Attachment 4 - Pier11South_Specs.pdf
PDF 1 MB Posted
- Attached to
- Pier 11 South Berth Expansion and Maintenance Dredging at Naval Station Norfolk, Norfolk, Virginia
- Solicitation number
- N4008521B0056
About this file
This solicitation seeks dredging services at Naval Station Norfolk in Virginia. The scope of work includes new dredging of the Pier 11 South Berth expansion area and maintenance dredging of the outer berths of Piers 5 North and 6 North. Maintenance dredging materials and non-POL contaminated materials from the berth expansion may be dredged via clamshell bucket and transported by sealed scow/barge to the Craney Island Dredged Material Management Area (CDMMA) rehandling basin or pumped via hydraulic unloader to an upland CDMMA cell. A portion of Pier 11S contains POL-contaminated sediments that must be dredged via clamshell bucket and disposed at an approved upland facility. Additional requirements include placing sandy capping materials dredged on-site and installing armor stone layers to cap remaining POL sediments. The Navy is the contracting agency, with proposals due by the date specified in the solicitation.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
eProjects WO#: 1663506
FY22 Pier 11S Berth Expansion New Dredging and Pier 5N and 6N Maintenance Dredging
AT
NORFOLK NAVAL STATION, NORFOLK, VIRGINIA
DESIGNED BY:
NAVFAC MID-ATLANTIC
DESIGN AND CONSTRUCTION
CORE HYDROGRAPHIC BRANCH (DC45D)
9080 VIRGINIA AVENUE, NS NORFOLK BLDG CEP-188
NORFOLK, VIRGINIA 23511
Date: JULY 30, 2021
SPECIFICATION PREPARED BY: James S. Georgo, P.E.
SPECIFICATIONS APPROVED BY:
Project Manager: Dean S. Gregory, P.E.
Director of Engineering: Eric J. Allen, P.E.
Lead Discipline Team Manager: ____________________________ ______
James S. Georgo, P.E. Date
James E. Donahue, R.A. Date
For Commander, NAVFAC MID-ATLANTIC:
Design Production Director Capital Improvements Core
FY21 NS Norfolk Pier 11S Berth Expansion and Maintenance Dredging 1663506
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 01 15 LIST OF DRAWINGS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00.00 20 PRICE AND PAYMENT PROCEDURES
01 22 00.00 10 MEASUREMENT AND PAYMENT
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT
MANAGEMENT SYSTEM
01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 20 QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
DI VI SI ON 35 - WATERWAY AND MARI NE CONSTRUCTI ON
35 20 23 DREDGING
35 31 19 STONE, CHANNEL, SHORELINE/COASTAL PROTECTION FOR
STRUCTURES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
List of Contract Drawings is contained on NAVFAC Drawing Sheet #12,834,668 which is the first sheet (V-001) of the contract drawings.
SHEET NO. NAVFAC # SHEET TITLE
1 V-001 12834668 TITLE SHEET
2 V-002 12834669 DETAILS AND NOTES
3 V-003 12834670 DETAILS
4 V-101 12834672 PIER 11 SOUTH BERTH EXPANSION POL CONTAMINATED
MATERIAL DREDGING
5 V-102 12834673 PIER 11 SOUTH BERTH EXPANSION DREDGING
6 V-003 12847048 PIER 5 NORTH (OUTER BERTH) MAINTENANCE DREDGING
7 V-104 12847049 PIER 6N (OUTER BERTH) MAINTENANCE DREDGING
8 V-201 12834674 DREDGED MATERIAL MANAGEMENT NARRATIVE
-- End of Document --
DOCUMENT 00 01 15 Page 1
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work includes New Dredging of Pier 11 South Berth Expansion Area and Maintenance Dredging of the outer berths of Piers 5 North and 6 North.
Maintenance Dredging of the outer berths of Piers 5 North and 6 North and Non-POL Contaminated Material from the Berth Expansion Area may be dredged via conventional clamshell bucket, transported via sealed scow/barge and deposited into the CDMMA Rehandling Basin or pumped via hydraulic unloader to an upland cell of the Craney Island Dredge Material Management Area (CDMMA) or dredged via hydraulic cutterhead dredge and pumped directly upland cell of CDMMA. Location of deposition within Craney Island Project Site is subject to change and should be coordinated with the Army Corps of Engineers before dredging begins. A portion of the Pier 11S Berth Expansion area contains sediment contaminated with Petroleum, Oil and Lubricant (POL) material as shown on the plans.
