Attachment 6 - Price Bid Worksheet Revision 01.pdf

PDF 467 KB Posted

Attached to
Pier 11 South Berth Expansion and Maintenance Dredging at Naval Station Norfolk, Norfolk, Virginia
Solicitation number
N4008521B0056
Issued by

About this file

This document contains a price bid worksheet and related solicitation for dredging services at Naval Station Norfolk in Virginia. The solicitation seeks bids for new dredging of Pier 11 South Berth Expansion areas to remove approximately 65,591 cubic yards of non-POL contaminated sediment and 64,712 cubic yards of POL contaminated sediment. Maintenance dredging of approximately 22,892 cubic yards at Pier 5 North and 69,329 cubic yards at Pier 6 North is also requested. Bidders must provide unit prices and total prices for each dredging item along with mobilization, disposal of debris, buoy relocation, and daymarker installation. Award will be made to the responsible bidder offering the lowest total price for all contract line items, with options to award maintenance dredging of Piers 5 North and 6 North within 90 days of the base contract. The performance period is 180 days from award.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PIER 11 SOUTH BERTH EXPANSION NEW DREDGING

AND PIER 5 NORTH AND 6 NORTH MAINTENANCE DREDGING IFB N40085-21-B-0056

ATTACHMENT 6

PRICE BID WORKSHEET

1. The terms Offeror and Bidder and versions thereof (offer/bid) have the same definition as used within this contract.

CLIN 0001 ‐ BASE PRICE – NS NORFOLK PIER 11S BERTH EXPANSION AND MAINTENANCE

DREDGING. Bidders will provide a unit price and total price for each item number (ex: 0001AA) on Table 1 below, and then provide a combined total costs for items 0001AA through 0001AJ under CLIN 0001 at the bottom of Table 1.

ITEMs 0001AA thru 0001AJ in accordance with the drawings and specifications as detailed in the TABLE 1 Below:

Table 1:

ITEM # Description UNIT

UNIT

PRICE

NO.

UNITS

TOTAL PRICE

FOR CLIN (UNIT

PRICE X NO.

UNITS)

0001AA Mobilization/Demobilizaton: LS

1 $_______

0001AB

Pier 11 South Berth Expansion ‐ New Dredging of Non‐POL Contaminated Material via Conventional Clamshell or Hydraulic Cutterhead Dredge, Dispose at Craney Dredge Material Management Area Upland Cell or Rehandling Basin. Unit price shall include all transportation and disposal related costs including Craney Island disposal fees payable to the Army Corps of Engineers. The government SHALL NOT be responsible for payment of any Craney Island disposal fees.

CY 65,591 $_______

0001AC

Clamshell Bucket Dredging Of Sandy Material From Side Slope Source Material Area As Shown On Plan (Sheet V‐102). Place Material Using Clamshell Bucket To Create A 3' Thick Layer Of Sandy Fill To Cap Southern And Eastern Side Slopes

CY 21,800 $_______

0001AD

Pier 11 South Berth Expansion ‐ Bucket dredging to remove sediment and debris within 60' x 200' area shown on plan. Sediment and debris dredged from this area that passes

CY 3,395 $_______

through the 12" x 12" grizzly screen are anticipated to be contaminated with POL material and consequently disposed at an approved upland facility in accordance with plans and specifications. Bucket dredging work in this area includes installation and maintenance of turbidity curtain and oil absorbent boom around entire dredging operation plus all other incidental work required. Unit price shall include all transportation and all disposal related costs including tipping fees, material sampling and analytical testing required by the disposal facility.

0001AE

Pier 11 South Berth Expansion ‐ New Dredging of POL Contaminated Sediment using standard clamshell bucket and disposed at an approved upland facility in accordance with plans and specifications. Bucket dredging work includes installation and maintenance of turbidity curtain and oil absorbent boom around entire dredging operation plus all other incidental work required. Unit price shall include all transportation and all disposal related costs including tipping fees, material sampling and analytical testing required by the disposal facility.

CY 64,712 $_______

0001AF

Furnish and place 13,400 CY VDOT Class 1 Rip‐ Rap armor stone, plus salvaged concrete rubble and salvaged rip‐rap stone over capping sand along Southern and Eastern Slopes of berth expansion as specified in plans and specs

LS 1 $_______

0001AG

Disposal of existing embedded steel sheet piling stubs, timber piling stubs and other misc debris

TON 1,000 $_______

0001AH

Remove 2 exist. buoys, anchor and chain, temporarily store upland (as directed by government) during dredging. Relocate 1 existing buoy as shown on plans. Second buoy to be moved to an upland location as directed by government

LS 1 $_______

0001AI

Furnish and Install (1) 48"H x 48"W Red Daymarker, Mount to West face of Exist. Conc.

