GSA Williams Building 10606BLDG
Section 02 82 16 Page 1
SECTION 02 82 16
ASBESTOS ABATEMENT
07/16
PART 1 GENERAL
Work outlined in this Section includes all work necessary for the removal and disposal of asbestos-containing materials (ACM) impacted during renovation/waterproofing and associated caulking abatement activities associated with the building. This work includes, but is not limited to, the removal and disposal of moisture barrier coating, caulking, and black floor expansion mastic and pressed board. The Contractor shall assume there is 1000 square feet of asbestos containing material within the abandoned coal vault that will need to be removed and properly disposed of.
It is suspected that the coal vault may have areas of Asbestos Containing Material (ACM) used to caulk joints in the walls and floor of the coal vault. It is the Government's intent to complete sampling and testing once the top of the structure is removed to determine appropriate handling and disposal if present. Work shall be sequenced to allow the Government to complete the sampling, testing and determination of appropriate follow on actions. It is estimated that this process will take 14 days (Amendment #1).
The Contractor shall be solely responsible for conducting this project and supervising all work in a manner that will be in conformance with all federal, state, and local regulations and guidelines pertaining to asbestos abatement.
1.1 RELATED DOCUMENTS
Refer to Appendix B "Hazardous Building Materials Assessment and Survey, Captain John Foster Williams U.S. Coast Guard Building, Boston, Massachusetts" prepared by GEI Consultants, Inc. dated May 17, 2016.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN INDUSTRIAL HYGIENE ASSOCIATION (AIHA)
AIHA Z88.6 (2006) Respiratory Protection - Respirator
Use-Physical Qualifications for Personnel
AMERICAN SOCIETY OF SANITARY ENGINEERING (ASSE)
ASSE Z9.2 (2012) Fundamentals Governing the Design and
Operation of Local Exhaust Ventilation Systems
ASTM INTERNATIONAL (ASTM)
PROPERTY OF THE UNITED STATES GOVERNMENT - FOR OFFICIAL USE ONLY - DO NOT REMOVE THIS NOTICE -
PROPERLY DESTROY DOCUMENTS WHEN NO LONGER NEEDED
Section 02 82 16 Page 2
ASTM C732 (2006; R 2012) Aging Effects of Artificial Weathering on Latex Sealants
ASTM D2794 (1993; R 2010) Resistance of Organic Coatings to the Effects of Rapid Deformation (Impact)
ASTM D522/D522M (2014) Mandrel Bend Test of Attached Organic
Coatings
ASTM E119 (2014) Standard Test Methods for Fire Tests of Building Construction and Materials
ASTM E1368 (2014) Visual Inspection of Asbestos
Abatement Projects
ASTM E736 (2000; R 2011) Cohesion/Adhesion of Sprayed
Fire-Resistive Materials Applied to Structural Members
ASTM E84 (2015b) Standard Test Method for Surface
Burning Characteristics of Building Materials
ASTM E96/E96M (2014) Standard Test Methods for Water Vapor
Transmission of Materials
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 560/5-85-024 (1985) Guidance for Controlling Asbestos-
Containing Materials in Buildings (Purple Book)
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1926.103 Respiratory Protection
29 CFR 1910.1001 Occupational Safety and Health Standards, Asbestos
29 CFR 1926.1101 Asbestos
29 CFR 1926.200 Accident Prevention Signs and Tags
29 CFR 1926.51 Sanitation
29 CFR 1926.59 Hazard Communication
40 CFR 61-SUBPART A General Provisions
40 CFR 61-SUBPART M National Emission Standard for Asbestos
40 CFR 763 Asbestos
UNDERWRITERS LABORATORIES (UL)
UL 586 (2009; Reprint Sep 2014) Standard for High-
Efficiency Particulate, Air Filter Units
Section 02 82 16 Page 3
MASSACHUSETTS DEPARTMENT OF ENVIRONMENTAL PROTECTION
310 CMR 19.000 Massachusetts Department of Environmental
Protection Solid Waste Management
APPENDIX B "Hazardous Building Materials Assessment and Survey Captain John Foster Williams U.S. Coast Guard Building, Boston, Massachusetts", dated May 2016, prepared by GEI Consultants, Inc.
TAppendix B is provided as a separate document in the contract documents.
If the appendix is missing from the contract documents notify the Contracting Officer.
1.3 DEFINITIONS
1.3.1 Abatement
Procedures to control fiber release from asbestos-containing materials;
includes removal, encapsulation, and enclosure.
1.3.2 ACM
Asbestos Containing Materials.
1.3.3 Air Monitoring
The process of measuring the fiber concentration of an area or of a person.
1.3.4 Amended Water
Water containing a wetting agent or surfactant with a maximum surface tension of 0.00042 psi.
1.3.5 Area Sampling
Sampling of asbestos fiber concentrations which approximates the concentrations of asbestos in the theoretical breathing zone but is not actually collected in the breathing zone of an employee.
1.3.6 Asbestos
The name given to a number of naturally occurring fibrous silicates. This includes the serpentine forms and the amphiboles and includes chrysotile, amosite, crocidolite, tremolite, anthophyllite, and actinolite, or any of these forms, which have been chemically altered.
1.3.7 Asbestos Control Area
The area where asbestos removal operations are performed which is isolated by physical boundaries which assist in the prevention of the uncontrolled release of asbestos dust, fibers, or debris. The regulated area shall comply with requirements of regulated area for demarcation, access, respirators, prohibited activities, competent persons and exposure assessments and monitoring.
