N3904027Q1001 RFQ.pdf

PDF 2 MB Posted

Attached to
Rental of Temporary HVAC System w/ Exhaust Blowers & Heaters
Solicitation number
N3904027Q1001
Issued by

About this file

This is a Request for Quote (RFQ) for temporary HVAC and exhaust system rentals to support operations at Portsmouth Naval Shipyard (PNSY). The solicitation number is N3904027Q1001, issued under a Women-Owned Small Business (WOSB) set-aside. The RFQ covers rental of multiple HVAC units, exhaust blowers, chillers, pumps, hoses, fittings, manifolds, and emergency stop equipment on a firm fixed price basis, with pricing arrangements specified in weeks or per job for freight. The base contract period consists of 52-week rental terms for primary equipment (CLINs 0001-0004) and 25-week terms for optional chillers and ancillary equipment (CLINs 0006-0009), followed by optional extension periods of 44 weeks (CLINs 1001-1010), 4 weeks (CLINs 2001-2009), and corresponding documentation deliverables across three contract phases (Exhibits A, B, and C). Preventative maintenance, weekly inspections, training, and technical support are contractor responsibilities throughout the lease period.

Equipment specifications are detailed and rigorous, requiring HVAC units with triple or dual coil configurations capable of 20,000 CFM with 120-ton minimum cooling capacity; 230-ton air-cooled chillers with dual compressor circuits and electronic flow metering; 600 GPM chilled water pumps; industrial exhaust blowers rated for 10,000 CFM at 14 inches static pressure; and electric fan coil heaters. All equipment must be newly manufactured or completely refurbished within ten years, rated for outdoor year-round operation in harsh marine environments (-10 to +110°F), equipped with 480 VAC three-phase electrical connections using camlok-style connectors, and include emergency remote stop systems with 1,500-foot cable runs. All chilled water hoses, manifolds, cooling coils, and valve assemblies require hydrostatic pressure testing to 150 psig within one year of delivery, with certified test documentation provided.

The contractor must deliver fully operational, functionally tested equipment ready for immediate use, provide comprehensive startup and commissioning services within 24 hours of notification, perform weekly maintenance inspections and preventative maintenance per OEM requirements, respond to repair requests within 48 hours or provide replacement equipment within 72 hours, furnish technical documentation including operations manuals and equipment data sheets, and train PNSY personnel on equipment operation and daily surveillance. All contractor personnel accessing the Naval Shipyard must be U.S. citizens and comply with DBIDS credentialing requirements, security protocols, and restrictions on camera-enabled devices in controlled industrial areas. The government will provide temporary storage and forklift services during work hours for equipment delivery and return.

View the file

Other files

File Type Posted
Exhibit C.pdf PDF
Attachment 3 - QASP Matrix.xlsx XLSX spreadsheet
Exhibit B.pdf PDF
Attachment 2 - QASP.pdf PDF
Attachment 1 - OPSEC Enclosure 2.pdf PDF
Exhibit A.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WOMEN-OWNED SMALL

BUSINESS (WOSB)

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES

1. REQUISITION NUMBER PAGE 1 OF

2. CONTRACT NUMBER 3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE

DATE

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME b. TELEPHONE NUMBER (No collect calls)

8. OFFER DUE DATE/

LOCAL TIME

9. ISSUED BY

13b. RATING

14. METHOD OF SOLICITATION

CODE

15. DELIVER TO 16. ADMINISTERED BY CODE

18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/

OFFEROR

CODE

FACILITY

CODE

CODE

TELEPHONE NUMBER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED

REQUEST

FOR QUOTE

(RFQ)

INVITATION

FOR BID

(IFB)

REQUEST

FOR

PROPOSAL

(RFP)

SEE ADDENDUM

19.

ITEM NUMBER

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Government Use Only)

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH

AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND

ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS

SPECIFIED

29. AWARD OF CONTRACT: REFERENCE OFFER

DATED . . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR

30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 11/2021)

Prescribed by GSA - FAR (48 CFR) 53.212

10. THIS ACQUISITION IS UNRESTRICTED OR

NORTH AMERICAN

INDUSTRY CLASSIFICATION

STANDARD (NAICS):

SIZE STANDARD:

13a. THIS CONTRACT IS A

RATED ORDER UNDER

THE DEFENSE PRIORITIES

AND ALLOCATIONS

SYSTEM - DPAS (15 CFR 700)

SET ASIDE: % FOR:

11. DELIVERY FOR FREE ON

BOARD (FOB) DESTINATION

UNLESS BLOCK IS MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

ARE ARE NOT ATTACHED

ARE ARE NOT ATTACHED

27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3

AND 52.212-5 ARE ATTACHED. ADDENDA

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

8(A)

ECONOMICALLY

DISADVANTAGED

WOMEN-OWNED SMALL

BUSINESS (EDWOSB)

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

(SDVOSB)

HUBZONE SMALL

BUSINESS

SMALL BUSINESS

NOTE: OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30.

Section A - Solicitation/Contract Form

Temp HVAC and Exhaust System

N3904027Q1001

Section B - Supplies or Services & Prices or Costs

Additional Information/Notes

Item Supplies/Service Quantity Unit Unit Price Amount

Rental of (3) V-01 or V-02 Triple/Double Coil HVAC in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

52 Week

Rental of (5) V-03 Exhaust Blowers in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

52 Week

Rental of (14) V-13 E-Stop Equipment in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

52 Week

Rental of (7) V-04 Electric Fan Coil Unit in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

18 Week

Freight: All transportation costs associated with CLINs 0001-0004

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Rental of (1) V-05 230 Ton Chiller & (1) V-06 CHW Pump 600gpm in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

25 Week

Option Line Item

Rental of (1) V-05 230 Ton Chiller & (1) V-06 CHW Pump 600gpm in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

25 Week

Option Line Item

Rental of Hoses & Elbows in accordance with the Statement of Work

V-07: 6 IN Dia CHW Hose V-08: 6 IN Dia 90 Elbow V-09: 4 IN Dia CHW Hose V-10: 4 IN Dia 90 Elbow

Pricing Arrangement: Firm Fixed Price

25 Week

Option Line Item

Rental of (4) V-11 CHW X Manifolds & V-12 CHW Adaptors in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