The POL contaminated material shall be dredged via conventional clamshell bucket and disposed at an upland facilty as specified herein and on plans.
Dredging from on-site location and placement of sandy material to be used as side-slope capping (as shown on plans) shall be done via conventional clamshell bucket.
Additional work as shown on the plans and specification shall be performed, including but not limited to, placement of sandy capping material dredged on-site (as shown on plan) and rip-rap armor stone layers along southern and eastern side slopes of Berth Expansion Area to cap disturbed POL contaminated material remaining in place and removal and disposal of debris remaining after the past demolition of steel sheet piling cofferdam break water and timber breakwater structures. Remaining debris may include steel sheet piling stubs and timber piling stubs, concrete rubble and rip-rap stone.
1.1.2 Location
The work shall be located at the Naval Station Norfolk, Norfolk, VA, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.2 CONTRACT DRAWINGS
The following drawings accompany this specification (incl appendicies) and are a part thereof.
NAVFAC Drawings Numbers as listed in Spec. Sec 00 01 15 LIST OF DRAWINGS
SECTION 01 11 00 Page 1
1.3 COMMENCEMENT OF WORK
Once the contract has been awarded the execution schedule shall be coordinated between the government and the contractor with a notice to proceed to be issued within approximately 90 days or less from the contract award date. Once the notice to proceed has been issued the contractor shall commence with mobilization and dredging no later than 30 days after Notice to Proceed.
1.4 WORK RESCHEDULING
Normal duty hours for work shall be 24 hours a day Sunday through Saturday. Contractor shall allow for a maximum of 200 hours where construction activity is prohibitive. Government shall notify Contractor 72 hours in advance as to any ship movements in the area dredging is being conducted.
NAVAL STATION NORFOLK HAS IMPLEMENTED ADDITIONAL SECURITY MEASURES ALONG
THE WATERFRONT. ACCESS TO THE WORK AREAS FROM THE WATER IS RESTRICTED. A
PORT SECURITY BARRIER (PSB) SYSTEM HAS BEEN DEPLOYED WHICH APPROXIMATES
THE RESTRICTED AREA IN THE WATERS SURROUNDING NAVAL STATION NORFOLK. THE
CONTRACTOR SHALL NOTIFY AND REQUEST PORT OPERATIONS TO MOVE AND REPLACE
THIS LINE EACH TIME THE CONTRACTOR REQUIRES ACCESS TO THE RESTRICTED
AREA. THE CONTRACTOR MUST NOTIFY PORT OPERATIONS AT 444-1121 AT LEAST
FIVE (5) BUSINESS DAYS IN ADVANCE OF ANY MOVEMENT OF THE PSB REGARDLESS OF
THE TIME OF DESIRED OPENING (WEEKENDS, WORKING/NON-WORKING HOURS ETC...)
FOR LONG TERM PSB OPENING REQUESTS (>1 HOUR) FOR APPROACH DREDGING AND
RELOCATION OF DREDGING EQUIPMENT AND PIPELINES, NOTIFY PORT OPS A MINIMUM
OF SEVEN DAYS IN ADVANCE. CONTRACTOR SHOULD EXPECT TO RECEIVE APPROVAL 24
HOURS PRIOR TO EACH DESIRED OPENING DATE (VETTING TAKES PLACE THE DAY
BEFORE ENTRY). ALL CONTRACTORS ON BOARD THE VESSEL ARE REQUIRED TO HAVE
VALID DBIDS CARDS FOR ENTRY TO NAVAL STATION NORFOLK.
1.5 PROJECT ENVIRONMENTAL GOALS
Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to produce an end product that meets the functional program needs and incorporates the principles of sustainability. Specifically:
a. Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion. Minimize offsite environmental impact.
b. Use the minimum amount of energy, water, and materials feasible to meet the design intent. Select energy and water efficient equipment and strategies.
c. Use environmentally preferable products and decrease toxicity level of materials used.
d. Use renewable energy and material resources.
e. Manage construction site and storage of materials to ensure no negative impact on the environment.
PART 2 PRODUCTS
Not Used.
