Amendment_0003.pdf
PDF 24 KB Posted
- Attached to
- MINI MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC), GENERAL CONSTRUCTION PROJECTS, NORTH CAROLINA AREA Federal contract opportunity
- Solicitation number
- N4008514R1302
About this file
Amendment 0003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B486_ASBESTOS_REPORT.pdf | ||
| N40085-14-R-1302_Amendment_0006.pdf | ||
| A-501_12647515_REV_3-7-2014.pdf | ||
| A-201_12647513_REV_3-7-2014.pdf | ||
| N40085-14-R-1302_Amendment_0005.pdf | ||
| N40085-14-R-1302_Amendment_0004.pdf | ||
| N40085-14-R-1302_Amendment_0002.pdf | ||
| N40085-14-R-1302_Amendment_0001.pdf | ||
| DrawingsAsOne.pdf | ||
| N40085-14-R-1302_(with_attachments_B-H).pdf | ||
| SpecsAsOne.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
N40085-13-R-1302, Mini General Construction Multiple Aw ard Construction Contract (MACC) North Carolina Area
The purpose of this Amendment is to provide responses to RFIs submitted.
See Attached
This amendment should be acknow ledged w hen your proposal is submitted. Failure to acknow ledge the amendment may constitute grounds for rejection of proposal.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 19-Feb-2014
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N40085-14-R-1302
X 9B. DATED (SEE ITEM 11)
10-Feb-2014
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Feb-2014
CODE
NAVFAC MID ATLANTIC
ROICC CHERRY POINT
BLDG 163 CURTIS ROAD
PSC BOX 8006
CHERRY POINT NC 28533-0006
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N40085-14-R-1302
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0003
Amendment 0003, RFI Questions & Answers
1. There is no response date on the SF1442, can you please tell me the date and time they are due.
A: See Amendment 0001 for clarification.
2. Section 10 of the SF1442 states “All proposal inquiries must be submitted no later than (NLT) 1400 12 March 20014.” When are proposal packages due? – Information is not in Section 13 of the SF1442, and I can’t find it mentioned anywhere else in the solicitation.
3. After reviewing the documents issued with this RFP on FBO, I noticed that there was no date listed on block 13 of the SF1442 to designate a due date for this RFP. Can the Government please tell us when the due date is for this specific RFP?
4. Can you provide the bid due date? It is not listed in section 13 of the SF1442.
5. What is the RFI procedure during the bid process?
A: Please submit all RFI’s in writing via email to jennifer.L.stewart1@navy.mil AND amy.k.bryant@navy.mil.
6. Will there be a site review? If not, is it possible to send individuals to review site conditions?
A: See Amendment 02 for clarification.
7. Page 16 of the solicitation states price range of $30,000 for projects but page 8 states $50,000. Please provide clarification.
A: The price range is $30,000
8. Will there be an organized site visit for the seed project?
9. I did not see a bid due date. FBO.gov does say that the notice does NOT constitute a request for proposal, request for quote, or invitation for bit. Should we consider this the nature of a presolicitation?
A: See Amendment 01 for clarification.
10. Solicitation Number: N4008514R1302 NAVFAC MINI MACC- The 1442 Form states that Competition is restricted to Small Business. Teaming Arrangements and Joint Ventures are excluded from competition. Does this exclusion include SBA Mentor Protégé Joint Ventures?
A: No, this does not exclude bona fide Mentor-Protégés from competition. Please include appropriate documentation with your proposal package.
11. Page 8 of 64-order of Factors does not match the requirements-requirements have Factor 2 as Safety-please clarify for technical factors.
A: Technical Factors are as follows:
Factor 1: Corporate Experience Factor 2: Past Performance Factor 3: Safety
12. Page 8 of 64-Corporate Experience requires 5 projects however Page 16 of 64 requires 2 projects.
Please clarify requirements for technical proposal. It looks as if there are 2 sets of requirements included in the solicitation.
A: Submit two (2) general construction projects.
13. The subject solicitation indicates that a site visit date will be scheduled via amendment to the solicitation. Do you anticipate eminent release of the amendment and date?
14. The interested vendor list is not showing up on this solicitation. Do you know why it is not visible?
A: The customer service number for FBO.gov is: 1-866-606-8220
15. Can we get directions to where the site visit will be held?
A: MCAS Cherry Point is located off of Highway 70 in Havelock, NC (Craven County). Contractors shall report to Marine Corps Air Station Cherry Point Main Gate located on Hwy 101. The Pass & ID office will provide you with a temporary pass to gain access to B-163. Contractors will be escorted to the site from B-163. The Pass & ID office can be extremely busy at times so it is recommended you arrive early and allow plenty of time at Pass & ID.
16. Are there any special requirements for accessing base?
A: To obtain access to the base, contractors will need a valid driver’s license, current registration, and proof of insurance.
17. We would like to attend the site visit but we only have passes to Camp Lejeune. Can we be added to a list to get access the morning of the site visit?
A: See answers to Questions 9 & 10 above.
18. Factor 1, Corporate Experience. Page 8 of 64 in the solicitation states “submit 5 general construction projects withing the last three years to demonstrate relevant experience, however page 16 of 64 states submit 2 projects. Which one applies?
A: See Answer to question 6 above.
19. Can you please advise on the steps we need to take to ensure our representative(s) may enter the base facilities to attend the site visit.
A: See answer to questions 9 & 10 above.