N4008314R2710_Amendment_0005.pdf
PDF 59 KB Posted
- Attached to
- MECHANICAL MULTIPLE AWARD CONSTRUCTON CONTRACT Federal contract opportunity
- Solicitation number
- N4008314R2710
About this file
Amendment 0005 Questions/Clarifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N4008314R2710_MECHMAC_PHASE_II_AMEND_0001.pdf | ||
| N4008314R2710_AMEND_0007.pdf | ||
| N4008314R2710_Amendment_0006.pdf | ||
| Attachments_pages26-50_Word_doc.docx | DOCX document | |
| N4008314R2710_Amend_0004_MechMAC.pdf | ||
| N40083-14-R-2710_MECH_MAC_AMEND_0003_PHASE_I.pdf | ||
| N4008314R2710_Amend_0002_MechMAC.pdf | ||
| MECH_MAC_AMENDMENT_0001.pdf | ||
| N4008314R2710_MECH_MAC_PHASE_I.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP N40083-14-R-2710; MECHANICAL CONSTRUCTION
MULTIPLE AWARD CONTRACT at the NAVAL SUPPORT
ACTIVITY, CRANE IN
AMENDMENT 0005: Questions/Clarifications 05/19/2014 - Continued question set
PHASE I
14. Part 2; Factor 1 Technical Approach; (3) Corporate Management; page 11 Offerors shall complete Personnel Reference sheets in the solicitation for all key personnel (e.g., corporate personnel who will have decision making responsibilities over the term of the contract).
Where can offerors find the Personnel Reference Sheets?
RESPONSE: There is not a form for “personnel reference sheets” this would be a resume
15. Attachment A-E; pages 26-50 Will the government provide the attachments as Word files?
RESPONSE: Attachment A-E are provided in word format.
16. Factor 1 Technical Approach; (3); Financial Support; page 11 Offerors shall clearly demonstrate their financial stability by providing the information requested below. Offerors shall also demonstrate their ability to sustain their financial obligations during the first 90 days of this contract:
Line of credit: Provide a letter from a financial institution showing your available line of credit (e.g., Minimum six figures) or a letter from your financial institution showing proof of financial stability, i.e. high and low account averages over the last six months.
Documented Bonding Capacity of at least $2 million per project and $5 million per year
Please confirm that the Financial Support section is part of the overall 5 double-sided maximum page counts for the Technical Approach.
RESPONSE: FACTOR 1: Technical Approach (a) (1) paragraph #2, is corrected to read:
“The technical approach narrative shall be limited to five (5) double-sided pages plus the organizational chart. The information requested in items 2, 3, and 4 below are not included in this page limitation.
Proposal Receipt date remains Monday, June 02, 2014 @ 2:00 p.m. Eastern Time.
All questions must be submitted in writing to Annette Taylor @ annette.taylor@navy.mil
Amendment 0005 is acknowledged by signing below:
Contractor Signature