PPI#
Section of RFP or Page Number
Paragraph Reference Drawing Number Question Response
1 Page 9 and 11 of 79.
Factor 1 Construction and Design Experience
N/A
The RFP stipulates that for projects to be considered relevant that they must be completed within the past 5 years. It also states that solely horizontal or civil projects will NOT be considered. In light of the fact that this is a Small Business set-a-side contract with a unique civil component (seawall repair) would the government reconsider the time frame to include the past 7 years so that Small business offerors can submit their most relevant qualifying projects for consideration.
Seven (7 ) years is acceptable for both design and construction (See Amendment 0003 for changes).
Specifications
p. 34 of 547
Will US Harbor & Longshoreman insurance be required? The insurance requirements are identified in the Project Specifications document (Item 1.4, Pgs 34 & 35). Any coverage requirements in excess of what is stated, will be identified with the issuance of individual task orders.
Specifications
p. 34 of 547
Will pollution liability insurance be required? See response above.
Specifications
p. 34 of 547
Will builder’s risk insurance be required? See response above.
Solicitation Number: N40085-16-R-3034
PRE-PROPOSAL INQUIRY (PPI) - AMENDMENT 0003
Sheet1