25 Week

Option Line Item

Freight: All transportation costs associated with CLINs 0006-0009 in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

1 Job

See Exhibits: A Contract Data Requirements List (CDRL)

Data Items:

A01 - Certification Data Report A02 - Contractor's Personnel Roster A03 - Equipment Technical Manual A04 - Maintenance Service Report A05 - Hydrostatic Test Report A06 - Maintenance Support Plan A07 - Calibration Certificate/Report

A001 Certification Data Report in accordance with Exhibit A

Pricing Arrangement: Firm Fixed Price

1 Each

A002 Contractor's Personnel Roster in accordance with Exhibit A

Pricing Arrangement: Firm Fixed Price

1 Each

A003 Equipment Technical Manual in accordance with Exhibit A

Pricing Arrangement: Firm Fixed Price

1 Each

A004 Maintenance Service Report in accordance with Exhibit A

Pricing Arrangement: Firm Fixed Price

52 Week

A005 Hydrostatic Test Report in accordance with Exhibit A

Pricing Arrangement: Firm Fixed Price

1 Each

A006 Maintenance Support Plan in accordance with Exhibit A

Pricing Arrangement: Firm Fixed Price

1 Each

A007 Calibration Certificate/Report in accordance with Exhibit A 1 Each

Pricing Arrangement: Firm Fixed Price

Preventative, Routine Maintenance & Training in accordance with Sections 5.3 & 5.4 of the Statement of Work

Pricing Arrangement: Firm Fixed Price

52 Week

Option Line Item

Option to Extend CLIN 0001 - Rental of (3) V-01 or V-02 Triple/Double Coil HVAC in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

44 Week

Option Line Item

Option to Extend CLIN 0002 - Rental of (5) V-03 Exhaust Blowers in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

44 Week

Option Line Item

Option to Extend CLIN 0003 - Rental of V-13 E-Stop Equipment in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

44 Week

Option Line Item

Option to Extend - Rental of (7) V-04 Electric Fan Coil Unit in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

31 Week

Option Line Item

Freight: All transportation costs associated with Option CLINs 1001-1004

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Option to Extend CLIN 0006 - Rental of (1) V-05 230 Ton Chiller & (1) V-06 CHW Pump 600gpm in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

26 Week

Option Line Item

Option to Extend CLIN 0007 - Rental of (1) V-05 230 Ton Chiller & (1) V-06 CHW Pump 600gpm in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

26 Week

Option Line Item

Option to Extend CLIN 0008 - Rental of Hoses & Elbows in accordance with the Statement of Work

V-07: 6 IN Dia CHW Hose V-08: 6 IN Dia 90 Elbow V-09: 4 IN Dia CHW Hose V-10: 4 IN Dia 90 Elbow

26 Week

Option to Extend 0009 - Rental of (4) V-11 CHW X Manifolds & V-12 CHW Adaptors in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

26 Week

Option Line Item

Freight: All transportation costs associated with Option CLINs 1006-1009 in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

See Exhibits: B Contract Data Requirements List (CDRL)

Data Items:

B01 - Certification Data Report B02 - Contractor's Personnel Roster B03 - Equipment Technical Manual B04 - Maintenance Service Report B05 - Hydrostatic Test Report B06 - Maintenance Support Plan B07 - Calibration Certificate/Report

Option Line Item B001

Certification Data Report in accordance with Exhibit B

Pricing Arrangement: Firm Fixed Price

1 Each

Option Line Item B002

Contractor's Personnel Roster in accordance with Exhibit B

Pricing Arrangement: Firm Fixed Price

1 Each

Option Line Item B003

Equipment Technical Manual in accordance with Exhibit B

Pricing Arrangement: Firm Fixed Price

1 Each

Option Line Item B004

Maintenance Service Report in accordance with Exhibit B

Pricing Arrangement: Firm Fixed Price

44 Week

Option Line Item B005

Hydrostatic Test Report in accordance with Exhibit B

Pricing Arrangement: Firm Fixed Price

1 Each

B006

Maintenance Support Plan in accordance with Exhibit B

Pricing Arrangement: Firm Fixed Price

1 Each

Option Line Item B007

Calibration Certificate/Report in accordance with Exhibit B

Pricing Arrangement: Firm Fixed Price

1 Each

Option Line Item

Option to Extend CLIN 0012 - Preventative, Routine Maintenance & Training in accordance with Sections 5.3 &

5.4 of with the Statement of Work

Pricing Arrangement: Firm Fixed Price

44 Week

Option Line Item

Option to Extend CLIN 1001 - Rental of (3) V-01 or V-02 Triple/Double Coil HVAC in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

4 Week

Option Line Item

Option to Extend CLIN 1002 - Rental of (5) V-03 Exhaust Blowers in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

4 Week

Option Line Item

Option to Extend CLIN 1003 - Rental of V-13 E-Stop Equipment in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

4 Week

Option Line Item

Option to Extend CLIN 1006 - Rental of (1) V-05 230 Ton Chiller & (1) V-06 CHW Pump 600gpm in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

4 Week

Option Line Item

Option to Extend CLIN 1007 - Rental of (1) V-05 230 Ton Chiller & (1) V-06 CHW Pump 600gpm in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

4 Week

Option Line Item

Option to Extend CLIN 1008 - Rental of Hoses & Elbows in accordance with the Statement of Work

V-07: 6 IN Dia CHW Hose V-08: 6 IN Dia 90 Elbow V-09: 4 IN Dia CHW Hose V-10: 4 IN Dia 90 Elbow

4 Week

Option to Extend 1009 - Rental of (4) V-11 CHW X Manifolds & V-12 CHW Adaptors in accordance with the Statement of Work

Pricing Arrangement: Firm Fixed Price

4 Week

Option Line Item

See Exhibits: C Contract Data Requirements List (CDRL)

Data Items:

C01 - Certification Data Report C02 - Contractor's Personnel Roster C03 - Equipment Technical Manual C04 - Maintenance Service Report C05 - Hydrostatic Test Report C06 - Maintenance Support Plan C07 - Calibration Certificate/Report