Section 02 82 16 Page 4
1.3.8 Asbestos Fibers
Those fibers having an aspect ratio of at least 3:1 and longer than 5 micrometers as determined by National Institute for Occupational Safety and Health (NIOSH) Method 7400.
1.3.9 Asbestos Permissible Exposure Limit (PEL)
The maximum airborne concentration of asbestos fibers to which an employee is allowed to be exposed. 0.1 fibers per cubic centimeter of air as an 8-hour time weighted average and 1.0 fibers /cc averaged over a sampling period of 30 minutes as an Excursion Limit as defined by 29 CFR 1926.1101.
The Contractor is responsible for maintaining work areas in a manner that this standard is not exceeded.
1.3.10 Background
The ambient airborne asbestos concentration in an uncontaminated area as measured prior to any asbestos hazard abatement efforts. Background concentrations for other (contaminated) areas are measured in similar but asbestos free locations.
1.3.11 Caulking
Resilient mastic compound often having a silicone bituminous or rubber base;
used to seal cracks, fill joints, and prevent leakage. Typical applications:
around windows, and doors. Caulking is at joints between two dissimilar materials (i.e. Masonry to wood, masonry to steel)
1.3.12 Clean Room
An uncontaminated area or room, which is a part of the worker decontamination enclosure with provisions for storage of workers' street clothes and protective equipment.
1.3.13 Clearance Sampling
Final air sampling performed aggressively after the completion of the abatement project in a regulated area. Air samples collected by the air sampling professional having a fiber concentration of less than 0.01 fibers/cc of air in each of five samples collected inside the containment will denote acceptable clearance sampling by Phase Contrast Microscopy
(PCM).
or Five air samples collected inside the containment by the air sampling professional having an average asbestos concentration of less than 70 structures per square millimeter of air will denote acceptable clearance sampling for Transmission Electron Microscopy.
1.3.14 Competent Person
A person meeting the requirements for competent person as specified in 29 CFR 1926.1101 including a person capable of identifying existing asbestos hazards in the workplace and selecting the appropriate control strategy for asbestos exposure, who has the authority to take prompt corrective measures to eliminate them, and is specifically trained in a training course which
Section 02 82 16 Page 5 meet the criteria of EPA's Model Accreditation Plan (40 CFR 763) for project designer or supervisor, or its equivalent.
1.3.15 Decontamination Enclosure System
A series of connected areas, with curtained doorways between any two adjacent areas, for the decontamination of workers and equipment. A decontamination enclosure system always contains at least one airlock and is adjacent and connected to the regulated area, where possible.
1.3.16 Encapsulation
The abatement of an asbestos hazard through the appropriate use of chemical encapsulants.
1.3.17 Encapsulants
Specific materials in various forms used to chemically or physically entrap asbestos fibers in various configurations to prevent these fibers from becoming airborne. There are four types of encapsulants as follows which must comply with performance requirements as specified herein.
a. Removal Encapsulant (can be used as a wetting agent)
b. Bridging Encapsulant (used to provide a tough, durable surface coating to asbestos containing material)
c. Penetrating Encapsulant (used to penetrate the asbestos containing material encapsulating all asbestos fibers and preventing fiber release due to routine mechanical damage)
d. Lock-Down Encapsulant (used to seal off or "lock-down" minute asbestos fibers left on surfaces from which asbestos containing material has been removed).
1.3.18 Friable Asbestos Material
One percent asbestos containing material that can be crumbled, pulverized, or reduced to powder by hand pressure when dry.
1.3.19 HEPA Filter Equipment
High efficiency particulate air (HEPA) filtered vacuum and/or exhaust ventilation equipment with a filter system capable of collecting and retaining asbestos fibers. Filters shall retain 99.97 percent of particles
0.3 microns or larger as indicated in UL 586.
1.3.20 Government Consultant (GC)
That qualified person employed directly by the Government to monitor, sample, inspect the work or in some other way advise the Contracting Officer. The GC is normally a private consultant, but can be an employee of the Government.
1.3.21 Negative Pressure Enclosure (NPE)
Section 02 82 16 Page 6
That engineering control technique described as a negative pressure enclosure in 29 CFR 1926.1101.
1.3.22 Personal Sampling
Air sampling which is performed to determine asbestos fiber concentrations within the breathing zone of a specific employee, as performed in accordance with 29 CFR 1926.1101.
1.3.23 Project Monitor
A professional capable of conducting air monitoring and analysis of schemes.
This individual should be an industrial hygienist, an environmental scientist, or an engineer with experience in asbestos air monitoring and worker protection equipment and procedures. This individual should have demonstrated proficiency in conducting air sample collection in accordance with 29 CFR 1910.1001 and 29 CFR 1926.1101.
1.3.24 Private Qualified Person (PQP)
That qualified person hired by the Contractor to perform the herein listed tasks.
1.3.25 Qualified Person (QP)
A Registered Architect, Professional Engineer, Certified Industrial Hygienist, consultant or other qualified person who has successfully completed training and is therefore accredited under a legitimate State Model Accreditation Plan as described in 40 CFR 763 as a Building Inspector, Contractor/Supervisor Abatement Worker, and Asbestos Project Designer; and has successfully completed the National Institute of Occupational Safety and Health (NIOSH) 582 course "Sampling and Evaluating Airborne Asbestos Dust" or equivalent. The QP must be qualified to perform visual inspections as indicated in ASTM E1368.
1.3.26 Regulated Area
An area established by the employer to demarcate where Class I, II, and III asbestos work is conducted and any adjoining area where debris and waste from such asbestos work accumulate, and a control area within which airborne concentrations of asbestos exceed or there is a reasonable possibility that they may exceed the PEL.
