REVISED_SECTION_01_45_02_QUALITY_CONTROL.pdf
PDF 101 KB Posted
- Attached to
- Magazine and inert building maintenance and repair at the Naval Support Activity, Crane, Indiana.
- Solicitation number
- N4008519R7704
About this file
This technical specification outlines quality control requirements for a magazine and inert building maintenance and repair contract at Naval Support Activity Crane in Indiana. Key details include:
-
The contractor must implement a thorough quality control program led by a qualified QC Manager to ensure all work meets specifications. Three phases of control—preparatory, initial, and follow up—are required for each definable feature of work.
-
Comprehensive documentation and reporting is mandated, including daily reports, testing plans and logs, rework item lists, as-built drawings, and certifications. Rigorous testing by an accredited lab is specified.
-
The 12-month base contract with four 12-month options allows for $5,000 minimum to $35 million maximum in work through task orders. The solicitation will use low price technically acceptable procedures.
-
Scope of work involves maintenance and repairs to magazines, inert buildings and associated infrastructure like concrete docks, walls and doors. Hazardous material removal and grounding are also included.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0005_19R7704_MagazineMntRrp.pdf | ||
| Amend_0005_Revised_N4008519R7704_ELINS.xlsx | XLSX spreadsheet | |
| Amendment_0004_19R7704_MagazineMntRpr.pdf | ||
| Amend_0004_Revised_N4008519R7704_ELINS.xlsx | XLSX spreadsheet | |
| Revised_N4008519R7704_ELINS.xlsx | XLSX spreadsheet | |
| Amendment0003_N4008519R7704_MagazineMntRprs.pdf | ||
| PW 6087CAS MAG SECURITY.pdf | ||
| Amendment_0002_N4008519R7704_MagazineMntRpr.pdf | ||
| Amendment_0001_N4008519R7704_MagazineMntRpr.pdf | ||
| N4008519R7704.pdf | ||
| N4008519R7704ELINS.xlsx | XLSX spreadsheet |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 45 00.00 20 Page 1
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704
SECTION TABLE OF CONTENTS DIVISION
01 - GENERAL REQUIREMENTS SECTION
01 45 00.00 20
QUALITY CONTROL REVISED 05/20/2020
11/11
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 INFORMATION FOR THE CONTRACTING OFFICER
1.4 QC PROGRAM REQUIREMENTS
1.4.1 Commissioning
1.4.2 Acceptance of the Construction Quality Control (QC) Plan
1.4.3 Preliminary Construction Work Authorized Prior to Acceptance
1.4.4 Notification of Changes
1.5 QC ORGANIZATION
1.5.1 QC Manager
1.5.1.1 Duties
1.5.1.2 Qualifications
1.5.2 LEED Commissioning Authority
1.5.2.1 Duties
1.5.2.2 Qualifications
1.5.3 Construction Quality Management Training
1.5.4 Alternate QC Manager Duties and Qualifications
1.6 QUALITY CONTROL (QC) PLAN
1.6.1 Construction Quality Control (QC) Plan
1.6.1.1 Requirements
1.7 COORDINATION AND MUTUAL UNDERSTANDING MEETING
1.7.1 Purpose
1.7.2 Coordination of Activities
1.7.3 Attendees
1.8 QC MEETINGS
1.9 DESIGN REVIEW AND DOCUMENTATION
1.9.1 Basis of Design and Design Intent
1.9.2 Design Review
1.9.3 Contract Document Review
1.10 THREE PHASES OF CONTROL
1.10.1 Preparatory Phase
1.10.2 Initial Phase
1.10.3 Follow-Up Phase
1.10.4 Additional Preparatory and Initial Phases
1.10.5 Notification of Three Phases of Control for Off-Site Work
1.11 SUBMITTAL REVIEW AND APPROVAL
1.12 TESTING
1.12.1 Accreditation Requirements
1.12.2 Laboratory Accreditation Authorities
1.12.3 Capability Check
1.12.4 Test Results
1.12.5 Test Reports and Monthly Summary Report of Tests
1.13 QC CERTIFICATIONS
1.13.1 CQC Report Certification
annette.taylor1 Highlight
SECTION 01 45 00.00 20 Page 2
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704
1.13.2 Invoice Certification
1.13.3 Completion Certification
1.14 COMPLETION INSPECTIONS
1.14.1 Punch-Out Inspection
1.14.2 Pre-Final Inspection
1.14.3 Final Acceptance Inspection
1.15 DOCUMENTATION
1.15.1 Construction Documentation
1.15.2 Quality Control Validation
1.15.3 Reports from the QC Specialist(s)