Option Line Item C001

Certification Data Report in accordance with Exhibit C

Pricing Arrangement: Firm Fixed Price

1 Each

Option Line Item C002

Contractor's Personnel Roster in accordance with Exhibit C

Pricing Arrangement: Firm Fixed Price

1 Each

Option Line Item C003

Equipment Technical Manual in accordance with Exhibit C

Pricing Arrangement: Firm Fixed Price

1 Each

Option Line Item C004

Maintenance Service Report in accordance with Exhibit C

Pricing Arrangement: Firm Fixed Price

4 Week

Option Line Item C005

Hydrostatic Test Report in accordance with Exhibit C

Pricing Arrangement: Firm Fixed Price

1 Each

Option Line Item C006

Maintenance Support Plan in accordance with Exhibit C

Pricing Arrangement: Firm Fixed Price

1 Each

C007

Calibration Certificate/Report in accordance with Exhibit C

Pricing Arrangement: Firm Fixed Price

1 Each

Option Line Item

Option to Extend CLIN 1012 - Preventative, Routine Maintenance & Training in accordance with Sections 5.3 &

5.4 of the Statement of Work

Pricing Arrangement: Firm Fixed Price

4 Week

Section C - Description/Specifications/Statement of Work

STATEMENT OF WORK

1. SCOPE

1.1. Portsmouth Naval Shipyard (PNSY) is seeking to lease a temporary HVAC & Exhaust system with steam heat connections, but electric heat is an acceptable option if the rental industry cannot support the steam request.

2. REFERENCES

2.1. The following documents in effect on the date of this requested proposal is a part of this specification to the Issues of Publications -extent applicable, or as specified herein. Within the specification, they shall be referred to by their basic designation only.

2.1.1. Government

2.1.1.1. US Federal standard A-A-59326: Standard for cam action couplings.

2.1.2. Nongovernment

2.1.2.1. Spark Resistant Construction (SRC: AMCA Standard 99-0401-86) Type C

2.1.2.2. AHRI Standard 410

2.2. - In the event of conflict between the text of this specification and that of the references cited above, the text of Order of precedence this specification shall take precedence. Nothing in this specification, however, shall supersede applicable laws or regulations unless a specific exemption has been obtained.

3. TECHNICAL REQUIREMENTS

3.1. Component List

PIECE NO. QTY. NAME OF PART Table Section

V-01 1-3 HVAC Unit: Triple Coil Unit 1 & 1A 4.3-4.5

4.7-4.14

V-03 5 Industrial Exhaust Blower 5 4.4, 4.8-

4.14

V-04 7 Electric Fan Coil Unit- Heater (150 KW) 6 4.4, 4.8-

4.14

V-05 2 230 Ton Chiller 2

4.1-4.3, 4.5, 4.6, 4.8-4.14

V-06 2 Chilled Water Pump: 600 GPM 3 4.1-4.5, 4.8-4.14

V-07 1,000 FT 6 IN Dia Chilled Water Hose 4 4.2, 4.3, 4.5

V-08 4 6 IN Dia. 90 Degree Elbows 4 4.2, 4.3, 4.5

V-09 1,000 FT 4 IN Dia Chilled Water Hose 4 4.2, 4.3, 4.5

V-10 10 4 IN Dia. 90 Degree Elbows 4 4.2, 4.3, 4.5

V-11 4 Chilled Water X Manifold 4 4.2, 4.3, 4.5

V-12 4 CHW Adaptors / Transition Fittings 4 4.2, 4.3, 4.5

V-13 14 Emergency Remote Stop (E-Stop) 7 5.2.4.1.7

3.2. Alternate Component List

PIECE NO. QTY. NAME OF PART Table. Section

V-02 0-2 HVAC Unit: Dual Coil Unit 1 4.3-4.5

4.7-4.14

Table 1: Dual Coil HVAC Unit

Maximum Dimensions 21 ft long, 8.5 ft wide, 17,000 lbs

Emergency Stop

Must be pre-wired for, compatible with, and supplied with, Emergency Remote Stop (E- Stop)

(See Table 7 for E-Stop Requirement)

Fabrication All components must be fully integrated within single housing equipped with appropriately rated overhead lifting points.

Power Supply 480 VAC Nominal / 3 Phase / 400FLA max.

Electrical Connections Camlok Style (J Series locking style i.e. 1016 series)

Process Air Minimums Four outlets. (All outlets must be 20" diameter, each, capable of connecting 20" flex duct).

20,000 CFM (5,000 per outlet) at 7 inches External Static Pressure

TEFC Premium Motors, VFD fan controller capable of 50% of rated airflow

Tightly sealed non-detachable process air inlet/outlet.

Detachable covers are permitted.

Process Air Filtration Moisture Separator/Demister type filtration for purging 98% of the moisture. Paper or fibrous filtration media is NOT ACCEPTABLE.

Metal process air inlet filters

Electric Heater

Minimums

240KW electric heating element, thermostatically controlled to discharge air temperature set point.

Cooling Coil Ton (min) 120 Tons with 42F entering chill water and 10F T thermostatically controlled.

Cooling Coil Connection

4" non-ferrous, non-galvanized, metal cam and groove quick-disconnect style per reference

2.1.1.1, with manual air bleed valves

Table 1A: Triple Coil HVAC Unit: Option

Steam Heat Minimum 2.0 MMBH

Steam Connection Type 11/2" FNPT 3 EA Inlet, 3/4" NPT Condensate drain

Steam Trap PSI Minimum 150 PSI

* : If industry cannot support the desired Triple Coils, an option is to provide one Triple Coil (Table 1 and Table 1A) and two units NOTE meeting Table 1 specifications.

Table 2: 200-230 Ton Air Cooled Chiller Unit

Maximum Dimensions 27.5 ft long, 8.5 ft wide, 22,000 lbs

Safety Must have a low-flow switch ( a pressure differential switch). not

Fabrication All components (with sole exception of the pump) must be fully integrated within single housing equipped with appropriately rated overhead lifting points.

Electrical 480 VAC Nominal / 3 Phase / 400FLA max per circuit. Integrated chiller pump be powered MUST separately.