1.3.27 Shower Room
A room between the clean room and the equipment room in the work decontamination enclosure with hot and cold running water and suitably arranged for employee showering during decontamination. The shower room is located in an airlock between the contaminated area and the clean area.
1.3.28 Waterproofing
Material, usually a membrane or applied compound (tar/mastic), used to make a surface impervious to water, includes concealed conditions (applications around doors, windows, and in wall cavities). Sometimes combined with felts.
Section 02 82 16 Page 7
1.3.29 Wetting Agent
A chemical added to water to reduce the water's surface tension thereby increasing the water's ability to soak into the material to which it is applied. An equivalent wetting agent must have a surface tension of at most
0.00042 psi.
1.4 REQUIREMENTS
1.4.1 Existing Conditions
It shall be incumbent upon the Contractor to visit the site and determine what exists, its condition, and what will be required to accomplish the Work intended by the Contract Documents.
Except for unforeseeable concealed conditions, as determined by the Contracting Officer, the Contractor shall make no claim for additional cost due to the existing conditions at the site.
1.4.2 Medical Requirements
Provide medical requirements including but not limited to medical surveillance and medical record keeping as listed in 29 CFR 1926.1101.
1.4.2.1 Medical Examinations
Before exposure to airborne asbestos fibers at or above the PEL, provide workers with a comprehensive medical examination as required by 29 CFR
1926.1101. In the absence of specific airborne fiber data provide medical examinations for all workers who will enter the control area for any reason.
In addition, provide an evaluation of the individual's ability to work in environments capable of producing heat stress in the worker. This requirement must be satisfied within the 12 months prior to the start of work on this contract.
Submit, at a minimum, for each worker the following:
a. Name and Social Security Number
b. Physicians Written Opinion from examining physician including at a minimum the following:
(1) Whether worker has any detected medical conditions that would place the worker at an increased risk of material health impairment from exposure to asbestos.
(2) Any recommended limitations on the worker or on the use of personal protective equipment such as respirators.
(3) Statement that the worker has been informed by the physician of the results of the medical examination and of any medical conditions that may result from asbestos exposure.
1.4.2.2 Medical Records
Maintain complete and accurate records of employees' medical examinations, medical records, and exposure data for a period of 50 years after termination of employment and make records of the required medical examinations and exposure data available for inspection and copying to: The Assistant Secretary of Labor for Occupational Safety and Health (OSHA), or
Section 02 82 16 Page 8 authorized representatives of them, and an employee's physician upon the request of the employee or former employee.
1.4.3 Employee Training
Submit certificates, prior to the start of work but after the main abatement submittal, signed by each employee indicating that the employee has received training in the proper handling of materials and wastes that contain asbestos in accordance with 40 CFR 763; understands the health implications and risks involved, including the illnesses possible from exposure to airborne asbestos fibers; understands the use and limits of the respiratory equipment to be used; and understands the results of monitoring of airborne quantities of asbestos as related to health and respiratory equipment as indicated in 29 CFR 1926.1101 on an initial and annual basis. Certificates shall be organized by individual worker, not grouped by type of certification.
Train all personnel involved in the asbestos control work in accordance with United States Environmental Protection Agency (USEPA) Asbestos Hazard Emergency Response Act (AHERA) training criteria or State training criteria whichever is more stringent. The Contractor shall document the training by providing: dates of training, training entity, course outline, names of instructors, and qualifications of instructors upon request by the Contracting Officer.
Furnish each employee with respirator training and fit testing administered by the PQP as required by 29 CFR 1926.1101. Fully cover engineering and other hazard control techniques and procedures.
1.4.4 Permits and Notifications
Obtain necessary permits in conjunction with asbestos removal, encapsulation, hauling, and disposition, and furnish notification of such actions required by Federal, State, regional, and local authorities prior to the start of work.
Notify the following in writing 20 working days prior to commencement of work in accordance with 40 CFR 61-SUBPART M:
a. MassDEP P.O. Box 4062 Boston, MA 02211
b. Electronic Filing: File the ANF-001 online via MassDEP's website.
https://edep.dep.mass.gov/DEPLogin.aspx
The minimum information included in the notification to the agency includes:
a. Name and address of the buildings the Owner/Operator(Government)
b. Building location
c. Building size, age, and use
d. Amount of friable asbestos
e. Work schedule, including proposed start and completion date
Section 02 82 16 Page 9
f. Asbestos removal procedures to be used
g. Name and location of disposal site for generated asbestos waste, residue, and debris
Notify the Contracting Officer and other appropriate Government agencies in writing 20 working days prior to the start of asbestos work as indicated in applicable laws, ordinances, criteria, rules, and regulations. Submit copies of all Notifications to the Contracting Officer.
The Contractor shall immediately notify the Contracting Officer of the delivery of all permits, licenses, certificates of inspection, of approval, or occupancy, and any other such instruments required under codes by authorities having jurisdiction, regardless of who issued them, and shall cause them to be displayed to the Contracting Officer for verification and recording.
1.4.5 Inspections
The Contractor shall allow the work of this contract to be inspected if required by local, state, federal, and any other authorities having jurisdiction over such work. The Contractor shall immediately notify the Contracting officer and shall maintain written evidence of such inspection for review by the Contracting Officer.
1.4.6 Environment, Safety and Health Compliance
In addition to detailed requirements of this specification, comply with those applicable laws, ordinances, criteria, rules, and regulations of Federal, State, regional, and local authorities regarding handling, storing, transporting, and disposing of asbestos waste materials. Comply with the applicable requirements of the current issue of 29 CFR 1926.1101, 40 CFR 61- SUBPART A, and 40 CFR 61-SUBPART M. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting the work. Where the requirements of this specification, applicable laws, rules, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirement as defined by the Government shall apply.