SECTION 01 11 00 Page 2
PART 3 EXECUTION
Not Used.
-- End of Section --
SECTION 01 11 00 Page 3
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Pier Parking Authorization; G
Personnel List; G
Vehicle List; G
Dredge Plans; G
Dredge plans to show progressive positioning of hydraulic dredge, crane barge(s), scows, tender boats, etcat the dredging site. If contractor opts to use the government designated on-base material mixing and offloading site as shown in Appendix "C", plan shall also show site trailer if proposed, material staging, barge staging, barge transport route to/from dredging area truck ingress and egress route, etc.
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. The piers and waterfront at Norfolk Naval Station, Norfolk, VA will remain in operation during the entire dredging period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the activity.
b. Contractor shall coordinate with the Contracting Officer prior to start of dredging to determine order of work. The Government reserves the right to change the order of work at any time.
c. Permission to interrupt any Activity roads, railroads, and/or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
d. At Naval Station, Norfolk, due to extremely heavy ship berthing schedule during the holidays, dredging work or hydroid net work may only occur during the period from 15 Nov - 15 Jan of any year with special authorization by the contracting officer. This period of time shall be referred to as the "holiday berthing period of restricted contractor activity."
SECTION 01 14 00 Page 1
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at . No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
1.3.1.2.1 Registration for DBIDS
All Contractor personnel shall obtain access to the installation through enrollment and registration into the Defense Biometric Identification System (DBIDS). Procedure includes:
a. Presnet a letter or official award document (i.e. DD FORM 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at .
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, finger prints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.3.1.2.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must
SECTION 01 14 00 Page 2 continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualificatoin from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.
The Government is the final authority.
1.3.1.2.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installatoin or anyone therin.
1.3.1.2.4 One-Day Passes
Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.3.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours must consist of a period established by the Contractor Officer, between 7 a.m. and 3:30 p.m., Monday through Friday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
SECTION 01 14 00 Page 3
1.4 SECURITY REQUIREMENTS
Contract Clause FAR 52.204-2 Security Requirements and Alternate II," "FAC 5252.236-9301, Special Working Conditions and Entry to Work Area," and the following apply:
1.4.1 Naval Base, Norfolk, VA
a. Contractor registration. Register with the Base Police Truck Investigation Team, located behind pass and ID Office (Bldg CD-9) on Hampton Boulevard, Naval Air Station, Norfolk, VA 23511-5000, telephone number (757) 322-2979.
b. Storage and office trailer registration. Register storage and office trailers to be used on base with the truck investigation team. Trailers must meet State law requirements and must be in good condition.
(1) Trailers shall be lockable and must be locked when not in use.
(2) Trailers shall have a sign in the lower left hand corner of left door of trailer with the following information: Company name, address, registration number of trailer or vehicle identification number, location on base, duration of contract or stay on base, contract number, local on-base phone number, off-base phone number of main office, and emergency recall person and phone number.
c. Equipment markings. Equipment owned or rented by the company shall have the company name painted or stenciled on the equipment in a conspicuous location. Rented equipment is to be conspicuously marked with a tag showing who rented the equipment. Register the equipment with the truck investigation team.
d. Procedure information. For additional information regarding registration procedures, contact the Officer in Charge of Construction at (757) 445-1463 or Base Police at (757) 444-8856.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
SECTION 01 14 00 Page 4
SECTION 01 20 00.00 20
PRICE AND PAYMENT PROCEDURES
11/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP-1110-1-8 (2009) Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Schedule of Prices; G
1.3 SCHEDULE OF PRICES
1.3.1 Data Required
Within 15 calendar days of notice of award, prepare and deliver to the Contracting Officer a Schedule of Prices (construction contract) as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices therefore in accordance with the bid schedule. Costs shall be summarized and totals provided for each construction category.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause "DFARS 252.236-7000, Modification Proposals-Price Breakdown," and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates shall be based upon the applicable provisions of the EP-1110-1-8 .
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27, Prompt Payment Construction Contracts and FAR 52.232-5, Payments Under Fixed-Price Construction Contracts. The
SECTION 01 20 00.00 20 Page 1 requests for payment shall include the documents listed below.