Electrical Connections Camlok Style (J Series locking style i.e. 1016 series)

Cooling Capacity 210 Ton heat rejection @ 95F Ambient conditions

Leaving Water Temp 422F

Chill Water Outlet Range 38F-60F

Condenser Type Air Cooled, forced air

Chiller Components Minimum of 2 separate compressor and refrigeration circuits

Chill Water Connection 6 inch, non-ferrous, non-galvanized, metal cam and groove quick disconnect fittings per reference 2.1.1.1.

Chiller Interface Must have a display which allows end-user to jog through current and historical data.

Data Requirements System Performance Data

System Parameters Adjustment

System Errors (Recorded and logged during equipment failure)

Flow Meter (Calibrated) Electronic 100-800 GPM @ 1 GPM resolution Electronic in-line, downstream of pump designed for system working pressure.

Table 3: Chiller Pump

Configuration Can be integral to the Chiller, or standalone, with same connection requirements as Chiller.

Performance 600 GPM at 100 ft head (H2O) compatible with chiller unit, if standalone.

Motor Low speed, 1750 RPM

Electrical 480 VAC Nominal/ 3 Phase, capable of being powered independently of Chiller with appropriately sized disconnect switch.

Safety Differential Pressure gage rated from 0-150 PSI, or Max discharge pressure +20 PSI, whichever is greater.

Table 4: Hoses & Fittings

Hose Type 6" and 4" non-collapsible suction/discharge hose.

Hose Lengths (max) 25 ft

Connection Types Male & Female Cam and Groove quick disconnect fittings, per reference 2.1.1.1 supplied with new gaskets for all hoses and manifolds.

Pressure Rating 150 PSI

Manifold Cross-style, with two 6" connections (male & female) and two 4" connections (female).

Sufficient adapters to convert half of 4" female to 4" male.

All connections must have hydrostatic caps/plugs capable of sealing against system pressure.

All 4" legs shall have isolation valves.

Manifolds shall be designed such that they stack together to minimize laydown space.

Transition fittings Adapter fittings to attach 4" hose to 3" equipment connections required if any equipment is provided with 3" connections.

Test Requirements All hoses and fittings must have been previously hydrostatically testing to 1.5 times the pressure rating within 1 year of issuance.

Spare Soft goods All hoses and fittings must be supplied with replacement gaskets for each fitting/hose size.

Table 5: Industrial Exhaust Blowers

Physical Attributes 8'-6"L &W x 9'H

Minimum Capacity 10,000 CFM at 14 inches External Static Pressure

Electrical 480 VAC Nominal/ 3 Phase, with appropriately sized disconnect switch. 100FLA max.

Motor NEMA Design B, TEFC premium, industrial, continuous-duty, ball bearing, foot mounted. Bearings shall be rated L-10 life (40,000 hrs). Equipped with VFD.

Safety

Must be pre-wired for, compatible with, and supplied with, Emergency Remote Stop (E-Stop)

See Table 7

Must include guards for drive assembly per OSHA regulations and suction /discharge outlet fan guards

Vibration Sensor with programmable electronic automatic shutdown, for protection of equipment. Sensor shall have two setpoints: lower setpoint illuminates a "caution" light. Upper setpoint secures blower automatically and illuminates a "warning" light.

Construction

AMCA Standard 99-0401-86 Type C, Centrifugal, Up-Blast. Fan Wheel must be constructed with flat blades. Airfoil and backward incline blades are not acceptable. Blades shall be continuously welded to reduce stress.

Connections Adaptable to two 14" inlets or six 8" inlets, capable of connecting 14" or 8" flexible duct. Contractor is responsible for providing transition inlet assembly.

Cleanout Gasketed door, either hinged or bolted, to provide maintenance and cleanout access. Drain pipe connected to lowest point on fan housing, due to up-blast configuration.

Table 6: 150KW Electric Heaters

Maximum Dimensions 4'W x 8' L x 5' H. 2000lbs

Minimum Airflow 7000 CFM at 5.6 inches Total Static Pressure

Minimum Heat 150KW electric heat with 240F air temperature rise

Motor TEFC Premium Motors with VFD Controller

Electrical 480 VAC Nominal / 3 Phase / 200FLA max.

Electrical Connections Camlok Style (J Series locking style i.e. 1016 series)

Controls Thermostatically controlled discharge air temperature set point

Safety Must be pre-wired for, compatible with, and supplied with, Emergency Remote Stop (E-Stop)

See Table 7

Safety controls integrated into controller

Connection One 20 inch diameter outlet capable of connecting to 20 inch flexible ducting.

Construction Must include fork pocket slots and overhead rigging connections (padeyes)

Table 7: Emergency Remote Stop (E-Stop)

Cable Type Type SO or equivalent (Heavy duty, flexible, portable, durable)

Cable Length 1500 ft per E-Stop to accommodate tortured routing paths

Accessories Plexiglas cover for all E-Stop buttons to prevent inadvertent activation

* : Contractor is responsible for installation and routing of all E-Stop components.NOTE

4. NOTES:

4.1. Chiller Capacity & Utilities:

4.1.1. Cooling: The primary utility for the Chiller shall be all electric and air-cooled. The minimum nominal chilled water capacity shall be as indicated with the actual capacity, based on an ambient temperature of 95F dry bulb with an Entering Water Temperature (EWT) of 52F and a Leaving Water Temperature (LWT) of 42F, to be not less than 5% of the desired nominal capacity. The unit capacity shall not be greater than one-third above (+) the minimum specified capacity and shall be able to run continuously at one-quarter of that unit's stated capacity.

4.1.2. Automatic Operation, Regulation, & Controls: The Chilled Water Unit or Chiller Module shall be equipped with an automatic variable capacity control requiring only initial temperature adjustment of from 38 to 60F by the operator. Refrigeration circuits shall maintain the specified temperature condition while protecting against coil freeze-up. The unit / modules shall be completely wired for safety, capacity, and operation such as a power/switch system with circuit breakers, manual/automatic controller, motor overload protection, high/low pressure cut-outs, energy control system, and other essential components. The unit / modules shall be fully controllable under a wide range of loads even though the daily and seasonal ambient temperatures vary greatly.