1.4.7 Respiratory Protection Program
Establish and implement a respirator program as required by AIHA Z88.6, 29 CFR 1926.1101, and 29 CFR 1926.103. Submit a written description of the program to the Contracting Officer. Submit a written program manual or operating procedure including methods of compliance with regulatory statutes.
1.4.7.1 Respirator Program Records
Submit records of the respirator program as required by AIHA Z88.6, 29 CFR 1926.103, and 29 CFR 1926.1101.
Submit statements that workers are able to wear and use the type of respiratory protection proposed for the project, and they are able to work safely in an environment capable of producing heat stress in the worker.
Submit copies of worker respirator fit test (less than 1 year old) for all
Section 02 82 16 Page 10 site personnel performing abatement. The Contracting Officer reserves the right to require that any employee be retested for respirator fitness when considered to be at risk of exposure to air ACM conditions.
1.4.8 Asbestos Abatement Supervisor
The Asbestos Abatement Contractor shall employ a competent Asbestos Abatement Supervisor with at least three (3) years of experience on projects of similar scope and magnitude who shall be responsible for all work involving asbestos abatement as described in the specifications and defined in applicable regulations, and have full time daily supervision of the same.
The Supervisor shall be the competent person as defined by 29 CFR 1926.1101.
1.4.9 Hazard Communication
Adhere to all parts of 29 CFR 1926.59 and provide the Contracting Officer with a copy of the Material Safety Data Sheets (MSDS) for all materials brought to the site.
1.4.10 Asbestos Hazard Abatement Plan
Submit a detailed plan of the safety precautions such as lockout, tagout, tryout, fall protection, and confined space entry procedures and equipment and work procedures to be used in the removal and demolition of materials containing asbestos. The plan, not to be combined with other hazard abatement plans, shall be prepared, signed, and sealed by the PQP. Provide a Table of Contents for each abatement submittal, which shall follow the sequence of requirements in the contract. Such plan shall include but not be limited to the precise personal protective equipment to be used including, but not limited to, respiratory protection, type of whole-body protection, the location of asbestos control areas including clean and dirty areas, buffer zones, showers, storage areas, change rooms, removal method, interface of trades involved in the construction, sequencing of asbestos related work, disposal plan, type of wetting agent and asbestos sealer to be used, locations of local exhaust equipment, planned air monitoring strategies, and a detailed description of the method to be employed in order to control environmental pollution. The plan shall also include (both fire and medical emergency) response plans. The Asbestos Hazard Abatement Plan must be approved in writing prior to starting any asbestos work. The Contractor, Asbestos Hazard Control Supervisor, and PQP shall meet with the Contracting Officer prior to beginning work, to discuss in detail the Asbestos Hazard Abatement Plan, including work procedures and safety precautions. Once approved by the Contracting Officer, the plan will be enforced as if an addition to the specification. Any changes required in the specification as a result of the plan shall be identified specifically in the plan to allow for free discussion and approval by the Contracting Officer prior to starting work.
1.4.11 Testing Laboratory
The Contractor shall submit the name, address, and qualifications of proposed laboratories and licensed project monitors intended to be utilized for sample analysis as required by this section.
The laboratory must be an approved accredited Department of Defense laboratory. The testing laboratory firm shall be independent of the
Section 02 82 16 Page 11 asbestos Contractor and shall have no employee or employer relationship which could constitute a conflict of interest.
PLM analysis will be done in accordance with the requirements of 40 CFR 763, Subpart F, Appendix A.
1.4.12 Landfill Approval
Submit written evidence that the landfill is for asbestos disposal by the U.S. Environmental Protection Agency, Region 3, Air Enforcement Section (38W12), and local regulatory agencies. Within 3 working days after delivery, submit detailed delivery tickets, prepared, signed, and dated by an agent of the landfill, certifying the amount of asbestos materials delivered to the landfill. Submit a copy of the waste shipment records within 1 day of the shipment leaving the project site.
1.4.13 Medical Certification
Provide a written certification for each worker and supervisor, signed by a licensed physician indicating that the worker and supervisor has met or exceeded all of the medical prerequisites listed herein and in 29 CFR
1926.1101 and 29 CFR 1926.103 as prescribed by law. Submit certificates prior to the start of work but after the main abatement submittal.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Hauling Contractor; G
Medical Examinations; G
Permits And Notifications; G
SD-03 Product Data
Local Exhaust Equipment; G
Vacuums; G
Respirators; G
Pressure Differential Automatic Recording Instrument; G
Amended Water; G
Material Safety Data Sheets (Msds) for all materials proposed for transport to the project site; G
Encapsulants; G
SD-06 Test Reports
Section 02 82 16 Page 12
Air Sampling Results; G
Pressure Differential Recordings For Local Exhaust System; G
Asbestos Disposal Quantity Report; G
Clearance Sampling; G
SD-07 Certificates
Asbestos Hazard Abatement Plan; G
Testing Laboratory; G
Private Qualified Person Documentation; G
Contractor's License; G
Competent Person documentation; G
Landfill Approval; G
Employee Training; G
Medical Certification requirements; G
Waste Shipment Records and if applicable exemption report; G
Respiratory Protection Program; G
Delivery Tickets; G
Vacuums; G
Water Filtration Equipment; G
Ventilation Systems; G
Other Equipment Used To Contain Airborne Asbestos Fibers; G
Chemical Encapsulants Sealers; G
Notifications
Show compliance with ASSE Z9.2 by providing manufacturers' certifications.