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 shall include certification by Quality Control (QC) Manager as required by the contract.
b. The Estimate for Voucher/Contract Performance Statement on NAVFAC Form 7300/31 furnished by the Government, showing in detail: the estimated cost, percentage of completion, and value of completed performance.
Use NAVFAC LANT Form 4-330/110 (New 7/84) on NAVFAC LANT contracts when a Monthly Estimate for Voucher is required.
c. Updated Project Schedule and reports required by the contract.
d. Contractor Safety Self Evaluation Checklist.
e. Other supporting documents as requested.
f. Updated copy of submittal register.
g. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.
1.5.2 Submission of Invoices
If NFAS Clause 5252.232-9301 is included in the contract, the documents listed in paragraph "CONTENT OF INVOICE" shall be provided in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction it shall be provided as instructed by the Contracting Officer.
1.5.3 Final Invoice
a. A final invoice shall be accompanied by the certification required by DFARS 252.247.7023 TRANSPORTATION OF SUPPLIES BY SEA, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release shall contain the corporate seal. An officer of the corporation shall sign and the corporate secretary shall certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor shall then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
SECTION 01 20 00.00 20 Page 2
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to reductions and/or suspensions permitted under the FAR and agency regulations including the following in accordance with "FAR 32.503-6:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to provide up to date record drawings not current as stated in Contract Clause "FAC 5252.236-9310, Record Drawings."
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
SECTION 01 20 00.00 20 Page 3
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
04/06
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
1.2 LUMP SUM PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2.1 Mobilization and Demobilization
1.2.1.1 Payment
Payment will be made for costs associated with mobilization and demobilization, as defined in Special Clause PAYMENT FOR MOBILIZATION AND
DEMOBILIZATION.
1.2.1.2 Unit of Measure
Unit of measure: lump sum.
1.3 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.3.1 Dredging and Upland Disposal
1.3.1.1 Payment
Payment will be made for costs associated with hydraulic dredging in accordance with the drawings and specifications which includes performing
SECTION 01 22 00.00 10 Page 1 required operations incidental thereto.
1.3.1.2 Measurement
The total quantity of dredged material for which payment occurs will be measured by computing the volume between the bottom surface shown by soundings of the last surveys made by the government before dredging, and the bottom surface shown by the soundings of surveys made by the government after the work has been completed. Allowance will be made for overdepth dredging as indicated on the contract drawings. No allowance will be made for the removal of any material outside the required slope lines or outside and beyond overdredge depths, unless authorized.
1.3.1.3 Unit of Measure
Unit of measure: cubic yard.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
SECTION 01 22 00.00 10 Page 2
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.3 SUPERVISION
1.3.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.00 20 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
1.3.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.3.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red
SECTION 01 30 00 Page 1
Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.3.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.4 PRECONSTRUCTION MEETING
Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The meeting must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.4.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.5 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)
Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NRZ Meetings beginning at approximately 75 percent of project completion.
Include the following in the facility Turnover effort:
1.5.1 Red Zone Checklist
a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.
b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.
SECTION 01 30 00 Page 2
1.5.2 Meetings
a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.
b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer.
At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.
c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.
d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.
e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.
Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.
1.6 MOBILIZATION
Contractor shall mobilize to the jobsite within 60 calendar days of contract award. Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
SECTION 01 30 00 Page 3
SECTION 01 31 23.13 20
ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM
05/17
PART 1 GENERAL
1.1 CONTRACT ADMINISTRATION
Utilize the Naval Facilities Engineering Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or e-mail submission, including originals or copies, of the documents identified in Table 1 are not permitted, except where eCMS is unavailable, non-functional or specifically requested in addition to electronic submission. Contact the Contracting Officer's Representative (COR) regarding availability of eCMS training and reference materials.
1.2 USER PRIVILEGES
The Contractor will be provided access to eCMS. All technical submittals and documents must be transmitted to the Government via the COR. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contractor's Personnel; G
1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY
1.4.1 General
The eCMS requires a web-browser (platform-neutral) and Internet connection. Obtain from an approved vendor an External Certification Authority (ECA), Primary Key Infrastructure (PKI) certificate, or other similar digital identification to support two-factor authentication and access to eCMS. Provide and maintain computer hardware and software for the eCMS access throughout the duration of the contract for all Contractor-designated users. Provide connectivity, speed, bandwidth, and access to the Internet to ensure adequate functionality. Neither upgrading of the Contractor's computer system nor delays associated from the usage of the eCMS will be justification or grounds for a time extension or cost adjustment to the Contract.
