This document contains the pre-proposal inquiry log and questions and answers for a solicitation seeking a Job Order Contract for construction services in the Kingdom of Bahrain and United Arab Emirates. The work includes renovation, repair, maintenance, replacement, alteration, demolition and construction tasks. The indefinite-delivery, indefinite-quantity contract has a maximum value of $75 million over a five-year period including a one-year base and four one-year options. The minimum value is $5,000. Responses were provided to clarify that quantities can be purchased in rolls or bulk, RS Means pricing should be based on national averages, subcontractor experience will not be considered, reasonable amounts of water and electricity will be provided at no cost, a project manager is not required for each task order but dedicated safety and quality control personnel are required. The proposal due date was extended to April 21, 2020.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE PROPOSAL INQUIRY LOG

SOLICITATION N33191-20-R-4003

QUESTION ANSWER AMD #

1 Will there be a SEED Task Order or a sample Task Order to properly come up with a right coefficient?

There will not be a seed project. AMD # 01

2 RFP requirement section C.4.2 says that "Quantities used on individual Task

Order proposals shall be taken from field measurement or design plans, as appropriate, without allowance for waste". Can the government accept quantities of those materials that are purchased in ROLLS or by bulk quantities instead of the exact measurement because you usually can't buy it by the exact quantity required?

Yes, rolls or other typical bulk quantities can be used.

AMD # 01

3 RFP requirement section C.4, contractor will propose a coefficients using RS

MEANS. Based on our experience, RS MEANS price varies depending on location of state in the US. Can you please which define which state in the US should we base our pricing to come up with coefficient.

RS Means pricing is based on US National average costs. Contractor proposals shall be based on the standard US National average costs listed in RS

Means with no locality factor applied.

AMD # 01

4 We intend to bid for the above mentioned project. Can an offeror utilize a subcontractor's experience to be considered for FACTOR 1, EXPERIENCE and

NON-PRICE FACTOR 4, PAST PERFORMANCE of technical proposal?

No, Subcontractors experience will not be evalutated. Please see Pg. 21 of the Soliciation. The

Government will not consider any project submitted for Factor 1 if it was performed by a firm other than the offeror and there is no supporting joint venture agreement, partnership agreement, teaming agrement, letter of commitment, or explanation of meaningful involvement.

AMD # 01

5 Page 16 of the solicitation, para 1.8 what situations would allow for a 4% performance guarantee?

A request by Offeror must be submitted for

Contracting Officer approval.

AMD # 01

6 Can we provide a surety (bond), upon award for the overall project covering several TOs or does each TO have to have its own bond?

Please see Pg. 16 of the solicitation. The offeror shall provide, within ten (10) days after award of task/delivery order equal to or greater than

$250,000, either (1) a notarized Performance

Gurantee letter, or (2) Performance and Payment bonds conforming to the requirements noted in paragraph 1.8 Performance Guarantee.

AMD # 01

7 What is the incumbent's historical coefficients? The incumbent's coefficient will not be released. AMD # 01

8 Reference C.4 COEFFICIENTS, Section C.4.2 indicates the coefficient is to include off base storage facilities and offices. Sec C.2.3, Government

Furnished Facilities, Equipment, Materials and Services states 1. Facilities. The

Government will designate a Laydown Area for contractor operations during the term of the contract. The Contractor will be responsible for providing

Administrative Space which will be located within the Laydown Area.

Question: If on-site storage and administrative space is required under a specific task order, will the cost of the storage and administrative space be part to the direct cost of the task order and not part of the coefficient?

Re: C.4 Coefficients; Costs for any off base storage and administrative facilities, if required by the contractor, shall be included in the coefficient. Re:

C2.3 Government furnished facilities; Space will be designated for laydown and administrative space.

That is all that the government will provide. Any costs associated with administrative and laydown space, whether on site or off base will be included in the contractors coefficient. No direct costs allowance will be permitted for administrative or laydown space, regardless of location. These costs must be included in the contractors coefficient.

This is considered part of the contractors overhead and a routine costs of doing business.

AMD # 01

9 RFP requirement section C.14.16 says that "NSA Passes and Badges:

Contractor employees and representatives performing work under this contract are required to be either United States citizens or documented legal residents". Please define the nationality of DOCUMENTED LEGAL RESIDENTS mentioned.

Access to NSA requires a DBIDS Badges. The requirement documentation for the DBIDS application include the following: Passport, CPR

Card (Bahrain's ID), and Resident Visa.

AMD # 02

10 We refer to section 00800- Special Contract Requirements, paragraph C.2, sub paragraph C.2.3, which states that the government will furnish water and electricity at existing outlets required for the work to be performed under the contract at no cost to the Contractor. Under the same sub paragraph C.2.3, under point 3 (Availability of Utility Sservices), it is mentioned that water and electricity will be available to the Contractor on a reimbursable basis. There is a conflict in the above statements. Kindly clarify.

Reasonable amounts of water and electricity (at existing outlets) will be made available to the

Contractor without charge. Local Utilities Energy

Management will determine what is reasonable.

The Contractor shall pay all costs incurred in connecting, converting and transferring the utilities from existing outlets to the work. The

Contractor shall be responsible for making connections, providing transformer(s), etc., and making disconnection. It is standard practice that contractors use generators at their laydown areas for their electricity.

AMD # 02

11 We refer to section 00800- Special Contract Requirements, paragraph number C.2 (Management and Administration), sub paragraph number C.2.6.

Kindly confirm if we need to provide dedicated PM, SSHO & Quality Control

Manager for each task orders running concurrently under this contract.

PM – No. QC- No, unless stated on the individual task order. SSHO- Yes they must be dedicated to the project, and cannot serve any other organizational roles.

AMD # 02

12 We refer to section 00100- Bidding Schedule / Instruction to Bidders, subsection 1.9, which states the submission date as 14th April 2020. In view of the current COVID19 pandemic, we are countering following issues: a) 50% staff loading at office which is resulting in delay of proposal compilation b)

Delayed response from suppliers for major material pricing We request for an extension to the proposal submission date by minimum two weeks.

The proposal due date is extended to 21 April

2020.

AMD # 02

13 Do the details of the coefficient need to be disclosed at any point during contract performance or proposal?

Reference page 16 of the solicitation, item #5. A bulleted list, identifying all the cost factors included in your coefficent shall be submitted as part of the price proposal.

AMD # 02

14 The RS means databook is usually provided in other solicitations for similar projects as a reference. Will that be provided?

The RS Means data will NOT be provided. It is expected and required that the contractor have the most current editions of the various RS Means databooks throughout the life of this contract. It is also available as an electronic document

(Costworks). RS Means has a variety of cost and pricing tools available for contractors that tie back into their database.