Amendment 0001.pdf

PDF 282 KB Posted

Attached to
DESIGN-BUILD, STEAM B BOILER REPLACEMENT, NAVAL SUPPORT FACILITY, INDIAN HEAD, MARYLAND
Solicitation number
N4008023R0010
Issued by

About this file

This document contains an amendment to a solicitation for a design-build project to replace the Steam B boiler plant at the Naval Support Facility in Indian Head, Maryland. The period of performance has been revised from 380 calendar days to 1022 calendar days to allow sufficient time for design, equipment fabrication and delivery. Responses have also been provided to three pre-proposal inquiries, confirming that only new construction experience of a similar size and scope will be considered under Factor 2 for construction and design experience, and that the experience of key subcontractors cannot be submitted. The solicitation is seeking a design-build contract for replacement of the Steam B boiler plant at the Naval Support Facility in Indian Head, Maryland, issued by the Naval Facilities Engineering Command.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

SOLICITATION: N40080-23-R-0010 STEAM BOILER REPLACEMENT, NAVAL SUPPORT FACILITY INDIAN HEAD, MD

PLEASE SEE SECTION SF30 CONTINUATION PAGE

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 17-Mar-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008023R0010

X 9B. DATED (SEE ITEM 11)

28-Feb-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

17-Mar-2023

CODE

COMNAVFACSYSCOM WASHINGTON

1314 HARWOOD ST

WASHINGTON DC 20374

N40080 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008023R0010

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0001

THE PURPOSE OF THIS AMENDMENT IS TO PROVIDE THE FOLLOWING:

1. Responses to Pre-Proposal Inquiries

N4008023R0010

SOLICITATION NO.: N4008023R0010

PROJECT TITLE/LOCATION: Steam Boiler Replacement, Indian Head MD

PRE-PROPOSAL INQUIRY FORM (PPI FORM)

Question No.

Date Received

REFERENCE QUESTION GOVERNMENT RESPONSE

Posted on Amend No.

Page Section Para

Phase I RFP, Page 1 (SF

1442 box 11)

The stated period of performance for the project is 380 calendar days. This appears to be a design build project and the design will take 9 months to complete.

The fabrication and delivery of the mechanical equipment may well be 1 year. Therefore, the stated period of performance is not achievable. Can the period of performance be revised to a more realistic performance period?

The period of performance for this project is now 1022 calendar days.

2 Phase I RFP pp. 12‐15

For Factor 2 (Construction and Design Experience: Scope), will the Government allow offerors to submit experience that involved the installation of relevant steam (or cogeneration or HTHW) plant equipment within an existing facility (in other words, a relevant system installation/repair), provided offerors still show at least one central plant facility new construction that meets current size/scope/ complexity requirements as written? Allowing for this would still require offerors to show experience with key relevant systems requirements in each project submitted while broadening the relevant projects offerors can present.

No 0001

3 Phase I RFP pp. 12‐13

For Factor 2 (Construction Experience), will the Government allow offerors to submit the experience of a key construction subcontractor?

No 0001