1.15.4 Testing Plan and Log
1.15.5 Rework Items List
1.15.6 As-Built Drawings
1.16 NOTIFICATION ON NON-COMPLIANCE
1.17 CONSTRUCTION INDOOR AIR QUALITY (IAQ) MANAGEMENT PLAN
1.17.1 Requirements During Construction
1.17.1.1 Control Measures
1.17.1.2 Moisture Contamination
1.17.2 Requirements after Construction
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 PREPARATION
-- End of Section Table of Contents --
SECTION 01 45 00.00 20 Page 3
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704
SECTION 01 45 00.00 20
QUALITY CONTROL
11/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 52.2 (2012; Errata 1 2013; INT 1 2014; ADD A, B, AND D SUPP 2015; INT 3 2015; Errata 2 2015; ADD C 2015; ADD E, F 2016) Method of Testing General Ventilation Air-Cleaning Devices for Removal Efficiency by Particle Size
ASTM INTERNATIONAL (ASTM)
ASTM D6245 (2012) Using Indoor Carbon Dioxide
Concentrations to Evaluate Indoor Air Quality and Ventilation
ASTM D6345 (2010) Selection of Methods for Active, Integrative Sampling of Volatile Organic Compounds in Air
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
ANSI/SMACNA 008 (2007) IAQ Guidelines for Occupied
Buildings Under Construction, 2nd Edition
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES
SD-01 Preconstruction Submittals
Construction Quality Control (QC) Plan; G
Submit a Construction QC Plan prior to start of construction.
SECTION 01 45 00.00 20 Page 4
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704
Indoor Air Quality (IAQ) Management Plan; G
Basis of Design and Design Intent
SD-05 Design Data
Design Review
Contract Document Review
SD-07 Certificates
CA Resume
1.3 INFORMATION FOR THE CONTRACTING OFFICER
Prior to commencing work on construction, the Contractor can obtain a single copy set of the current report forms from the Contracting Officer.
The report forms will consist of the Contractor Production Report, Contractor Production Report (Continuation Sheet), Contractor Quality Control (CQC) Report, CQC Report (Continuation Sheet), Preparatory Phase Checklist, Initial Phase Checklist, Rework Items List, and Testing Plan and Log.
Deliver the following to the Contracting Officer during Construction:
a. CQC Report: Mail or hand-carry the original (wet signatures) and one copy by 10:00 AM the next working day after each day that work is performed and for every seven consecutive calendar days of no-work.
b. Contractor Production Report: Submit the report electronically by 10:00
AM the next working day after each day that work is performed and for every seven consecutive calendar days of no-work.
c. Preparatory Phase Checklist: Submit the report electronically in the same manner as the CQC Report for each Preparatory Phase held.
d. Initial Phase Checklist: Submit the report electronically in the same manner as the CQC Report for each Initial Phase held.
f. Field Test Reports: Within two working days after the test is performed, submit the report as an electronic attachment to the CQC Report.
g. Monthly Summary Report of Tests: Submit the report as an electronic attachment to the CQC Report at the end of each month.
h. Testing Plan and Log: Submit the report as an electronic attachment to the CQC Report, at the end of each month. Provide a copy of the final Testing Plan and Log to the OMSI preparer for inclusion into the OMSI documentation.
i. Rework Items List: Submit lists containing new entries daily, in the same manner as the CQC Report.
j. CQC Meeting Minutes: Within two working days after the meeting is held, submit the report as an electronic attachment to the CQC Report.
k. QC Certifications: As required by the paragraph entitled "QC
SECTION 01 45 00.00 20 Page 5
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704
Certifications."
1.4 QC PROGRAM REQUIREMENTS
Establish and maintain a QC program as described in this section. This QC program is a key element in meeting the objectives of NAVFAC Commissioning.