Air Sampling Professional; G
Asbestos Abatement Supervisor; G
Worker's Accreditation; G
SD-11 Closeout Submittals
Notifications; G
Section 02 82 16 Page 13
Respirator Program Records; G
Protective Clothing Decontamination Facility Notification; G
1.6 QUALITY ASSURANCE
1.6.1 Private Qualified Person Documentation
Submit the name, address, and telephone number of the Private Qualified Person (PQP) selected to prepare the Asbestos Hazard Abatement Plan, direct monitoring and training, and documented evidence that the PQP has successfully completed training in and is accredited and where required is certified as, a Building Inspector, Contractor/Supervisor Abatement Worker, and Asbestos Project Designer as described by 40 CFR 763 and has successfully completed the National Institute of Occupational Safety and Health (NIOSH) 582 course "Sampling and Evaluating Airborne Asbestos Dust" or equivalent. The PQP shall be appropriately licensed in the Commonwealth of Massachusetts as a Project Monitor. The PQP and the asbestos contractor shall not have an employee/employer relationship or financial relationship which could constitute a conflict of interest. The PQP shall be a first tier subcontractor.
1.6.2 Competent Person Documentation
Submit training certification and a current Commonwealth of Massachusetts Asbestos Contractor's and Supervisor's License.
1.6.3 Worker's Accreditation
Submit copies of certificates from an EPA-approved AHERA Abatement Workers course for each worker as evidence that each asbestos Abatement Worker is accredited as required by the AHERA Regulation 40 CFR 763 Appendix C to Subpart E, February 3, 1994.
1.6.4 Contractor's License
The Contractor is required to be certified and accredited as required by the State of Massachusetts Department of Labor & Standards. The Contractor must appear on the approved list of Asbestos Abatement contractors on file at the State of Massachusetts Department of Public Health and hold a valid license for asbestos abatement within the State of Massachusetts.
The Contractor shall submit a record of prior experience in asbestos abatement projects, listing no less than three (3) completed jobs in the past year, with all projects of similar size and scope. The Contractor shall list the experience and training of the project foremen and all on-site personnel. The information that should be included is as follows:
a. Project Name and Address
b. Government's Name and Address
c. Architect/Contracting officer
d. Contract Amount
e. Date of Completion
Section 02 82 16 Page 14
f. Extras and Changes
Submit a written statement regarding whether the Contractor has ever been found out-of-compliance with federal or state asbestos and/or lead regulations pertaining to worker protection, removal, transport, or disposal.
1.6.5 Air Sampling Professional
The Contractor shall independently retain an air sampling professional licensed by the Massachusetts Department of Labor & Standards to monitor airborne asbestos concentrations in the workers' breathing zone and to establish conditions and work procedures for maintaining compliance with 29 CFR 1910.1001 and 29 CFR 1926.1101.
1.6.6 Air Sampling Results
The Contractor's air sampling professional shall document all air sampling results and provide a report to the Contracting officer within 48 hours after sample collection. All air sampling shall be conducted in accordance with methods described in 29 CFR 1910.1001 and 29 CFR 1926.1101.
Complete fiber counting and provide results to the PQP and GC for review within 16 hours of the "time off" of the sample pump. Notify the Contracting Officer immediately of any airborne levels of asbestos fibers in excess of the acceptable limits. Submit sampling results to the Contracting Officer and the affected Contractor employees where required by law within 3 working days, signed by the testing laboratory employee performing air sampling, the employee that analyzed the sample, and the PQP. Notify the Contracting Officer immediately of any variance in the pressure differential which could cause adjacent unsealed areas to have asbestos fiber concentrations in excess of 0.01 fibers per cubic centimeter or background whichever is higher. In no circumstance shall levels exceed 0.1 fibers per cubic centimeter.
1.6.7 Pressure Differential Recordings for Local Exhaust System
Provide a local exhaust system that creates a negative pressure of at least
0.02 inches of water relative to the pressure external to the enclosure and operate it continuously, 24 hours a day, until the temporary enclosure of the asbestos control area is removed. Submit pressure differential recordings for each work day to the PQP and GC for review and to the Contracting Officer within 24 hours from the end of each work day.
1.6.8 Protective Clothing Decontamination Facility Notification
Submit written evidence that persons who decontaminate, store, or transport asbestos contaminated clothing used in the performance of this contract were duly notified in accordance with 29 CFR 1926.1101.
1.7 PRECONSTRUCTION SUBMITTALS
1.7.1 Hauling Contractor
Submit the identity of the hauling contractor, location of the landfill to be used and standards for proof of acceptance by the receiving facility.
Section 02 82 16 Page 15
1.7.2 Videos and Photographs
Submit a copy of videos (VHS or approved equal) and still photos (in ".jpg" format) showing the conditions of the building prior to the start of work.
The contractor will be held responsible for all damage to the building and its contents not shown in the still photo and video tape.
1.8 DELIVERY, STORAGE AND HANDLING
Deliver all materials in the original packages, containers, or bundles bearing the name of the manufacturer and the brand name and product technical description. Damaged or deteriorating materials shall not be used and shall be removed from the premises. Material that become contaminated with asbestos shall be decontaminated or disposed of as asbestos waste.
Impermeable containers are to be used to receive and retain any asbestos-containing or contaminated materials until disposal at an acceptable disposal site. The containers shall be labeled in accordance with OSHA Standard 29 CFR 1926.1101. Containers must be both air and watertight.