4.1.3. Design & Component Integration: The unit / modules shall be designed for continuous operation at minimal loading (i.e.

one-quarter of full capacity for refrigeration & one-third of full capacity for pumping) despite extreme ambient conditions (e.g. -10 to +100F and 0 to 100% RH).

4.1.4. Cooling: The condenser(s) shall be air-cooled via fan(s). The chiller shall have a sufficient water storage capacity to run isolated from a make-up water connection.

4.1.5. Energy Efficiency: For energy efficient operation in a fully loaded condition, the Full Load Amperage (FLA) rating for the combined Chilled Water Unit or the FLA summation for a separate Chiller Module plus one Pump Module shall be two and a half amperes or less per ton of actual chilled water capacity.

4.2. Coolant Free: Besides manifolds and hose assemblies that are normally flushed and tested, all machinery conveying chilled water such as: the Chiller, Pump and machines with a chilled water coil; shall arrive with no coolant of any type in its piping (i.e. No Water & No Anti-Freeze).

4.3. Chilled Water Hose Assembly / Manifold Construction / Cooling Coil Hydrostatic Testing: For standard Chilled Water Hose assemblies of six inch nominal diameter or less, the exterior cover shall be a thick rubber (Buna-N) type material designed as a CHW insulator. All Chilled Water connectors / fittings must be quick disconnect style fittings meeting the requirements defined in reference

2.1.1.1. Chilled Water Hose assemblies shall be noncollapsible and the camlock fittings shall be attached to the hose material via the more secure, newer type, crimp style hose fitting via a single specified diameter, elongated sleeve length and not from the less secure, older type, band clamp style hose fitting via multiple universal diameter, shorter ferrules. Gaskets for couplings shall be preinstalled inside the female coupling(s) of hose assemblies and manifolds. The gasket shall be inspected for presence, tight fit, and lack of deterioration. Gaskets shall not protrude into the waterway.. Hose/manifold/valve assemblies and all cooling coils shall be hydrostatically tested with new hose gaskets for Strength and Tightness and/or Valve Seat Leakage by an independent (of the Contractor) and certified Contractor to a minimum of 150 psig for five minutes and visually inspected and/or internal valve leakage measured while pressurized. Hydrostatic test date shall be within one calendar year of scheduled Arrival Date of the equipment. Hoses/manifolds/valve assemblies shall have a banded identification (ID) tag or label attached to the assembly displaying the hydrostatic test results. (CDRL A005, B005, C005)

4.4. Phase Rotation: To prevent or identify an out-of-phase electrical power situation, three-phase machines shall include either: a (a) reverse phase relay and/or meter that identifies an out-of-phase condition and prevents operation especially applied to complex machinery in which such a condition could cause damage or an arrow prominently displayed at an appropriate location on the machine's housing (b) to indicate the proper direction of shaft rotation with the ability to observe a portion of the shaft after a momentary application of power (a.

k.a. jog or bump). A reverse phase relay is not required nor desired for VFD motors, however, the VFD shall have a jog button so as to verify correct rotation.

4.5. Supplemental Equipment: For the protection and cleanliness of the machinery components, all chilled water connection points shall be shipped with plug/cap fittings.

4.6. Hydronic Flow Meter: Attached to the Chiller and its associated pump shall be a continuous reading liquid flow meter, preferably, in-line with flow. The type of meter may be Electronic Metering. The physical positioning of the instrument shall be downstream of the Chiller immediately after its discharge. The flow meter assembly shall be rated for 150 psig;. The instrument shall be calibrated by a licensed Metrology Laboratory within five years of its scheduled delivery with certified calibration test results both accompanying the flow meter assembly. (CDRL A007, B007, C007)

4.7. HVAC Capacity & Utilities

4.7.1. Control: The unit shall include a permanently mounted control board accessible without opening any panels with temperature thermometer(s) and pressure gauge(s) as necessary for monitoring and control. The unit shall be fully controllable under a wide range of loads even though the diurnal and seasonal ambient temperatures vary greatly.

4.8. Construction: Except as noted for a particular machine type, units shall be a single integrated framed structure manufactured as a complete entity to include all devices, accessories, and fittings necessary to perform the function for which it was designed. Each unit shall be capable of continuous, year-round, outdoor, unmanned operation even at minimal loading while exposed from inclement to extremely harsh weather (e.g. deep snow, strong & gusty winds, and/or heavy rain) and varied ambient conditions (-10 to +110F & 0 to 100% RH).

Machines shall meet State and federal requirements for its type such as the National Electrical Code (NEC) for electrical devices / components and the American Society of Mechanical Engineers (ASME) for pressurized vessels / components. Machines shall be modular in design so as to act as a stand-alone unit; compact so as to fit in the tight confines of a drydock; portable so as to be transported by forklift and then lifted by crane; and ruggedly constructed so as to endure a marine industrial environment. Machines shall be newly manufactured / completely refurbished and factory tested within ten (10) years.

4.9. Electrical: Electrical components shall conform to a NEMA standard (NEMA 3 or 4) that allows for unsheltered outdoor use of the unit. Each machine shall require only one type / source of electrical power (480 Nominal VAC / three-phase / 60 hertz). The type of electrical power required (voltage & amperage) must be clearly indicated on the outside of the equipment, readily detected, and collocated with all other electrical information. The

Contractor shall provide the PNSY Contracting Office with the following details: (i) electrical power type (amperage & voltage); (ii) confirming that the type of electrical connectors for three phase shall be camlok; (iii) breaker type/size or recommended capacity for the electrical source; and (iv) whether the machine is furnished with overcurrent protection.

4.10. Lifting & Handling:

4.10.1. Lifting & Handling Exception: Although considered to be machinery, individual pump units, being relatively lightweight and compact, are not required to be enclosed in a caged frame. However, the remaining Lifting and Handling requirements pertain in that the unit will be handled by forklift.

4.11. Noise Requirement: When operating at full speed, noise levels must not be over 85 dB[A] at less than three feet from the unit or frame unless a quieter noise level is specified. A hearing protection safety placard shall be posted on each machine generating more than 85 dB[A] at the unit's edge or frame.