The QC program consists of a QC Organization, QC Plan, QC Plan Meeting(s), a Coordination and Mutual Understanding Meeting, QC meetings, three phases of control, submittal review and approval, testing, completion inspections, QC certifications, and documentation necessary to provide materials, equipment, workmanship, fabrication, construction and operations which comply with the requirements of this Contract. The QC program must cover on-site and off-site work and be keyed to the work sequence. No construction work or testing may be performed unless the QC Manager is on the work site. The QC Manager must report to an officer of the firm and not be subordinate to the Project Superintendent or the Project Manager.
The QC Manager, Project Superintendent and Project Manager must work together effectively. Although the QC Manager is the primary individual responsible for quality control, all individuals will be held responsible for the quality of work on the job.
1.4.1 Preliminary Construction Work Authorized Prior to Acceptance
The only construction work that is authorized to proceed prior to the acceptance of the QC Plan is mobilization of storage and office trailers, temporary utilities, and surveying.
1.4.2 Notification of Changes
Notify the Contracting Officer, in writing, of any proposed changes in the QC Plan or changes to the QC organization personnel, a minimum of 10 work days prior to a proposed change. Proposed changes are subject to acceptance by the Contracting Officer.
1.5 QC ORGANIZATION
1.5.1 QC Manager
1.5.1.1 Duties
Provide a QC Manager at the work site to implement and manage the QC program. In addition to implementing and managing the QC program, the QC Manager may perform the duties of Project Superintendent. The QC Manager is required to attend the partnering meetings, QC Plan Meetings, Coordination and Mutual Understanding Meeting, conduct the QC meetings, perform the three phases of control except for those phases of control designated to be performed by QC Specialists, perform submittal review and approval, ensure testing is performed and provide QC certifications and documentation required in this Contract. The QC Manager is responsible for managing and coordinating the three phases of control and documentation performed by the QC Specialists, testing laboratory personnel and any other inspection and testing personnel required by this Contract. The QC Manager is the manager of all QC activities.
1.5.1.2 Qualifications
An individual with a minimum of 5 years combined experience in the following positions: Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction contracts which included the major trades that are part of
SECTION 01 45 00.00 20 Page 6
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704 this Contract. The individual must have at least two years experience as a QC Manager. The individual must be familiar with the requirements of EM 385-1-1, and have experience in the areas of hazard identification, safety compliance, and sustainability.
1.5.2 Construction Quality Management Training
In addition to the above experience and education requirements, the QC Manager must have completed the course entitled "Construction Quality Management (CQM) for Contractors." If the QC Manager does not have a current certification, they must obtain the CQM for Contractors course certification within 90 days of award. This course is periodically offered by the Naval Facilities Engineering Command and the Army Corps of Engineers. Contact the Contracting Officer for information on the next scheduled class.
1.5.3 Alternate QC Manager Duties and Qualifications
Designate an alternate for the QC Manager at the work site to serve in the event of the designated QC Manager's absence. The period of absence may not exceed two weeks at one time, and not more than 30 workdays during a calendar year. The qualification requirements for the Alternate QC Manager must be the same as for the QC Manager.
1.6 QUALITY CONTROL (QC) PLAN
1.6.1 Construction Quality Control (QC) Plan
1.6.1.1 Requirements
Provide, for acceptance by the Contracting Officer, a Construction QC Plan submitted in a three-ring binder that includes a table of contents, with major sections identified with tabs, with pages numbered sequentially, and that documents the proposed methods and responsibilities for accomplishing quality control commissioning activities during the construction of the
SECTION 01 45 00.00 20 Page 7
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704 project:
a. QC ORGANIZATION: A chart showing the QC organizational structure.
b. NAMES AND QUALIFICATIONS: Names and qualifications, in resume format, for each person in the QC organization. Include the CQM for Contractors course certifications for the QC Manager and Alternate QC Manager as required by the paragraphs entitled "Construction Quality Management Training" and "Alternate QC Manager Duties and Qualifications".
c. DUTIES, RESPONSIBILITY AND AUTHORITY OF QC PERSONNEL: Duties, responsibilities, and authorities of each person in the QC organization.
d. OUTSIDE ORGANIZATIONS: A listing of outside organizations, such as architectural and consulting engineering firms, that will be employed by the Contractor and a description of the services these firms will provide.
e. APPOINTMENT LETTERS: Letters signed by an officer of the firm appointing the QC Manager and Alternate QC Manager and stating that they are responsible for implementing and managing the QC program as described in this Contract. Include in this letter the responsibility of the QC Manager and Alternate QC Manager to implement and manage the three phases of control, and their authority to stop work which is not in compliance with the Contract. Letters of direction are to be issued by the QC Manager to the Assistant QC Manager and all other QC Specialists outlining their duties, authorities, and responsibilities.