Labels and signs, as required by OSHA Standard 29 CFR 1926.1101, will be used.
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Polyethylene Sheet
Polyethylene sheet shall be in a roll size to minimize the frequency of joints and shall be delivered to the job site with factory label indicating 4 or 6 mil.
2.1.2 Polyethylene Disposable Bags
Polyethylene disposable bags shall be 6 mil with pertinent pre-printed label. Tie wraps for bags shall be plastic, 5-inches long (minimum), pointed and looped to secure filled plastic bags.
2.1.3 Tape or Adhesive Spray
Tape or adhesive spray will be capable of sealing joints in adjacent polyethylene sheets and for attachment of polyethylene sheet to finished or unfinished surfaces of dissimilar materials and capable of adhering under both dry and wet conditions, including use of amended water.
2.1.4 Surfactant (Wetting Agent)
Surfactant (wetting agent), shall consist of fifty percent polyoxyethylene ether and fifty percent polyoxyethylene ester, or equivalent, and shall be mixed with water to provide a concentration of 1 ounce surfactant to 5 gallons of water or as directed by manufacturer.
The Contractor shall have available spray equipment capable of mixing wetting agent with water and capable of generating sufficient pressure and volume and having sufficient hose length to reach all areas with asbestos.
Section 02 82 16 Page 16
2.1.5 Encapsulants
Shall conform to current USEPA requirements, shall contain no toxic or hazardous substances as defined in 29 CFR 1926.59, and shall conform to the following performance requirements.
2.1.5.1 Removal Encapsulants
Removal encapsulant shall be non-flammable factory prepared penetrating chemical encapsulant found acceptable to the Contracting officer. Usage shall be in accordance with manufacturer's printed technical data.
Requirement Test Standard
Flame Spread - 25, Smoke Emission - 50 ASTM E84
Life Expectancy - 20 years ASTM C732 Accelerated Aging Test
Permeability - Minimum 0.4 perms ASTM E96/E96M
Fire Resistance - Negligible affect on fire resistance rating over 3 hour test (Classified by UL for use over fibrous and cementitious sprayed fireproofing)
ASTM E119
Impact Resistance - Minimum 43 in/lb ASTM D2794 Gardner Impact Test
Flexibility - no rupture or cracking ASTM D522/D522M Mandrel Bend Test
2.1.5.2 Bridging Encapsulant
Flame Spread - 25, Smoke Emission - 50 ASTM E84
Life Expectancy - 20 years ASTM C732 Accelerated Aging Test
Permeability - Minimum 0.4 perms ASTM E96/E96M
Fire Resistance - Negligible affect on fire resistance rating over 3 hour test (Classified by UL for use over fibrous and cementitious sprayed fireproofing)
ASTM E119
Section 02 82 16 Page 17
2.1.5.3 Penetrating Encapsulant
Flame Spread - 25, Smoke Emission - 50 ASTM E84
Life Expectancy - 20 years ASTM C732 Accelerated Aging Test
Permeability - Minimum 0.4 perms ASTM E96/E96M
Cohesion/Adhesion Test - 50 pounds of force/foot
ASTM E119
Fire Resistance - Negligible affect on fire resistance rating over 3 hour test (Classified by UL for use over fibrous and cementitious sprayed fireproofing)
ASTM E119
2.1.5.4 Lock-down Encapsulant
Flame Spread - 25, Smoke Emission - 50 ASTM E84
Life Expectancy - 20 years ASTM C732 Accelerated Aging Test
Permeability - Minimum 0.4 perms ASTM E96/E96M
Section 02 82 16 Page 18
Fire Resistance - Negligible affect on fire resistance rating over 3 hour test (Tested with fireproofing over encapsulant applied directly to steel member)
ASTM E119
Bond Strength: 100 pounds of force/foot ASTM E736
(Tests compatibility with cementitious and fibrous fireproofing)
2.2 TOOLS AND EQUIPMENT
The Contractor shall provide all tools and equipment necessary for asbestos removal, encapsulation, and enclosure. The Contractor shall have available sufficient inventory or dated purchase orders for materials necessary for the job including protective clothing, respirators, filter cartridges, polyethylene sheeting of proper size and thickness, tape and air filters.
PART 3 EXECUTION
3.1 EQUIPMENT
At all times, provide the Contracting Officer or the Contracting Officer's Representative, with at least two complete sets of personal protective equipment as required for entry to and inspection of the asbestos control area. Provide equivalent training to the Contracting Officer or a designated representative as provided to Contractor employees in the use of the required personal protective equipment. Provide manufacturer's certificate of compliance for all equipment used to contain airborne asbestos fibers.
3.1.1 Respirators
Select respirators from those approved by the National Institute for Occupational Safety and Health (NIOSH), Department of Health and Human Services.
3.1.1.1 Respirators for Handling Asbestos
Provide personnel engaged in pre-cleaning, cleanup, handling, encapsulation, removal and demolition of asbestos materials with respiratory protection as indicated in 29 CFR 1926.1101 and 29 CFR 1926.103.
3.1.2 Exterior Whole Body Protection
3.1.2.1 Outer Protective Clothing
Provide personnel exposed to asbestos with disposable "non-breathable," whole body outer protective clothing, head coverings, gloves, and foot coverings. Provide disposable plastic or rubber gloves to protect hands.
Section 02 82 16 Page 19
Cloth gloves may be worn inside the plastic or rubber gloves for comfort, but shall not be used alone. Make sleeves secure at the wrists, make foot coverings secure at the ankles, and make clothing secure at the neck by the use of tape.
