This Statement of Work (SOW) details the yearly maintenance requirements for two 15KW diesel generators located at the Nuclear Regional Maintenance Department Point Loma (NRMD-PL). The SOW specifies identical maintenance procedures for Generator A (#7DC5521MZM04633) and Generator B (#7DC3574MZM0634), which include replacing fuel filter cartridges, oil and oil filter cartridges, air cleaner elements, and fan belts, as well as cleaning water separators and water jackets. All replacement parts must be new OEM parts. The work will be performed on-site at NRMD-PL, with the government providing escorts and electrical connections, and the contractor responsible for executing the maintenance. The period of performance is upon contract award and annually through December 31, 2030.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (Yearly)
1. SCOPE:
1.1. This specification gives the minimum yearly requirements for service of Portsmouth’s Portable 15KW Diesel Generators A and B at Nuclear Regional Maintenance Department Point Loma (NRMD-PL).
2. APPLICABLE DOCUMENTS: None
3. REQUIREMENTS:
3.1. 15KW Generator A #7DC5521*MZM04633
3.1.1. Replace fuel filter cartridge
3.1.2. Replace oil and oil filter cartridge.
3.1.3. Replace air cleaner element.
3.1.4. Replace fan belt.
3.1.5. Clean water separator.
3.1.6. Clean water jacket (radiator interior)
3.1.7. All replacement parts shall be New OEM replacement parts.
3.2. 15KW Generator B #7DC3574*MZM0634
3.2.1. Replace fuel filter cartridge
3.2.2. Replace oil and oil filter cartridge.
3.2.3. Replace air cleaner element.
3.2.4. Replace fan belt.
3.2.5. Clean water separator.
3.2.6. Clean water jacket (radiator interior)
3.2.7. All replacement parts shall be New OEM replacement parts.
4. RESPONSIBILITIES:
4.1. Government:
4.1.1. Provide escorts as required to allow vendor to service equipment.
4.1.2. Electrically Connect equipment as required to support post service operational checks.
4.2. Contractor:
4.2.1. All work shall be performed on site at NRMD-PL.
5. DELIVERY/PERIOD OF PERFORMANCE: Upon contract award and once per year through 12/31/30.
6. GENERAL: None