Contractor’s Representative” that will be responsible for receipt and review of draft performance evaluations prepared by the government in the appropriate system. It is the contractor’s responsibility to keep this contact information current.
Construction Wage Requirements: General Wage Determinations covering the areas of responsibility are included in this solicitation. The most current wage decision will be incorporated into the contract. Refer to Section 007000 - Contract Clauses and Section 010000 – General Requirements.
Bonding Requirements:
• A bid guarantee is required; Refer to Section 007000 –Conditions of Contract, 52.228-1 Bid Guarantee.
• Payment and Performance bonds are required; Refer to Section 002113 – Instructions to Bidders, 52.228-15 Performance and Payment Bonds-Construction.
• Bidders should account for this cost in their unit prices.
• Completed SF1442 (front and back) signed with all amendments acknowledged
• Section 001000 of the SF 1442– Solicitation Contract Form CLINs 0001AA-AJ (Base CLINs), CLIN 0002 (Option Item 0001) and CLIN 0003 (Option Item 2);
• Copy of Representation and Certifications and proof of registration in System for Award Management (SAM);
• Confirmation of filing of Veterans’ Employment and Training (VETS) VETS-4212 for the 2020 filing cycle;
• Bid Guarantee in accordance with FAR Clause 52.228-1
• Bidders are required to submit CLIN 0001 AA-AJ (Base Price), CLIN 0002 (Option Item 0001) and CLIN 0003 (Option Item 2) Bid schedule document.
BIDS SUBMITTED IN RESPONSE TO THIS INVITATION FOR BIDS MUST BE RECEIVED NO LATER
THAN THE DATE AND TIME SPECIFIED HEREIN. Bids not received by the time and date specified shall be treated in accordance with FAR 52.214-7 “Late Submissions, Modifications, and Withdrawals of Bids”.
SAM.gov: Amendments will be posted directly to SAM.gov. The technical documents will be posted on SAM.gov.
It is the contractor’s responsibility to check SAM.gov for all postings.
OFFERORS ARE ADVISED THAT FUNDING MAY NOT BECOME AVAILABLE. IF FUNDS ARE NOT
AVAILABLE, NO AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION. OFFERORS WILL
NOT BE REIMBURSED FOR ANY EFFORT OR PROPOSAL COSTS RESULTING FROM THIS
SOLICITATION.
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
The following have been added by full text:
252.223-7999
252.223-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021- O0009)
As prescribed in Class Deviation 2021-O0009, Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors, use the following clause:
ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS (DEVIATION
2021-O0009) (OCT 2021)
(a) Definition. As used in this clause –
United States or its outlying areas means—
(1) The fifty States;
(2) The District of Columbia;
(3) The commonwealths of Puerto Rico and the Northern Mariana Islands;
(4) The territories of American Samoa, Guam, and the United States Virgin Islands; and (5) The minor outlying islands of Baker Island, Howland Island, Jarvis Island, Johnston Atoll, Kingman Reef, Midway Islands, Navassa Island, Palmyra Atoll, and Wake Atoll.
(b) Authority. This clause implements Executive Order 14042, Ensuring Adequate COVID Safety Protocols for Federal Contractors, dated September 9, 2021 (published in the Federal Register on September 14, 2021, 86 FR 50985).
(c) Compliance. The Contractor shall comply with all guidance, including guidance conveyed through
Frequently Asked Questions, as amended during the performance of this contract, for contractor or subcontractor workplace locations published by the Safer Federal Workforce Task Force (Task Force Guidance) at https:/www.saferfederalworkforce.gov/contractors/.
(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in subcontracts at any tier that exceed the simplified acquisition threshold, as defined in Federal Acquisition Regulation 2.101 on the date of subcontract award, and are for services, including construction, performed in whole or in part within the United States or its outlying areas.
(End of clause)
(End of Summary of Changes)