4.12. Machinery / Equipment Tagging and Markings: Fluid piping inlet(s) / outlet(s) must be clearly marked. Machinery and itemized equipment require tagging to show Project Number / Technical Specification Identification (ID) Number

4.13. Contractor Identification Of Itemized And Ancillary Equipment: The Contractor shall uniquely tag and permanently mark all of its ancillary and itemized equipment / hardware (e.g. manifolds, hose assemblies, pipe fittings, duct adapters, ducting, etc.) so as to differentiate from that owned by either the Shipyard or other Contractors.

4.14. Dead Front Control Panel or External Controller: Access to basic machinery controls, such as a Dead Front Control Panel or External Controller, shall be such that there is non-exposure to energized electrical circuits or other components regardless of "live" voltage, to include control circuitry, by ."a person on the operating side of the equipment"

5. RESPONSIBILITES

5.1. Government

5.1.1. Equipment Technical Evaluation: Temporary Services Engineering

5.1.2. Receipt Inspection: Contractor Officer Representative (COR)

5.1.3. Coordination of equipment delivery & returns: COR

5.1.4. Schedule equipment service, repair, and training: COR

5.2. Contractor

5.2.1. Use Table E1 of Enclosure 1 to verify conformity with the Technical Requirements.

5.2.2. The equipment will be operating around-the-clock under a rigorous deployment performance schedule. Within twenty-four

(24) hours of initial notification of the need for repair, the Contractor shall have a qualified and equipped technician on the job-site fully prepared to repair the rental equipment. The defective unit(s) shall be repaired within forty-eight (48) hours of initial notification or, if the original defective unit(s) cannot be made operational, replaced within seventy-two (72) hours of initial notification. If the equipment failure is not the fault of the Government, the Contractor shall bear all costs associated with its repair and/or replacement.

5.2.3. The contractor shall provide technical support to PNSY project personnel as required.

5.2.4. Equipment Start-up/ Commissioning Services

5.2.4.1. Contractor must provide start-up and commissioning services to prepare the equipment to be placed into service. This includes but is not limited to the following:

5.2.4.1.1. Pressurizing the system

5.2.4.1.2. Performing leak check of all contractor made connections

5.2.4.1.3. Adjusting setpoint(s) to meet the requirements of this Statement of Work

5.2.4.1.4. Verifying satisfactory operation of all drains installed on equipment

5.2.4.1.5. Troubleshooting/adjudicating any alarm conditions present on start-up (See 5.3) 5.2.4.1.6.

Training Government operators in equipment function, control and alarm(s)/indications.

5.2.4.1.7. Installation and routing of all E-Stop components.

5.3. Maintenance

5.3.1. Except for daily surveillance checks, the Contractor is responsible for all equipment preventative maintenance and repairs for the duration of the lease. Coordinate maintenance with Contracting Office Representative (COR) or Technical Point of Contact

(TPOC).

5.3.2. The contractor shall provide Preventative Maintenance (PM) schedules which are equipment specific. The PM shall meet all requirements determined by the Original Equipment Manufacturer (OEM). All PMs conducted shall(CDRL A006, B006, C006) include a technical service report identifying component, maintenance conducted, date, and next scheduled PM date. (CDRL A004, B004, C004).

5.3.3. In addition to providing routine preventative maintenance, the contractor shall provide a service technician on a weekly basis for the duration of the lease to perform weekly equipment inspections. Weekly equipment inspections shall consist of checking all functional operating parameters of each individual piece of equipment. This shall include but is not limited to: verifying correct equipment performance and operation, checking for diagnostic or trouble codes, measuring discharge air temps, verify amperage of all electric heating coils, verification of chilled water coils performance, verify pump operation, motor speed, and differential pressure, verify HVAC process air fan speeds, verify HVAC intake filter condition, Chiller performance operation, etc. Weekly equipment inspections shall include a technical field report identifying the status of each piece of equipment and shall include all data / measurement points verified. (CDRL A004, B004, C004).

5.3.4. The contractor shall provide a qualified service technician to cover the repair of all equipment deficiencies and malfunctions.

The response time for the repair or replacement of deficient equipment shall meet the requirements defined in section 5.2.2.

5.4. Training

5.4.1. The Contractor is responsible for and shall provide training sessions to Shipyard Personal on the operation, set-up and daily surveillance requirements. Training shall be available throughout the duration of the lease to accommodate equipment swap out and seasonal equipment operation.

5.5. In addition to all required equipment, technical documentation shall also be provided electronically to the project COR Deliverables -and Engineering. Minimally, the documentation shall consist of:

5.5.1. Lifting & Handling the equipment with its padeye(s) Certification (CDRL A001, B001, C001)

5.5.2. Points of contact with telephone numbers for requesting emergency repair regardless of the time or type of day (CDRL A002, B002, C002)

5.5.3. Technical Instructions (TIs) such as an Operations & Maintenance Manual, Controls Manual, and/or Mechanical/Electrical Manual with Schematics. (CDRL A003, B003, C003)

5.5.4. Operating Instructions, if not in the TI. (CDRL A003, B003, C003)

5.5.5. Preventative Maintenance Schedules & Weekly Maintenance Reports. (See section 5.3.2 & 5.3.3) (CDRL A006, B006, C006)

5.5.6. Equipment Data Sheet (EDS). (CDRL A003, B003, C003)

5.5.7. Hydrostatic Pressure Test Reports. (CDRL A005, B005, C005)

5.5.8. Flow meter calibration certificate. (CDRL A007, B007, C007)

6. DELIVERY / ACCEPTANCE / RETURN

6.1. - The machinery shall be in a fully-charged, fully-assembled, ready-to-use, and in a first-class-operating condition. Machines Delivery shall be functionally tested prior to its delivery and all leased products, including machine / equipment / ancillary component accompanying machine, must fully function as intended. The machinery with its support equipment shall be delivered to the site on or prior to the request date. It is incumbent and the responsibility of the Contractor to either confirm or coordinate the date and time of delivery prior to each shipment via the Point-of-Contact (POC) as designated on the Contract and/or the Contracting Officer's Representative (COR). The Government can provide forklift services for removing machinery from Contractor's transport during work hours. Documentation with Shipyard copies shall accompany each delivery.