Break Water as Specified on Plans

LS 1 $_______

0001AJ Downtime HR 24 $_______

TOTAL

ITEMs 0001AA through 0001AJ

CLIN 0002 – OPTION 0001 –MAINTENANCE DREDGING OF PIER 5 NORTH, NSN: Bidders will provide a unit price and total price for item number 0002AA on Table 2 below, and then provide a combined total cost for item 0002AA at the bottom of Table 2.

Note: Price for dredging in accordance with the drawings and specifications. No additional days will be added to the original contract completion date if this Option is awarded.

TABLE 2

ITEM Description UNIT UNIT

PRICE

NO.

UNITS

TOTAL PRICE

FOR CLIN 0002

(UNIT PRICE X

NO. UNITS)

0002AA

Price for Maintenance Dredging using conventional clamshell or hydraulic cutterhead dredge at outer berth of Pier 5 North in accordance with the drawings and specifications and disposal of material directly into an upland Containment Cell of Craney Island Dredge Material Management Area, Portsmouth, VA. Unit price shall include all transportation and disposal related costs including Craney Island disposal fees payable to the Army Corps of Engineers. The government SHALL NOT be responsible for payment of any Craney Island disposal fees.

Cubic Yard

$_______ 22,892 $_______

ITEM 0002AA

CLIN 0003 – OPTION 0002 – MAINTENANCE DREDGING OF PIER 6 NORTH, NSN: Bidders will provide a unit price and total price for item number 0003AA on Table 3 below, and then provide a combined total cost for item 0003AA at the bottom of Table 3.

Note: Price for dredging in accordance with the drawings and specifications. No additional days will be added to the original contract completion date if this Option is awarded.

TABLE 3

ITEM DESCRIPTION UNIT

UNIT

PRICE

NO.

UNITS

TOTAL PRICE

FOR CLIN 0003

(UNIT PRICE X

NO. UNITS)

0003AA

Price for Maintenance Dredging using conventional clamshell or hydraulic cutterhead dredge at outer berth of Pier 6 North in accordance with the drawings and specifications and disposal of material directly

Cubic Yard

$_______ 69,329 $_______ into an upland Containment Cell of Craney Island Dredge Material Management Area, Portsmouth, VA. Unit price shall include all transportation and disposal related costs including Craney Island disposal fees payable to the Army Corps of Engineers. The government SHALL NOT be responsible for payment of any Craney Island disposal fees.

ITEM 0003AA

TOTAL PRICE FOR CLINs 0001 + CLIN 0002 + CLIN 0003 ___________

2. GENERAL BID NOTES

a. Award will be made on the total sum of Contract Line Items (CLINs) 0001 (Item #s 0001AA through 0001AJ), CLIN 0002 (Item# 0002AA), and CLIN 0003 (Item#003AA). As advised, for each item number under CLINs 0001, 0002 and 0003, enter unit prices and extended totals in spaces provided. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.

b. The Government reserves the unilateral right to award CLIN 0002 and CLIN 0003 to the Contractor at the proposed price at the time of base award or within 90 calendar days after the contract award. A firm fixed proposed price is required for CLIN 0001 and CLIN 0002 and CLIN 0003. No provision is made for economic price adjustment. If Options are exercised, the contract completion date remains 180 calendar days after award of the contract.

c. Evaluation of Options (JUL 1990). Except when it is determined in accordance with

FAR 17.206(b), Evaluation, not to be in the best interest of the Government, the Government will evaluate offers for award purposes by adding the price for the Option(s), CLINS 0002 and 0003, to the total price for CLIN 0001. In accordance with FAR 52.217‐5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Options.

d. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work

e. If CLIN 0002 and/or 0003 are exercised, additional bonding and consent of surety is required. Consequently, the Performance Bond must reflect 100 percent of the aggregate amount of all awarded CLINs.

f. In Accordance with FAR 14.101(e), award will be made to the responsible bidder whose bid, conforming to the invitation for bids, will be most advantageous to the Government, considering only price and the price-related factors included in the invitation.