1.4.2 Contractor Personnel List
Within 20 calendar days of contract award, provide to the Contracting
SECTION 01 31 23.13 20 Page 1
Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing and management of electronic technical submittals and documents and will require access to the eCMS. Project personnel roles to be filled in the eCMS include the Contractor's Project Manager, Superintendent, Quality Control (QC) Manager, and Site Safety and Health Officer (SSHO). Personnel must be capable of electronic document management. Notify the COR immediately of any personnel changes to the project. The Contracting Officer reserves the right to perform a security check on all potential users. Provide the following information:
First Name Last Name E-mail Address Office Address Project Role (e.g. Project Manager, QC Manager, Superintendent)
1.4.3 Field Administration
Within 30 days of Contract Award, provide a tablet computer with a Common Access Card (CAC) reader at the job site for Government use only. The tablet computer must have a web-browser, built-in camera, and cellular data connectivity. Provide tablet computer with a rugged case suitable for use in a construction environment. The tablet computer must be fully charged and made available at all times for Government use to facilitate the input of construction data at the job site. After completion of the work, reset the tablet computer to factory default settings. The tablet computer remains the property of the Contractor and must be removed from the site. There are restrictions on use of WIFI on military bases.
Cellular data connectivity and availability, and use of WIFI requires coordination with and approval by the Contracting Officer.
1.5 SECURITY CLASSIFICATION
In accordance with Department of Navy guidance, all military construction contract data are unclassified, unless specified otherwise by a properly designated Original Classification Authority (OCA) and in accordance with an established Security Classification Guide (SCG). Refer to the project's OCA when questions arise about the proper classification of information.
The eCMS and tablet computer must only be used for the transaction of unclassified information associated with construction projects. In conformance with the Freedom of Information Act (FOIA), Department of Defense Manual 5200.01-V4: DoD Information Security Program: Controlled Unclassified Information (CUI), and DoD requirements, any unclassified project documentation uploaded into the eCMS must be designated either "U
- UNCLASSIFIED" (U) or "FOUO - UNCLASSIFIED-FOR OFFICIAL USE ONLY" (FOUO).
1.6 ECMS UTILIZATION
Establish, maintain, and update data and documentation in the eCMS throughout the duration of the contract.
Personally Identifiable Information (PII) transmittal is not permitted in the eCMS.
1.6.1 Information Security Classification/Identification
The eCMS must be used for the transmittal of the following documents.
SECTION 01 31 23.13 20 Page 2
This requirement supersedes conflicting requirements in other sections), however, submittal review times in Section 01 33 00 SUBMITTAL PROCEDURES remain applicable. Table 1 - Project Documentation Types provides the appropriate U and FOUO designations for various types of project documents. Construction documents requiring FOUO status must be marked accordingly. Apply the appropriate markings before any document is uploaded into eCMS. Markings are not required on U documents.