6.2. - Upon satisfactory completion of inspection and test of the equipment, the authorized Government Acceptance

Representative (Portsmouth Naval Shipyard, Equipment Manager) will sign and forward the acceptance document(s) to the POC as designated on the Contract and/or COR for completion. Unloading of equipment from Contractor's transport does not signify acceptance.

6.3. Upon delivery, the Contractor shall: provide start up and commissioning of the equipment to verify its operability per Start Up- (i) SOW section 5.2.4; provide all deliverables as required per SOW section 5.5 and train designated Shipyard personnel on how to(ii) (iii) properly run the equipment to include its operation, control, daily checks, & service contacts per SOW sections 5.2.4.1.6 and 5.4.

6.4. To be allowed onto PNSY: Security -

6.4.1. All personnel assigned by the contractor to perform work or site visits must be US citizens. The contractor company manager will be required to submit a visit request listing information of personnel needing access aboard Portsmouth Naval Shipyard. Visit request must include the full name of the persons nationality, birth date and Social Security Number. Visit request may be in the form of a letter on company stationery with signature from company security manager or authorized company representative and faxed to the Pass and ID office at (207) 438-2669 or emailed to PNSDBIDS@US.NAVY.MIL. Company visit requests shall be submitted annually and as often as necessary to update employees of the company who need continued access to the Shipyard.

Criminal history and/or falsification of information provided by an employee of the company may be subject to denial for unescorted access up to and including general access to the Shipyard. For contractors needing short term access to the shipyard the PNSY sponsor will submit the NAVSEA LOCAL VISIT REQUEST via the PNSY homepage.

6.4.2. If employees do not have a government issued contractor CAC which will allow access to the base, a SECNAV 5512/1 will need to be filled out and brought in with them to Pass & ID in order for the individual to be vetted and granted a (DBIDS) Defense Biometric Identification System pass or credential to allow access to the base.

6.4.3. Personnel must provide two forms of ID. One of which must prove U.S. citizenship in order to access the NAVSEA Controlled Industrial Area (CIA) or any other NAVSEA spaces. Documents: a valid REAL ID compliant driver's license, passport, birth certificate or government CAC. All documents must be active. No expired documents will be accepted.

6.4.4. Badge Criteria:

6.4.4.1. Green badges will be issued to contractors who are verified U.S. citizens, have a shipyard sponsor and a verified need to provide a service or perform work at PNSY.

6.4.4.2. These badges provide unescorted access to the CIA, excluding Nuclear Work Area's (NWA's), Controlled Nuclear Information Areas (CNIA's), Security Islands (SI's) and Other Sensitive Areas (OSA)

6.4.4.3. The Standard Access Control Badge (SACB) is U.S. Government property and it must be protected and returned to Pass & ID office or Security Department upon termination of employment, completion of work, service performed, expiration of contract or no longer a need to enter NAVSEA controlled spaces.

6.4.4.4. The SACB will be displayed at the chest level area of the outer clothing with the picture side visible at all times.

6.4.4.5. No objects, pins or stickers can be attached to the badge. If the badge becomes faded, damaged or illegible for any reason the bearer will report to the Pass & ID office for a new badge.

6.4.5. Camera-enabled devices of any kind, including cell phones, laptops, and tablets, are prohibited inside the CIA. Laptops without cameras must be registered with the Security Office before entering the CIA.

6.4.6. All contractor vehicles are subject to inspection prior to allowing entry onto this installation.

6.4.7. Contractor vehicles may enter the CIA through the open CIA vehicle gate. Personal vehicles are precluded from entry. CIA access by Contractor vehicles will be kept to the absolute minimum necessary to accomplish the contracted work. All contractor vehicles must meet the following:

6.4.7.1. Possess a valid vehicle registration showing the vehicle is a company owned or leased vehicle, or rental vehicle rented by the company; a valid state safety inspection as required by the state of registration and an inspection pass from Commercial Vehicle Inspections Station (CVIS) located at the main gate.

6.4.7.2. Contractor logo should be located on both sides of the vehicle and either painted on or magnetic sign. Paper or cardboard signs are not authorized. Lettering must be a minimum of 2-inch font and displayed in a manner that is clearly visible. 6.4.7.3. Contractor vehicles will be authorized access to the CIA to deliver contractor equipment to the work site.

The use of these vehicles solely for the transport of personnel is not authorized.

6.4.8. CIA inspection passes will be issued to a contractor vehicle meeting the above criteria. CIA passes will have an expiration date, time and initials of the issuing officer. From the time of issue, the contractor vehicle must enter the CIA within 7 minutes from the time issued. Any contractor attempting to access the CIA after the 7-minute time window will be denied entry and directed back to CVIS for re-inspection.

6.5. - Equipment must meet all criteria defined in this specification. Receipt Inspection Criteria

6.6. - The Government will provide a temporary storage location convenient for Contractor pick-up. The Government will notify Return the Contractor as well as the Contracting Office as to when the rental Item has been released and is available for pick-up. The last day of the rental period shall be the next normal workday after the Contractor has been so notified. The Contractor shall be responsible for shipping. The Government can provide forklift services during work hours for placing the equipment onto the contractor's transport.

7. GENERAL

7.1. - As part of the response to this request, descriptive literature shall be furnished in sufficient detail to show that Response to Request the proposed design will meet these specifications. Contractor submittals shall include brochures of the model being submitted, assembly sketches with critical dimensions, sketches (with dimensions) of all tooling being provided, statements of compliance with specification, and performance statements with special instructions. Supporting information shall be organized and packaged by unit. If supporting information includes multiple models the contractor shall clearly state model number of proposed unit and redact all information not applicable to proposed unit.

Enclosure 1

Table E1

SOW Compliance Checklist

SOW REQUIREMENT

COMPLIANCE

WITH SOW.

(See Instructions Below)

EXCEPTIONS

TO SOW.

(See Instructions Below)

Equipment

Table 1 Equipment Specification

Table 2 Equipment Specification

Table 3 Equipment Specification

Table 4 Equipment Specification

Table 5 Equipment Specification

Table 6 Equipment Specification

Table 7 Emergency Remote Stop for Air Equip.

