N3319120R4013 Amendment 0002.pdf

PDF 144 KB Posted

Attached to
D-B Construct Additional Floor in Hematology Clinic, Skopje, North Macedonia
Solicitation number
N3319120R4013
Issued by

About this file

This solicitation amendment provides clarification to questions from potential offerors on a solicitation to construct an additional floor for a hematology clinic in Skopje, North Macedonia. The amendment separates pricing requirements into individual contract line items to allow for partial awards of separate areas, requires the awarded area to be fully operational independent of non-awarded areas, and provides a summary of an engineering report assessing the building's structural capacity.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACQR5768706

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

N3319120R4013 D-B Renovate Hematology Clinic, Skopje, North Macedonia

This solicitation amendment continues on page 2.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 19-May-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N3319120R4013

X 9B. DATED (SEE ITEM 11)

13-Apr-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

19-May-2020

CODE

NAVFAC EUROPE AFRICA CENTRAL

VIALE PORTO CAPODICHINO

NAPOLI 80144

N33191 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N3319120R4013

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0002

The purpose of the solicitation amendment is to respond to Pre-Proposal Inquiries (PPI’s)

QUESTION#1

According to Attachment 3 for Price Schedule we are requested to provide prices separately for each CLIN but according to the Textual description page 13, the areas of Isolation Rooms and Day Hospital CLIN001 need to be perfectly operational. Our concern is that it is not possible to provide separate offers as per the CLINS because the entire floor is interconnected via construction elements such as beams and concrete slabs and they all share the same installations (HVAC, Electrical, Heating which are based in the Technical Room). As an alternative, we could provide prices per separate phases instead, such as:

1. Shell construction position (includes walls, concrete works etc.)

2. Electrical installations

3. HVAC Installation

4. Water supply and sewage installations

5. Medical Gases installations etc.

Can you please review and revise this?

ANSWER TO QUESTION#1

The contractor needs to assume that the US Government may only award CLIN0001, and consequently this area needs to be fully operational without CLIN0002 or CLIN0003. However, the US Government cannot award CLIN0002 or CLIN0003 without awarding CLIN0001. To expand on this idea further:

CLIN0001 includes the design of all the works included in the Performance Technical Specification (PTS), but it includes only the construction of the Isolation Rooms and Day Hospital. It is possible that the US Government may only award this part of the building addition into the contract. In this case, the Isolation Rooms and Day Hospital areas shall be perfectly operational, but the other areas described in CLIN0002 and CLIN0003 shall not be built as part of this contract.

Paragraph 4.4 states: “The contract in its base-Bid includes the design for all portions of the contract, including the Contract Option-1 and the Contract Option-2. However, these areas and all related works shall be clearly defined as optional works. Similarly, the design shall include required elements, which are not part of the contract, as the wall mounted air conditioning equipment for the areas outside the Isolation areas, which shall be clearly marked as “NIC – Not in Contract””

It is possible that the US Government may only award CLIN0001 which shall include the complete design, and that the Government of North Macedonia may award a separate contract to a separate company to build the work included in CLIN0002 and CLIN0003.

Consequently, the schedule of prices need to be structured depending on how many CLIN’s are awarded.

If CLIN0001 is awarded, your structure is not reasonable, as you cannot include in CLIN0001 construction elements of CLIN0002 or CLIN0003 which will not be part of the contract.

If CLIN0002 is awarded, your structure for the Schedule of Prices is perfectly reasonable.

However, financially, CLIN0001 and CLIN0002 may be independent, and consequently we would need to separate them. In other words, if there is a common element, for example the electrical installation or the HVAC Installation, the Schedule of prices shall separate them by percentage. In the CLIN0001 would appear HVAC and Electrical Installation, and in CLIN0002 would also appear HVAC and Electrical Installations. There is nothing that impedes an element to be repeated in the Schedule of Prices between two or more CLIN’s.

QUESTION#2

In relation to the Addendum 0001 clarification response, we have some uncertainties regarding the report that was provided from the Civil Engineering Faculty UKIM which in a way does not guarantee if there are sufficient conditions for the construction of an additional floor with the existing structure. According to the Construction Regulation and Law of North Macedonia, the Construction permits are provided from the Reports of the competent Institutes for Civil Engineering (not the Faculty of Civil Engineering) that can guarantee the stability of the existing building. This step is crucial before conducting any construction activities or architectural design. Can you please provide a copy of the reports/tests from the Institute for Civil Engineering if any?

ANSWER TO QUESTION#2

Find the summary of the report from the Civil Engineering Faculty UKIM in the next 5 pages.

Attached seperately as enclosure 1.

(End of Summary of Changes)