Table 1 also identifies which eCMS application is to be used in the transmittal of data (these are subject to change based on the latest software configuration). If a designated application is not functional within 4 hours of initial attempt, defer to the Submittal application and submit the required data as an uploaded portable document (e.g. PDF), word processor, spreadsheet, drawing, or other appropriate format. Hard copy or e-mail submission of these items is acceptable only if eCMS is documented to be not available or not functional. After uploading documents to the Submittal application, transmit the submittals and attachments to the COR via the Transmittal application. For Submittals, select the following:
Preparation by = Contractor personnel assigned to prepare the submittal Approval by = Contracting Officer Representative (COR) Returned by = Design Lead/Manager Forwarded to = Contractor project manager
Table 1 - Project Documentation Types
SUBJECT/NAME CLASS REMARKS ECMS APPLI CATI ON
As-Built Drawings U Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Submittals and Transmittals
Building Information Modeling (BIM)
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
Construction Permits U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
SECTION 01 31 23.13 20 Page 3
SUBJECT/NAME CLASS REMARKS ECMS APPLI CATI ON
Construction Schedules (Activities and Milestones)
U After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Submittals, Transmittals and Scheduling App
Construction Schedules (Cost-Loaded)
FOUO After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Submittals, Transmittals and Scheduling App
Construction Schedules (3-Week Lookahead)
U Import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Scheduling App
DD 1354 Transfer of Real Property
U Submittals and Transmittals
Daily Production Reports
FOUO Provide weather conditions, crew size, man-hours, equipment, and materials information
Daily Report
Daily Quality Control (QC) Reports
FOUO Provide QC Phase, Definable Features of Work Identify visitors
Daily Report
Designs and Specifications
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
Environmental Notice of Violation (NOV), Corrective Action Plan
U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
Environmental Protection Plan (EPP)
FOUO Submittals and
SECTION 01 31 23.13 20 Page 4
Invoice (Supporting Documentation)
FOUO Applies to supporting documentation only. Invoices are submitted in Wide-Area Workflow (WAWF)
Submittals and Transmittals
Jobsite Documentation, Bulletin Board, Labor Laws, SDS
U Submittals and Transmittals
Meeting Minutes FOUO Meeting Minutes
Operations & Maintenance Support Information (OMSI/eOMSI), Facility Data Worksheet
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
Photographs U Subject to base/installation restrictions
Submittals and Transmittals
QCM Initial Phase Checklists
FOUO Checklists (Site Management)
QCM Preparatory Phase Checklists
FOUO Checklists (Site Management)
Quality Control Plans FOUO Submittals and Transmittals
QC Certifications U Submittals and Transmittals
QC Punch List U Punch Lists (Testing Logs)
Red-Zone Checklist U Checklists (Site Management)
Rework Items List FOUO Punch Lists (Testing Logs)
Request for Information (RFI) Post-Award
FOUO RFIs
SECTION 01 31 23.13 20 Page 5
Safety Plan FOUO Daily Report
Safety - Activity Hazard Analyses (AHA)
FOUO Daily Report
Safety - Mishap Reports
FOUO Daily Report
SCIF/SAPF
Accreditation Support Documents
FOUO Note: Some Construction Security plans may be classified as Secret.
Classified information must not be uploaded into eCMS. Refer to the Site Security Manager, as applicable.
Submittals and Transmittals
Shop Drawings U Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Submittals and Transmittals
Storm Water Pollution Prevention (Notice of Intent - Notice of Termination)
U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
Submittals and Submittal Log
U Submittals and Transmittals
Testing Plans, Logs, and Reports
FOUO Submittals and Transmittals
Training/Reference Materials
U Submittals and Transmittals
Training Records (Personnel)
FOUO Submittals and Transmittals
Utility Outage/Tie-In Request/Approval
FOUO Submittals and Transmittals
Warranties/BOD Letter FOUO Submittals and
SECTION 01 31 23.13 20 Page 6
Quality Assurance Reports
FOUO Checklists (Government initiated)
Non-Compliance Notices
FOUO Non-Compliance Notices (Government initiated)
Other Government-prepared documents
FOUO GOV ONLY
All Othere Documents FOUO Refer to FOIA guidelines and contact the FOIA official to determine whether exemptions exist
As applicable
1.6.2 Markings on FOUO documents
a. Only FOUO documents being electronically uploaded into the eCMS (.docx, .xlsx, .pptx, .pdf, .jpg, .zip, and others as appropriate), and associated paper documents described in the paragraph CONTRACT ADMINISTRATION require FOUO markings as indicated in the subparagraphs below.
b. FOUO documents that are originally created within the eCMS application using the web-based forms (RFIs, Daily Reports, and others as appropriate) will be automatically watermarked by the eCMS software, and these do not require additional markings.
c. FOUO documents must be marked "UNCLASSIFIED//FOR OFFICIAL USE ONLY" at the bottom of the outside of the front cover (if there is one), the title page, the first page, and the outside of the back cover (if there is one).
d. FOUO documents must be marked on the internal pages of the document as "UNCLASSIFIED//FOR OFFICIAL USE ONLY"' at top and bottom.
e. Where Installations require digital photographs to be designated FOUO, place the markings on the face of the photograph.
f. For visual documentation, other than photographs and audio documentation, mark with either visual or audio statements as appropriate at both the beginning and end of the file.
1.7 QUALITY ASSURANCE
Requested Government response dates on Transmittals and Submittals must be in accordance with the terms and conditions of the Contract. Requesting response dates earlier than the required review and response time, without concurrence by the Government COR, may be cause for rejection.