Section 4.1- 4.2 Chiller System Capabilities

Section 4.3 Hydrostatic Testing

Section 4.4 Phase Rotation Indication

Section 4.5-4.6 Accessories

Section 4.7 HVAC System Capabilities

Section 4.8 Construction & Weather Hardiness

Section 4.9 Electrical

Section 4.10 Lifting & Handling

Section 4.11 Noise

Section 4.12-

4.13 Tagging/Marking

Section 4.14 Electrical Safety

Section 5 (in its entirety) Deliverables

Section 6 (in its entirety) Delivery Acceptance and Return

INSTRUCTIONS

1. .COMPLIANCE WITH SOW

(i) Use or to identify if equipment and services comply with all SOW YES NO requirements.

(ii) Ensure answers are consistent with any brochures, specification sheets or other descriptive literature provided in your quote.

2. . EXCEPTIONS TO SOW

(i) Identify any exceptions to the SOW. Note, answers are required for any in prior column. (ii) Explain reason for exception. NO

Requirements Temp HVAC and Exhaust System

Additional Regulation or Supplemental Clauses Incorporated by Full Text

C-202-H001 ADDITIONAL DEFINITIONS--BASIC (Oct 2018)

(a) Department means the Department of the Navy.

(b) Commander, Naval Sea Systems Command means the Commander of the Naval Sea Systems Command of the Department of the Navy or his duly appointed successor.

(c) References to The Federal Acquisition Regulation (FAR) All references to the FAR in this contract shall be deemed to also reference the appropriate sections of the Defense FAR Supplement (DFARS), unless clearly indicated otherwise.

(d) National Stock Numbers Whenever the term Federal Item Identification Number and its acronym FIIN or the term Federal Stock Number and its acronym FSN appear in the contract, order or their cited specifications and standards, the terms and acronyms shall be interpreted as National Item Identification Number (NIIN) and National Stock Number (NSN) respectively which shall be defined as follows:

(1) . The number assigned to each approved Item Identification under the National Item Identification Number (NIIN) Federal Cataloging Program. It consists of nine numeric characters, the first two of which are the National Codification Bureau (NCB) Code. The remaining positions consist of a seven digit nonsignificant number.

(2) . The National Stock Number (NSN) for an item of supply consists of the applicable National Stock Number (NSN) four-position Federal Supply Class (FSC) plus the applicable nine-position NIIN assigned to the item of supply.

(End of Text)

C-204-H001 USE OF NAVY SUPPORT CONTRACTORS FOR OFFICIAL CONTRACT FILES (Oct 2018)

(a) NAVSEA may use a file room management support contractor, hereinafter referred to as "the support contractor", to manage its file room, in which all official contract files, including the official file supporting this procurement, are retained. These official files may contain information that is considered a trade secret, proprietary, business sensitive or otherwise protected pursuant to law or regulation, hereinafter referred to as "protected information". File room management services consist of any of the following: secretarial or clerical support; data entry; document reproduction, scanning, imaging, or destruction; operation, management, or maintenance of paper-based or electronic mail rooms, file rooms, or libraries; and supervision in connection with functions listed herein.

(b) The cognizant Contracting Officer will ensure that any NAVSEA contract under which these file room management services are acquired will contain a requirement that:

(1) The support contractor not disclose any information;

(2) Individual employees are to be instructed by the support contractor regarding the sensitivity of the official contract files;

(3) The support contractor performing these services be barred from providing any other supplies and/or services, or competing to do so, to NAVSEA for the period of performance of its contract and for an additional three years thereafter unless otherwise provided by law or regulation; and,

(4) In addition to any other rights the contractor may have, it is a third party beneficiary who has the right of direct action against the support contractor, or any person to whom the support contractor has released or disclosed protected information, for the unauthorized duplication, release, or disclosure of such protected information.

(c) Execution of this contract by the contractor is considered consent to NAVSEA's permitting access to any information, irrespective of restrictive markings or the nature of the information submitted, by its file room management support contractor for the limited purpose of executing its file room support contract responsibilities.

(d) NAVSEA may, without further notice, enter into contracts with other contractors for these services. Contractors should enter into separate non-disclosure agreements with the file room contractor. Contact the Procuring Contracting Officer for contractor specifics. However, any such agreement will not be considered a prerequisite before information submitted is stored in the file room or otherwise encumber the government.

(End of Text)

C-211-H001 ACCESS TO THE VESSEL(S) (Oct 2018)

Officers, employees and associates of other prime Contractors with the Government and their subcontractors, shall, as authorized by the Supervisor, have, at all reasonable times, admission to the plant, access to the vessel(s) where and as required, and be permitted, within the plant and on the vessel(s) required, to perform and fulfill their respective obligations to the Government. The Contractor shall make reasonable arrangements with the Government or Contractors of the Government, as shall have been identified and authorized by the Supervisor to be given admission to the plant and access to the vessel(s) for office space, work areas, storage or shop areas, or other facilities and services, necessary for the performance of the respective responsibilities involved, and reasonable to their performance.

(End of Text)

C-211-H018 APPROVAL BY THE GOVERNMENT (NAVSEA) (JAN 2019) (Jan 2019)

Approval by the Government as required under this contract and applicable specifications shall not relieve the Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.

(End of Text)

C-211-W001 REPLACEMENT PARTS AVAILABILITY (NAVSEA) (OCT 2018) (Oct 2018)

The contractor guarantees that replacement parts for each component part listed in this contract shall be available for a minimum of until the contract expires. Subsequent to this period, if parts are not available from the contractor, the contractor shall, if requested by the Government, furnish data to enable the Government to have such parts manufactured elsewhere.

(End of Text)

C-222-H001 ACCESS TO THE VESSELS BY NON-U.S. CITIZENS (NAVSEA) (APR 2019) (Apr 2019)

(a) No person not known to be a U.S. citizen shall be eligible for access to naval vessels, work sites and adjacent areas when said vessels are under construction, conversion, overhaul, or repair, except upon a finding by COMNAVSEA or his designated representative that such access should be permitted in the best interest of the United States. The Contractor shall establish procedures to comply with this requirement and NAVSEAINST 5510.2D.

(b) If the Contractor desires to employ non-U.S.

This is the start of the file's text. The full file is on GovTribe.