3.1.2.2 Work Clothing
Provide cloth work clothes for wear under the outer protective clothing and foot coverings and either dispose of or properly decontaminate them as recommended by the PQP after each use.
3.1.2.3 Personal Decontamination Unit
Provide a temporary, negative pressure unit with a separate decontamination locker room and clean locker room with a shower that complies with 29 CFR 1926.51(f)(4)(ii) through (V) in between for personnel required to wear whole body protective clothing. Provide two separate lockers for each asbestos worker, one in each locker room. Keep street clothing and street shoes in the clean locker. HEPA vacuum and remove asbestos contaminated disposable protective clothing while still wearing respirators at the boundary of the asbestos work area and seal in impermeable bags or containers for disposal. Do not wear work clothing between home and work.
Locate showers between the decontamination locker room and the clean locker room and require that all employees shower before changing into street clothes. Collect used shower water and filter with approved water filtration equipment to remove asbestos contamination. Dispose of filters and residue as asbestos waste. Discharge clean water to the sanitary system. Dispose of asbestos contaminated work clothing as asbestos contaminated waste. Decontamination units shall be physically attached to the asbestos control area. Build both a personnel decontamination unit and an equipment decontamination unit onto and integral with each asbestos control area.
3.1.2.4 Eye Protection
Provide goggles to personnel engaged in asbestos abatement operations when the use of a full face respirator is not required.
3.1.3 Warning Signs and Labels
Provide warning signs printed in English at all approaches to asbestos control areas. Locate signs at such a distance that personnel may read the sign and take the necessary protective steps required before entering the area. Provide labels and affix to all asbestos materials, scrap, waste, debris, and other products contaminated with asbestos.
3.1.3.1 Warning Sign
Provide vertical format conforming to 29 CFR 1926.200, and 29 CFR 1926.1101 minimum 20 by 14 inches displaying the following legend in the lower panel:
Legend Notation
Danger one inch Sans Serif Gothic or Block
Section 02 82 16 Page 20
Legend Notation
Asbestos one inch Sans Serif Gothic or Block
Cancer and Lung Disease Hazard 1/4 inch Sans Serif Gothic or Block
Authorized Personnel Only 1/4 inch Sans Serif Gothic or Block
Respirators and Protective Clothing are Required in this Area
1/4 inch Sans Serif Gothic or Block
Spacing between lines shall be at least equal to the height of the upper of any two lines.
3.1.3.2 Warning Labels
Provide labels conforming to 29 CFR 1926.1101 of sufficient size to be clearly legible, displaying the following legend:
DANGER
CONTAINS ASBESTOS FIBERS
AVOID CREATING DUST
CANCER AND LUNG DISEASE HAZARD
BREATHING ASBESTOS DUST MAY CAUSE SERIOUS BODILY HARM
3.1.4 Local Exhaust System
Provide a local exhaust system in the asbestos control area in accordance with ASSE Z9.2 and 29 CFR 1926.1101 that will provide at least four air changes per hour inside of the negative pressure enclosure. Local exhaust equipment shall be operated 24 hours per day, until the asbestos control area is removed and shall be leak proof to the filter and equipped with HEPA filters. Maintain a minimum pressure differential in the control area of minus 0.02 inch of water column relative to adjacent, unsealed areas.
Provide continuous 24-hour per day monitoring of the pressure differential with a pressure differential automatic recording instrument. In no case shall the building ventilation system be used as the local exhaust system for the asbestos control area. Filters on exhaust equipment shall conform to ASSE Z9.2 and UL 586. The local exhaust system shall terminate out of doors and remote from any public access or ventilation system intakes.
3.1.5 Tools
Section 02 82 16 Page 21
Vacuums shall be leak proof to the filter and equipped with HEPA filters capable of trapping and retaining at least 99.97 percent of all monodispersed particles of 0.3 micrometers in diameter or larger. Filters on vacuums shall conform to ASSE Z9.2 and UL 586. Do not use power tools to remove asbestos containing materials unless the tool is equipped with effective, integral HEPA filtered exhaust ventilation systems. Remove all residual asbestos from reusable tools prior to storage or reuse.
3.1.6 Rental Equipment
If rental equipment is to be used, furnish written notification to the rental agency concerning the intended use of the equipment and the possibility of asbestos contamination of the equipment.
3.2 WORK PROCEDURE
Perform asbestos related work in accordance with 29 CFR 1926.1101, 40 CFR 61-SUBPART M, and as specified herein.
3.2.1 Work Area Preparation
Where necessary, shut down electrical power, including receptacles and light fixtures. Under no circumstances during the decontamination procedures will lighting fixtures be permitted to be operating when the spraying of amended water may contact the fixture. Provide GFCI devices, temporary power, and temporary lighting installed in compliance with the applicable electrical codes. All installations are to be made by a State of Massachusetts licensed electrician. No wiring or electricity carry equipment compromised by damage, use or wear are acceptable for use on this project. Equipment will be immediately removed from service and the site by the contractor if directed by the Contracting Officer without compensation for replacement, loss of time or use.
Shut down and/or isolate heating, cooling, and ventilation air systems or zones to prevent contamination and fiber dispersal to other areas of the structure. During the work, vents within the work area shall be "criticalled" with duct tape and polyethylene sheeting.
3.2.2 Protection of Existing Work to Remain
Perform work without damage or contamination of adjacent work. Where such work is damaged or contaminated as verified by the Contracting Officer using visual inspection or sample analysis, it shall be restored to its original condition or decontaminated by the Contractor at no expense to the Government as deemed appropriate by the Contracting Officer. This includes inadvertent spill of dirt, dust, or debris in which it is reasonable to conclude that asbestos may exist. When these spills occur, stop work immediately. Then clean up the spill. When satisfactory visual inspection and air sampling results are obtained from the PQP work may proceed at the discretion of the Contracting Officer.
