N4008314R2710_Amendment_0005.pdf

PDF 59 KB Posted

Attached to
MECHANICAL MULTIPLE AWARD CONSTRUCTON CONTRACT Federal contract opportunity
Solicitation number
N4008314R2710
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

Amendment 0005 Questions/Clarifications

View the file

Other files for this federal contract opportunity

Other files attached to MECHANICAL MULTIPLE AWARD CONSTRUCTON CONTRACT, newest first.
File Type Posted
N4008314R2710_MECHMAC_PHASE_II_AMEND_0001.pdf PDF
N4008314R2710_AMEND_0007.pdf PDF
N4008314R2710_Amendment_0006.pdf PDF
Attachments_pages26-50_Word_doc.docx DOCX document
N4008314R2710_Amend_0004_MechMAC.pdf PDF
N40083-14-R-2710_MECH_MAC_AMEND_0003_PHASE_I.pdf PDF
N4008314R2710_Amend_0002_MechMAC.pdf PDF
MECH_MAC_AMENDMENT_0001.pdf PDF
N4008314R2710_MECH_MAC_PHASE_I.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP N40083-14-R-2710; MECHANICAL CONSTRUCTION

MULTIPLE AWARD CONTRACT at the NAVAL SUPPORT

ACTIVITY, CRANE IN

AMENDMENT 0005: Questions/Clarifications 05/19/2014 - Continued question set

PHASE I

14. Part 2; Factor 1 Technical Approach; (3) Corporate Management; page 11 Offerors shall complete Personnel Reference sheets in the solicitation for all key personnel (e.g., corporate personnel who will have decision making responsibilities over the term of the contract).

Where can offerors find the Personnel Reference Sheets?

RESPONSE: There is not a form for “personnel reference sheets” this would be a resume

15. Attachment A-E; pages 26-50 Will the government provide the attachments as Word files?

RESPONSE: Attachment A-E are provided in word format.

16. Factor 1 Technical Approach; (3); Financial Support; page 11 Offerors shall clearly demonstrate their financial stability by providing the information requested below. Offerors shall also demonstrate their ability to sustain their financial obligations during the first 90 days of this contract:

Line of credit: Provide a letter from a financial institution showing your available line of credit (e.g., Minimum six figures) or a letter from your financial institution showing proof of financial stability, i.e. high and low account averages over the last six months.

Documented Bonding Capacity of at least $2 million per project and $5 million per year

Please confirm that the Financial Support section is part of the overall 5 double-sided maximum page counts for the Technical Approach.

RESPONSE: FACTOR 1: Technical Approach (a) (1) paragraph #2, is corrected to read:

“The technical approach narrative shall be limited to five (5) double-sided pages plus the organizational chart. The information requested in items 2, 3, and 4 below are not included in this page limitation.

Proposal Receipt date remains Monday, June 02, 2014 @ 2:00 p.m. Eastern Time.

All questions must be submitted in writing to Annette Taylor @ annette.taylor@navy.mil

Amendment 0005 is acknowledged by signing below: