CRANE WORK PLAN REQUIREMENTS
(GUIDE LINE)
The contractor shall provide a crane work plan packet to the Contracting Officer for approval. The crane work plan shall include:
1. Crane operating permit and certificate of compliance
2. Cranes annual & quadrennial inspection
3. Copies of the operator’s medical certificate & crane operating qualifications by a source that qualifies crane operators (union, government agency, or an organization that tests and qualifies crane operators for the equipment being operated.
4. Name of the qualified person that is designated to perform rigger-in-charge duties, also the list of personnel that will perform riggers duties.
5. Copy of the load chart and data sheet for that specific crane.
6. Job site ground loading conditions with restrictions as applicable.
7. Cribbing plan if applicable.
8. Routine and critical lift plan (e.g. weights of heaviest item to be lifted, crane radius, net crane capacity, type of rigging gear, and rigging gear net capacity).
9. Listing of rigging gear to be utilized with OEM specifications
10. NOTE: tracking number is assigned to each crane package, once it has been received by the Crane Surveillance personnel. If additional information is needed for the crane package, please reference the assigned tracking number in your reply. ______________.
11. The contracting officer, if needed may request other documentations.