3.2.3 Furnishings
The Contractor shall be responsible for removing furniture from the work areas. The Contractor shall pre-clean moveable objects within the proposed work areas using HEPA vacuum equipment and/or wet cleaning methods as
Section 02 82 16 Page 22 appropriate and remove such objects from work areas and store in a location on site approved by the Contracting Officer.
3.2.4 Precleaning and Preparation
Pre-clean fixed objects within the work areas, using HEPA vacuum equipment and/or wet cleaning methods as appropriate, and enclose with a minimum 6-mil plastic sheeting sealed with duct tape. Do not use methods that raise dust, such as dry sweeping or vacuuming with equipment not equipped with HEPA filters
After HEPA vacuum cleaning, cover fixed walls with two layers of 4-mil polyethylene sheeting to the floor level. Where fixed walls are not used, two layers of 6-mil polyethylene sheeting will be applied to a rigid framework of wood, metal, or PVC. Where floor tile/mastic is not being abated, cover the floor with two layers of 6-mil polyethylene sheeting. All overlaps shall be sealed with tape or spray adhesive.
Clean and remove ceiling mounted objects, such as lights and other items not sealed off that interfere with asbestos abatement. Use hand-held amended water spraying or HEPA vacuuming equipment during fixture removal to reduce settled fiber dispersal.
3.2.5 Decontamination System
Construct the decontamination system with wood or metal framing, 3/8 inch sheathing and cover both sides with a double layer of 6-mil polyethylene sheeting, spray glued or taped at the joints. Caulk joints watertight at floor, walls, and ceiling.
Occupied areas and/or building space not within the work areas shall be separated from asbestos abatement work areas by means of airtight barriers.
The barriers shall be visually inspected several times daily to assure effective seal and the Contractor shall repair defects immediately.
3.2.5.1 Decontamination Enclosure
The Contractor shall establish contiguous to the work area, a decontamination enclosure consisting of an equipment room, shower room, and clean room in series. The only access between contaminated and uncontaminated areas shall be through this decontamination enclosure. If it is not feasible to set-up a contiguous decontamination unit, the Contractor shall establish a remote decontamination unit.
3.2.5.2 Access Between Rooms
Access between rooms in the decontamination system shall be through double flap curtain openings. The clean room, shower and equipment room within the decontamination enclosure, shall be completely sealed ensuring that the sole source of airflow through this area originates from uncontaminated areas outside the work area.
3.2.5.3 Equipment Decontamination Enclosure
The Contractor shall establish contiguous with the work area an equipment decontamination enclosure consisting of two (2) totally enclosed chambers
Section 02 82 16 Page 23 divided by double flap curtained opening. This enclosure must be constructed so as to ensure no personnel enter or exit through this unit.
3.2.6 Removal Procedures
The Contractor shall have a designated Competent Person on the job at all times to ensure establishment of a proper enclosure system and proper work practices throughout project. Abatement work will not commence until authorized by the Contracting officer. Proposed regulated areas for ACM abatement will be posted as required under 29 CFR 1926.1101, Communication of Hazards Section (k)
Spray asbestos materials with amended water using airless spray equipment or apply approved removal wetting agent to reduce the release of fibers during removal operations. The Contracting officer shall pre-approve the use of amended water as the wetting agent. In order to maintain indoor asbestos concentrations to the minimum, the wet asbestos must be removed in manageable sections. Material drop shall not exceed 8-feet. For heights up to 15-feet, provide inclined chutes or scaffolding to intercept drop.
Remove asbestos containing materials as appropriate by standard methods.
Fill disposal containers as removal proceeds; seal filled containers and clean containers before removal to equipment decontamination system. Wet clean each container thoroughly, double bag and apply caution label. Ensure that workers do not exit the work area thorough the equipment decontamination enclosure.
After completion of stripping work, all surfaces from which asbestos has been removed shall be wet brushed, using a nylon brush, wet wiped, and sponged or cleaned by an equivalent method to remove all visible material (wire brushes are not permitted). During this work, the surfaces being cleaned shall be kept wet.
Remove and containerize all visible accumulations of asbestos-containing and/or asbestos contaminated debris. During cleanup in the wet, utilize brooms, rubber dustpan, and rubber squeegees to minimize damage to floor covering. No dry sweeping is allowed instead use a HEPA filter equipped vacuum to clean debris on the floor and wet mop afterwards.
3.2.6.1 Sealing Contaminated Items Designated for Disposal
Sealed disposal containers, and all equipment used in the work area, shall be included in the cleanup and shall be removed from work areas via the equipment decontamination enclosure at an appropriate time in the cleaning sequence. All asbestos waste in 6-mil polyethylene disposal bags shall be double bagged in the equipment decontamination enclosure before removal from the site. Asbestos containing material shall be containerized while wet.
At no time shall asbestos material be allowed to accumulate or become dry.
Lower and otherwise handle asbestos containing material as indicated in 40
CFR 61-SUBPART M.
3.2.6.2 Contamination Outside Work Area
At any time during asbestos removal, should the Contracting officer suspect contamination of areas outside the work area(s), all abatement work shall stop until the Contractor takes steps to decontaminate these areas and eliminate the causes of such contamination. Unprotected individuals shall be
Section 02 82 16 Page 24 prohibited from entering suspected contaminated areas until air sampling and visual…