Include copies of the letters in the QC Plan.
f. SUBMITTAL PROCEDURES AND INITIAL SUBMITTAL REGISTER: Procedures for reviewing, approving, and managing submittals. Provide the name(s) of the person(s) in the QC organization authorized to review and certify submittals prior to approval. Provide the initial submittal of the Submittal Register as specified in Section 01 33 00 SUBMITTAL
PROCEDURES.
g. TESTING LABORATORY INFORMATION: Testing laboratory information required by the paragraphs entitled "Accreditation Requirements", as applicable.
h. TESTING PLAN AND LOG: A Testing Plan and Log that includes the tests required, referenced by the specification paragraph number requiring the test, the frequency, and the person responsible for each test. Use Government forms to log and track tests.
i. PROCEDURES TO COMPLETE REWORK ITEMS: Procedures to identify, record, track, and complete rework items. Use Government forms to record and track rework items.
j. DOCUMENTATION PROCEDURES: Use Government form.
k. LIST OF DEFINABLE FEATURES: A Definable Feature of Work (DFOW) is a task that is separate and distinct from other tasks and has control requirements and work crews unique to that task. A DFOW is identified by different trades or disciplines and is an item or activity on the construction schedule. Include in the list of DFOWs, but not be limited to, all critical path activities on the NAS. Include all activities for which this specification requires QC Specialists or
SECTION 01 45 00.00 20 Page 8
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704 specialty inspection personnel. Provide separate DFOWs in the Network Analysis Schedule for each design development stage and submittal package.
l. PROCEDURES FOR PERFORMING THE THREE PHASES OF CONTROL: Identify procedures used to ensure the three phases of control to manage the quality on this project. For each DFOW, a Preparatory and Initial phase checklist will be filled out during the Preparatory and Initial phase meetings. Conduct the Preparatory and Initial Phases and meetings with a view towards obtaining quality construction by planning ahead and identifying potential problems for each DFOW.
m. PERSONNEL MATRIX: Not Applicable
n. PROCEDURES FOR COMPLETION INSPECTION: Not Applicable
o. TRAINING PROCEDURES AND TRAINING LOG: Not Applicable
p. ORGANIZATION AND PERSONNEL CERTIFICATIONS LOG: Procedures for coordinating, tracking and documenting all certifications on subcontractors, testing laboratories, suppliers, personnel, etc. QC Manager will ensure that certifications are current, appropriate for the work being performed, and will not lapse during any period of the contract that the work is being performed.
1.7 COORDINATION AND MUTUAL UNDERSTANDING MEETING
After submission of the QC Plan, and prior to Government approval and the start of construction, the QC Manager will meet with the Contracting Officer to present the QC program required by this Contract. When a new QC Manager is appointed, the coordination and mutual understanding meeting must be repeated.
1.7.1 Purpose
The purpose of this meeting is to develop a mutual understanding of the QC details, including documentation, administration for on-site and off-site work, design intent, Cx, environmental requirements and procedures, coordination of activities to be performed, and the coordination of the Contractor's management, production, and QC personnel. At the meeting, the Contractor will be required to explain in detail how three phases of control will be implemented for each DFOW, as well as how each DFOW will be affected by each management plan or requirement as listed below:
a. Waste Management Plan.
b. IAQ Management Plan.
c. Procedures for noise and acoustics management.
d. Environmental Protection Plan.
e. Environmental regulatory requirements.
f. Cx Plan.
SECTION 01 45 00.00 20 Page 9
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704
1.7.2 Coordination of Activities
Coordinate activities included in various sections to assure efficient and orderly installation of each component. Coordinate operations included under different sections that are dependent on each other for proper installation and operation. Schedule construction operations with consideration for indoor air quality as specified in the IAQ Management Plan. Coordinate prefunctional tests and startup testing with Cx.
