0902_B_DRY_DOCKING_AND_UNDOCKING_VESSEL_REV_-.docx

DOCX document 29 KB Posted

Attached to
USNS CHARLES DREW: Regular Schedule Overhaul/Dry-Docking Federal contract opportunity
Solicitation number
N32205-18-R-4252
Issued by
Department of the Navy Military Sealift Command

About this file

Revised Work Item 902

View the file

Other files for this federal contract opportunity

Other files attached to USNS CHARLES DREW: Regular Schedule Overhaul/Dry-Docking, newest first.
File Type Posted
N32205-18-R-4252_Amendment_0004.docx DOCX document
0902_B_REDOCKING_AND_UNDOCKING_VESSEL_REV.docx DOCX document
0208_A_MDG_2_AND_3_9_CYL_30000_HR_SCHEDULED_MAINTENANCE_REV1.docx DOCX document
1046_A_RAM_TENSIONER_REMOVAL_AND_REPLACEMENT.doc DOC document
1048_A_FAS_FAIRLEAD_BLOCK_REMOTELY_FED_GREASE_LINES.doc DOC document
0501_A_FIREFIGHTING_INSPECTION_AND_TESTING_(1-YR)_REV_1.doc DOC document
0207_A_MDG1_8_CYL_24000_HOUR_SCHEDULED_MAINTENANCE_11DEC17.docx DOCX document
0916_A_UNDERWATER_HULL_CLEANING_AND_PAINTING_(SPOT_BLAST_20).docx DOCX document
N32205-18-R-4252_Amendment_00003.docx DOCX document
0517_A_LTFW_COOLER_CLEANING_AND_GASKET_CHANGE_(TALT_426)_Rev1.doc DOC document
0011_A_GENERAL_SERVICES_FOR_SHIP,_T_AKE,_REV_FEB_14_Rev1.doc DOC document
0941_A_FW_Stern_Tube_Lub_System_Install_TALT_403__Rev_2_V6_SA.doc DOC document
0021_A_CLEAN_AND_GAS_FREE_TANKS_VOIDS_COFFERDAMS_AND_SPACE_REV_3.doc DOC document
J_-_2_Category_A_Items.xls XLS spreadsheet
0142_A_Tank_Coatings_Gray_WTR_and_FD_Waste_VRR17-057_Rev1.doc DOC document
N32205-18-R-4252_Amendment_0002.docx DOCX document
J_-_3_Category_B_Items.xls XLS spreadsheet
Q_AND_A_Responses_1.docx DOCX document
N32205-18-R-4252_Amendment_0001.docx DOCX document
0021_A_CLEAN_AND_GAS_FREE_TANKS,_VOIDS,_COFFERDAMS_AND_SPACE_REV_2.doc DOC document
Work_Items.zip ZIP file
J_-_14_Technical_Data_Non-Disclosure.docx DOCX document
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS CHARLES DREW

(T-AKE 10)

DRYDOCKING AND UNDOCKINGN32205-18-R-4252
13 October 2017
ITEM NO. 902Category "B"N756/SWI/JSH

DRY DOCKING AND UNDOCKING VESSEL REV -

1.0 ABSTRACT:

1.1 Continue dry-docking ship past the scheduled Contract Completion Date.

2.0 REFERENCES:

2.1 Work Item 901, Dry-Docking and Undocking Vessel

3.0 ITEM LOCATION/DESCRIPTION:

3.1 In accordance with reference 2.1 (WI 901 Dry-Docking and Undocking Vessel)

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None.

5.0 NOTES:

5.1 The Contractor and all Subcontractors, regardless of tier, must consult the General Technical Requirements (GTRs) to determine applicability to this work item. In performance of this work item, the Contractor and all Subcontractors, regardless of tier, must comply with the requirements of all applicable GTRs.

5.2 The Contractor and all Subcontractors, regardless of tier, are advised to review other work items under this contract to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in Work Item 001.

5.3 THIS SHIP CONTAINS HIGH VOLTAGE (HV) ELECTRICAL SYSTEMS. OBEY ALL POSTED AND VERBAL INSTRUCTIONS REGARDING SAFETY AND EXCLUSION FROM HIGH VOLTAGE AREAS. AT NO TIME APPROACH, WORK ON, OR ENTER A HIGH VOLTAGE AREA WITHOUT PROPER AUTHORIZATION.

5.4 THE T-AKE CLASS ELECTRICAL COLOR CODING DOES NOT FOLLOW CONSISTENT COLOR SCHEME. THE SHIP IS KNOWN TO HAVE CURRENT CARRYING CONDUCTORS COLORED GREEN, BLUE, BLACK, AND WHITE. ASSUME ALL ELECTRICAL CABLES ARE ENERGIZED UNTIL TESTED AND PROVEN OTHERWISE. TEST ALL ELECTICAL CABLES TO ENSURE THEY ARE DE-ENERGIZED PRIOR TO WORKING ON THE ITEM.

6.0 QUALITY ASSURANCE REQUIREMENTS: None additional.

7.0 STATEMENT OF WORK REQUIRED:

7.1 Submit a unit price per day and extended price for up to a maximum of fifteen (15) days to continue all services in accordance with Work Item 901.

8.0 GENERAL REQUIREMENTS:

8.1 If this CAT B Work Item is invoked, the work requirements in this work item shall be finalized and/or completed as required for meeting scheduled milestones as outlined in Work Item 013 “Project Planning and Production Status Monitoring Reports”, paragraph 7.1.7 “Milestones”.

8.2 Offers must provide both a unit price and an extended total price for accomplishing the above paragraph 7 scope of work.

902 - 1