Incomplete submittals will be rejected without further review and must be resubmitted. Required Government response dates for resubmittals must reflect the date of resubmittal, not the original submittal date.
SECTION 01 31 23.13 20 Page 7
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
SECTION 01 31 23.13 20 Page 8
SECTION 01 32 16.00 20
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
08/18
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Baseline Construction Schedule; G
SD-07 Certificates
Monthly Updates
1.2 PRE-CONSTRUCTION SCHEDULE REQUIREMENT
Prior to the start of work, prepare and submit to the Contracting Officer a Baseline Construction Schedule in the form of a Bar Chart Schedule in accordance with the terms in Contract Clause FAR 52.236-15 Schedules for Construction Contracts, except as modified in this contract. The approval of a Baseline Construction Schedule is a condition precedent to:
a. The Contractor starting demolition work or construction stage(s) of the contract.
b. Processing Contractor's invoice(s) for construction activities/items of work.
c. Review of any schedule updates.
Submittal of the Baseline Construction Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
1.3 SCHEDULE FORMAT
1.3.1 Bar Chart Schedule
The Bar Chart must, as a minimum, show work activities, submittals, Government review periods, material/equipment delivery, utility outages, on-site construction, inspection, testing, and closeout activities. The Bar Chart must be time scaled and generated using an electronic spreadsheet program.
1.3.2 Schedule Submittals and Procedures
Submit Schedules and updates in hard copy and on electronic media that is
SECTION 01 32 16.00 20 Page 1 acceptable to the Contracting Officer. Submit an electronic back-up of the project schedule in an import format compatible with the Government's scheduling program.
1.4 SCHEDULE MONTHLY UPDATES
Update the Construction Schedule at monthly intervals or when the schedule has been revised. Keep the updated schedule current, reflecting actual activity progress and plan for completing the remaining work. Submit copies of purchase orders and confirmation of delivery dates as directed by the Contracting Officer.
a. Narrative Report: Identify and justify the following:
(1) Progress made in each area of the project;
(2) Longest Path: Include printed copy on 11 by 17 inch paper, landscape setting;
(3) Date/time constraint(s), other than those required by the contract;
(4) Listing of changes made between the previous schedule and current updated schedule including: added or removed activities, original and remaining durations for activities that have not started, logic (sequence, constraint, lag/lead), milestones, planned sequence of operations, longest path, calendars or calendar assignments, and cost loading.
(5) Any decrease in previously reported activity Earned Amount;
(6) Pending items and status thereof, including permits, changes orders, and time extensions;
(7) Status of Contract Completion Date and interim milestones;
(8) Current and anticipated delays (describe cause of delay and corrective actions(s) and mitigation measures to minimize);
(9) Description of current and future schedule problem areas.
For each entry in the narrative report, cite the respective Activity ID and Activity Name, the date and reason for the change, and description of the change.
1.5 3-WEEK LOOK AHEAD SCHEDULE
Prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Construction Schedule.
Key the work plans to activity numbers when a NAS is required and update each week to show the planned work for the current and following two-week period. Additionally, include upcoming outages, closures, preparatory meetings, and initial meetings. Identify critical path activities on the Three-Week Look Ahead Schedule. The detail work plans are to be bar chart type schedules, maintained separately from the Construction Schedule on an electronic spreadsheet program and printed on 8-1/2 by 11 inch sheets as directed by the Contracting Officer. Activities must not exceed 5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work. Deliver three hard copies and one electronic file of the 3-Week Look Ahead Schedule to the
SECTION 01 32 16.00 20 Page 2
Contracting Officer no later than 8 a.m. each Monday, and review during the weekly CQC Coordination or Production Meeting.
1.6 CORRESPONDENCE AND TEST REPORTS:
Correspondence (e.g., letters, Requests for Information (RFIs), e-mails, meeting minute items, Production and QC Daily Reports, material delivery tickets, photographs) must reference Schedule Activities that are being addressed. Test reports (e.g., concrete, soil compaction, weld, pressure) must reference Schedule Activities that are being addressed.
1.7 ADDITIONAL SCHEDULING REQUIREMENTS
Any references to additional scheduling requirements, including systems to be inspected, tested and commissioned, that…