1.7.3 Attendees
As a minimum, the Contractor's personnel required to attend include an officer of the firm, the Project Manager, Project Superintendent, QC Manager, Alternate QC Manager, CA, Environmental Manager, and subcontractor representatives. Each subcontractor who will be assigned QC responsibilities must have a principal of the firm at the meeting. Minutes of the meeting will be prepared by the QC Manager and signed by the Contractor and the Contracting Officer. Provide a copy of the signed minutes to all attendees.
1.8 QC MEETINGS
After the start of construction, conduct weekly QC meetings once every two weeks by the QC Manager at the work site with the Project Superintendent.
The CA, and the foremen who are performing the work of the DFOWs. The QC Manager is to prepare the minutes of the meeting and provide a copy to the Contracting Officer within two working days after the meeting. The Contracting Officer may attend these meetings. As a minimum, accomplish the following at each meeting:
a. Review the minutes of the previous meeting.
b. Review the schedule and the status of work and rework.
c. Review the status of submittals.
d. Review the work to be accomplished in the next two weeks and documentation required.
e. Resolve QC and production problems (RFI, etc.).
f. Address items that may require revising the QC Plan.
g. Review Accident Prevention Plan (APP).
h. Review environmental requirements and procedures.
i. Review Waste Management Plan.
j. Review IAQ Management Plan.
k. Review Environmental Management Plan.
l. Review the status of training completion.
m. Review Cx Plan and progress.
SECTION 01 45 00.00 20 Page 10
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704
1.9 DESIGN REVIEW AND DOCUMENTATION
1.9.1 Basis of Design and Design Intent
Review the basis of design received from the Contracting Officer and the design intent.
1.9.2 Design Review
Review design documents to verify that each commissioned system meets the design intent relative to functionality, energy performance, water performance, maintainability, sustainability, system cost, indoor environmental quality, and local environmental impacts. Fully document design review in written report.
1.9.3 Contract Document Review
Review the Contract documents to verify that Cx is adequately specified, and that each commissioned system is likely to meet the design intent relative to functionality, energy performance, water performance, maintainability, sustainability, system cost, indoor environmental quality, and local environmental impacts. Fully document contract document review in written report.
1.10 THREE PHASES OF CONTROL
Adequately cover both on-site and off-site work with the Three Phases of Control and include the following for each DFOW.
1.10.1 Preparatory Phase
Notify the Contracting Officer at least two work days in advance of each preparatory phase meeting. The meeting will be conducted by the QC Manager and attended by the QC Specialists, the Project Superintendent, the CA, and the foreman responsible for the DFOW. When the DFOW will be accomplished by a subcontractor, that subcontractor's foreman must attend the preparatory phase meeting. Document the results of the preparatory phase actions in the daily Contractor Quality Control Report and in the Preparatory Phase Checklist. Perform the following prior to beginning work on each DFOW:
a. Review each paragraph of the applicable specification sections.
b. Review the Contract drawings.
c. Verify that field measurements are as indicated on construction and/or shop drawings before confirming product orders, in order to minimize waste due to excessive materials.
d. Verify that appropriate shop drawings and submittals for materials and equipment have been submitted and approved. Verify receipt of approved factory test results, when required.
e. Review the testing plan and ensure that provisions have been made to provide the required QC testing.
f. Examine the work area to ensure that the required preliminary work has been completed.
SECTION 01 45 00.00 20 Page 11
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704
g. Coordinate the schedule of product delivery to designated prepared areas in order to minimize site storage time and potential damage to stored materials.
h. Arrange for the return of shipping/packaging materials, such as wood pallets, where economically feasible.
i. Examine the required materials, equipment and sample work to ensure that they are on hand and conform to the approved shop drawings and submitted data and are properly stored.
j. Discuss specific controls used and construction methods, construction tolerances, workmanship standards, and the approach that will be used to provide quality construction by planning ahead and identifying potential problems for each DFOW.
k. Review the APP and appropriate Activity Hazard Analysis (AHA) to ensure that applicable safety requirements are met, and that required Material Safety Data Sheets (MSDS) are submitted.
l. Review the Cx Plan and ensure all preliminary work items have been completed and documented.
1.10.2 Initial Phase
Notify the Contracting Officer at least two work days in advance of each initial phase. When construction crews are ready to start work on a DFOW, conduct the initial phase with the QC Specialists, the Project Superintendent, and the foreman responsible for that DFOW. Observe the initial segment of the DFOW to ensure that the work complies with Contract requirements. Document the results of the initial phase in the daily CQC Report and in the Initial Phase Checklist. Repeat the initial phase for each new crew to work on-site, or when acceptable levels of specified quality are not being met. Perform the following for each DFOW:
a. Establish level of workmanship and verify that it meets the minimum acceptable workmanship standards. Compare with required sample panels as appropriate.
b. Resolve any workmanship issues.
c. Ensure that testing is performed by the approved laboratory.
d. Check work procedures for compliance with the APP and the appropriate
AHA to ensure that applicable safety requirements are met.
e. Review project specific work plans (i.e. Cx, HAZMAT Abeatement, Stormwater Management) to ensure all preparatory work items have been completed and documented.
1.10.3 Follow-Up Phase
Perform the following for on-going work daily, or more frequently as necessary, until the completion of each DFOW and document in the daily CQC Report:
a. Ensure the work is in compliance with Contract requirements.
SECTION 01 45 00.00 20 Page 12
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704
b. Maintain the quality of workmanship required.
c. Ensure that testing is performed by the approved laboratory.
d. Ensure that rework items are being corrected.
e. Assure manufacturers representatives have performed necessary inspections if required and perform safety inspections.
f. Review the Cx Plan and ensure all work items, testing, and documentation has been completed.
1.10.4 Additional Preparatory and Initial Phases
Conduct additional preparatory and initial phases on the same DFOW if the quality of on-going work is unacceptable, if there are changes in the applicable QC organization, if there are changes in the on-site production supervision or work crew, if work on a DFOW is resumed after substantial period of inactivity, or if other problems develop.
1.10.5 Notification of Three Phases of Control for Off-Site Work
Notify the Contracting Officer at least two weeks prior to the start of the preparatory and initial phases.
1.11 SUBMITTAL REVIEW AND APPROVAL
Procedures for submission, review and approval of submittals are described in Section 01 33 00 SUBMITTAL PROCEDURES.
1.12 TESTING
Except as stated otherwise in the specification sections, perform sampling and testing required under this Contract.
1.12.1 Accreditation Requirements
Construction materials testing laboratories must be accredited by a laboratory accreditation authority and will be required to submit a copy of the Certificate of Accreditation and Scope of Accreditation. The laboratory's scope of accreditation must include the appropriate ASTM standards (E 329, C 1077, D 3666, D 3740, A 880, E 543) listed in the technical sections of the specifications. Laboratories engaged in Hazardous Materials Testing must meet the requirements of OSHA and EPA.
The policy applies to the specific laboratory performing the actual testing, not just the Corporate Office.
1.12.2 Laboratory Accreditation Authorities
Laboratory Accreditation Authorities include the National Voluntary Laboratory Accreditation Program (NVLAP) administered by the National Institute of Standards and Technology at http://ts.nist.gov/ts/htdocs/210/214/214.htm , the American Association of State Highway and Transportation Officials (AASHTO) program at http://www.amrl.net/amrlsitefinity/default/aap.aspx , International Accreditation Services, Inc. (IAS) at http://www.iasonline.org, U. S. Army Corps of Engineers Materials Testing Center (MTC) at
SECTION 01 45 00.00 20 Page 13
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704 http://gsl.erdc.usace.army.mil/SL/MTC/, the American Association for Laboratory Accreditation (A2LA) program at http://www.a2la.org/, the Washington Association of Building Officials (WABO) at http://www.wabo.org/ (Approval authority for WABO is limited to projects within Washington
State), and the Washington Area Council of Engineering Laboratories (WACEL) at http://wacel.org/fmi/xsl/wacel/index.xsl (Approval authority by WACEL is limited to projects within Facilities Engineering Command (FEC) Washington geographical area).
1.12.3 Capability Check
The Contracting Officer retains the right to check laboratory equipment in the proposed laboratory and the laboratory technician's testing procedures, techniques, and other items pertinent to testing, for compliance with the standards set forth in this Contract.
1.12.4 Test Results
Cite applicable Contract requirements, tests or analytical procedures used. Provide actual results and include a statement that the item tested or analyzed conforms or fails to conform to specified requirements. If the item fails to conform, notify the Contracting Officer immediately.
Conspicuously stamp the cover sheet for each report in large red letters "CONFORMS" or "DOES NOT CONFORM" to the specification requirements, whichever is applicable. Test results must be signed by a testing laboratory representative authorized to sign certified test reports.
Furnish the signed reports, certifications, and other documentation to the Contracting Officer via the QC Manager. Furnish a summary report of field tests at the end of each month, in accordance with paragraph INFORMATION
FOR THE CONTRACTING OFFICER.
1.12.5 Test Reports and Monthly Summary Report of Tests
Furnish the signed reports, certifications, and a summary report of field tests at the end of each month to the Contracting Officer. Attach a copy of the summary report to the last daily Contractor Quality Control Report of each month. Provide a copy of the signed test reports and certifications to the OMSI preparer for inclusion into the OMSI
1.13 QC CERTIFICATIONS
1.13.1 CQC Report Certification
Contain the following statement within the CQC Report: "On behalf of the Contractor, I certify that this report is complete and correct and equipment and material used and work performed during this reporting period is in compliance with the contract drawings and specifications to the best of my knowledge, except as noted in this report."
1.13.2 Invoice Certification
Furnish a certificate to the Contracting Officer with each payment request, signed by the QC Manager, attesting that as-built drawings are current, coordinated and attesting that the work for which payment is requested, including stored material, is in compliance with Contract requirements.
SECTION 01 45 00.00 20 Page 14
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704
1.13.3 Completion Certification
Upon completion of work under this Contract, the QC Manager must furnish a certificate to the Contracting Officer attesting that "the work has been completed, inspected, tested and is in compliance with the Contract."
Provide a copy of this final QC Certification for completion to the OMSI preparer for inclusion into the OMSI documentation.
1.14 COMPLETION INSPECTIONS
1.14.1 Punch-Out Inspection
Near the completion of all work or any increment thereof, established by a completion time stated in the Contract Clause entitled "Commencement, Prosecution, and Completion of Work," or stated elsewhere in the specifications, the QC Manager and the CA must conduct an inspection of the work and develop a "punch list" of items which do not conform to the approved drawings, specifications and Contract. Include in the punch list any remaining items on the "Rework Items List", which were not corrected prior to the Punch-Out Inspection. Include within the punch list the estimated date by which the deficiencies will be corrected. Provide a copy of the punch list to the Contracting Officer. The QC Manager, or staff, must make follow-on inspections to ascertain that all deficiencies have been corrected. Once this is accomplished, notify the Government that the facility is ready for the Government "Pre-Final Inspection".
1.14.2 Pre-Final Inspection
The Government and QCM will perform this inspection to verify that the facility is complete and ready to be occupied. A Government "Pre-Final Punch List" will be documented by the CQM as a result of this inspection.
The QC Manager will ensure that all items on this list are corrected prior to notifying the Government that a "Final" inspection with the Client can be scheduled. Any items noted on the "Pre-Final" inspection must be corrected in a timely manner and be accomplished before the contract completion date for the work, or any particular increment thereof, if the project is divided into increments by separate completion dates.
1.14.3 Final Acceptance Inspection
Notify the Contracting Officer at least 14 calendar days prior to the date a final acceptance inspection can be held. State within the notice that all items previously identified on the pre-final punch list will be corrected and acceptable, along with any other unfinished Contract work, by the date of the final acceptance inspection. The Contractor must be represented by the QC Manager, the Project Superintendent, the CA, and others deemed necessary. Attendees for the Government will include the Contracting Officer, other FEAD/ROICC personnel, and personnel representing the Client. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with the Contract Clause entitled "Inspection of Construction."
1.15 DOCUMENTATION
Maintain current and complete records of on-site and off-site QC program operations and activities.
SECTION 01 45 00.00 20 Page 15
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704
1.15.1 Construction Documentation
Reports are required for each day that work is performed and must be attached to the Contractor Quality Control Report prepared for the same day. Maintain current and complete records of on-site and off-site QC program operations and activities. The forms identified under the paragraph "INFORMATION FOR THE CONTRACTING OFFICER" will be used. Reports are required for each day work is performed. Account for each calendar day throughout the life of the Contract. Every space on the forms must be filled in. Use N/A if nothing can be reported in one of the spaces. The Project Superintendent and the QC Manager must prepare and sign the Contractor Production and CQC Reports, respectively. The reporting of work must be identified by terminology consistent with the construction schedule. In the "remarks" sections of the reports, enter pertinent information including directions received, problems encountered during construction, work progress and delays, conflicts or errors in the drawings or specifications, field changes, safety hazards encountered, instructions given and corrective actions taken, delays encountered and a record of visitors to the work site, quality control problem areas, deviations from the QC Plan, construction deficiencies encountered, meetings held. For each entry in the report(s), identify the Schedule Activity No. that is associated with the entered remark.
1.15.2 Quality Control Validation
Establish and maintain the following in a series of three ring binders.
Binders must be divided and tabbed as shown below. These binders must be readily available to the Contracting Officer during all business hours.
a. All completed Preparatory and Initial Phase Checklists, arranged by specification section.
b. All milestone inspections, arranged by Activity Number.
c. An up-to-date copy of the Testing Plan and Log with supporting field test reports, arranged by specification section.
d. Copies of all contract modifications, arranged in numerical order.
Also include documentation that modified work was accomplished.
e. An up-to-date copy of the Rework Items List.
f. Maintain up-to-date copies of all punch lists issued by the QC staff to the Contractor and Sub-Contractors and all punch lists issued by the Government.
g. Commissioning documentation including Cx checklists, schedules, tests, and reports.
1.15.3 Reports from the QC Specialist(s)
Reports are required for each day that work is performed in their area of responsibility. QC Specialist reports must include the same documentation requirements as the CQC Report for their area of responsibility. QC Specialist reports are to be prepared, signed and dated by the QC Specialists and must be attached to the CQC Report prepared for the same day.
SECTION 01 45 00.00 20 Page 16
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704
1.15.4 Testing Plan and Log
As tests are performed, the QC Manager will record on the "Testing Plan and Log" the date the test was performed and the date the test results were forwarded to the Contracting Officer. Attach a copy of the updated "Testing Plan and Log" to the last daily CQC Report of each month, per the paragraph "INFORMATION FOR THE CONTRACTING OFFICER".
Provide a copy of the final "Testing Plan and Log" to the OMSI preparer for inclusion into the OMSI
1.15.5 Rework Items List
The QC Manager must maintain a list of work that does not comply with the Contract, identifying what items need to be reworked, the date the item was originally discovered, the date the item will be corrected by, and the date the item was corrected. There is no requirement to report a rework item that is corrected the same day it is discovered. Attach a copy of the "Rework Items List" to the last daily CQC Report of each month. The Contractor is responsible for including those items identified by the Contracting Officer.
1.15.6 As-Built Drawings
The QC Manager is required to ensure the as-built drawings, required by Section 01 78 00 CLOSEOUT SUBMITTALS are kept current on a daily basis and marked to show deviations which have been made from the Contract drawings. Ensure each deviation has been identified with the appropriate modifying documentation (e.g. PC No., Modification No., Request for Information No., etc.). The QC Manager or QC Specialist assigned to an area of responsibility must initial each revision. Upon completion of work, the QC Manager will furnish a certificate attesting to the accuracy of the as-built drawings prior to submission to the Contracting Officer.
1.16 NOTIFICATION ON NON-COMPLIANCE
The Contracting Officer will notify the Contractor of any detected non-compliance with the Contract. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, is deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time for excess costs or damages by the Contractor.
SECTION 01 45 00.00 20 Page 17
Magazine & Inert Building Maintenance & Repair Contract N40085‐19‐R‐7704
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 PREPARATION
Designate receiving/storage areas for incoming material to be delivered according to installation schedule and to be placed convenient to work area in order to minimize waste due to excessive materials handling and misapplication. Store and handle materials in a manner as to prevent loss from weather and other damage. Keep materials, products, and accessories covered and off the ground, and store in a dry, secure area.
Prevent contact with material that may cause corrosion, discoloration, or staining. Protect all materials and installations from damage by the activities of other trades.
-- End of Section --