USNS CHARLES DREW
(T-AKE-10)
| MACHINERY PROPULSION | N32205-18-R-4255 | |
| 11 DECEMEBER 2017 | ||
| ITEM NO. 207 | Category "A" | N756/SWI/SA |
8 CYLINDER MAIN DIESEL ENGINE 24,000 HOUR SCHEDULED MAINTENANCE
1.0 ABSTRACT:
1.1 This item describes the requirement to provide the technical services and industrial support to accomplish a 24,000-hour overhaul of MDG No. 1 eight cylinder main diesel engine.
2.0 REFERENCES:
2.1 T/M T9233-CF-IMC-010; Diesel Engines, Main Power Generation, Models 9L 48/60 and 8L 48/60, Volume B1, Engine Operating Instructions
2.2 T/M T9233-CF-IMC-020; Diesel Engines, Main Power Generation, Models 9L 48/60 and 8L 48/60, Volume B2, Engine Working Instructions
2.3 T/M T9233-CF-IMC-060; Diesel Engines, Main Power Generation, Models 9L 48/60 and 8L 48/60, Volumes C1, C2 &C3 , Exhaust Gas Turbocharger
3.0 ITEM LOCATION/DESCRIPTION:
3.1 Location/Quantity:
3.1.1 Location: Main Machinery Room 5-66-0
3.1.2 Quantity: No. “1” Main Diesel Engine
3.2 Item Description/Manufacturer's Data:
3.2.1 Bill of Materials:
3.3 Description of Equipment/Systems:
3.3.1 Fairbanks Morse Diesel Engine Model 8L 48/60
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES:
4.1 Government Furnished Equipment (GFE):
4.1.1 Eight (8) cylinder heads per engine.
4.2 Government Furnished Material (GFM):
4.2.1 One (1) 24K FME P/N (M12702080)8L parts kit (Same as 6k Parts Kit).
5.0 NOTES:
5.1 The contractor and all subcontractors, regardless of tier, must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTRs.
5.2 The contractor and all subcontractors regardless of tier are advised to review the other work items under this contract to determine their effect on the work required under this work item.
5.3 THIS SHIP CONTAINS HIGH VOLTAGE (HV) ELECTRICAL SYSTEMS. OBEY ALL POSTED AND VERBAL INSTRUCTIONS REGARDING SAFETY AND EXCLUSION FROM HIGH VOLTAGE AREAS. AT NO TIME APPROACH, WORK ON, OR ENTER A HIGH VOLTAGE AREA WITHOUT PROPER AUTHORIZATION.
5.4 THE T-AKE CLASS ELECTRICAL COLOR CODING DOES NOT FOLLOW CONSISTENT COLOR SCHEME. THE SHIP IS KNOWN TO HAVE CURRENT CARRYING CONDUCTORS COLORED GREEN, BLUE, BLACK, AND WHITE. ASSUME ALL ELECTRICAL CABLES ARE ENERGIZED UNTIL TESTED AND PROVEN OTHERWISE. TEST ALL ELECTICAL CABLES TO ENSURE THEY ARE DE-ENERGIZED PRIOR TO WORKING ON THE ITEM.
6.0 QUALITY ASSURANCE REQUIREMENTS: None additional.
7.0 STATEMENT OF WORK REQUIRED:
7.1 Tag-Out all required systems and equipment. Drain and dispose of any liquid in accordance with all federal, state, and local regulations.
7.2 Provide the services of the Original Equipment Manufacturer (OEM) representatives identified in paragraph 7.10.
7.3 Provide all tools required, including special tools, for accomplishment of all elements of this work item. Ship’s force will NOT provide any tools.
7.4 Accomplish the requirements associated with 18,000 operating hours as found in reference 2.1 section 4, as listed below in Table 209 – 1. Work cards are available in reference 2.2.
Table 209 – 1
| Ref 2.1 Maintenance Task Serial Number |
| Category |
| Job Description |
| Work Card |
| Scope of Work |
| 009 |
| Fuel Oil System |
| Check/overhaul buffer pistons |
| 434.04 |
| Engine # 1 |
| 017 |
| Lube Oil System |
| Check oil drainage of piston, big-end and main bearings, camshaft bearings, injection pumps and valve gear (visually) |
| none |
| Engine # 1 |
| 018 |
| Lube Oil System |
| Check oil drainage of camshaft bearings, injection pumps and valve gear in the rocker are casing (visually) |
| none |
| Engine # 1 |
| 045 |
| Compressed Air and Control air System |
| Control air system: Clean the water separator and air filter. |
| 125.10 |
| Engine # 1 |
| 073 |
| Measurement and Control Systems |
| Dismantle control Valves of the 10 and 30 bar system, replace wearing parts |
| none |
| Engine # 1 |
| 076 |
| Measurement and Control Systems |
| Check measuring system for exhaust gas temperatures |
| none |
| Engine # 1 |
| 082 |
| Engine Foundations – Pipe Connections |
| Foundation: check tension of bolts. Check parts for tight fit. |
| 012.01 |
| Engine # 1 |
| 083 |
| Engine Foundations – Pipe Connections |
| Resilient Mount: Check amount of settling of resilient elements. |
| 012.01 |
| Engine # 1 |
| 086 |
| Engine Foundations – Pipe Connections |
| Bolted connections: check for tight fit and proper preload. |
| 000.30 |
| Engine # 1 |
| 092 |
| Flexible Coupling – Turning Gear |
| Flexible Coupling: Check alignment and rubber elements |
| 000.09 |
| Engine # 1 |
| 093 |
| Flexible Coupling – Turning Gear |
| Coupling Bolts: Check for tight fit/proper preload |
| 020.02 |
| Engine # 1 |
| 112 |
| Running Gear – Crankshaft |
| Check the running gear (visually) |
| none |
| Engine # 1 |
| 113 |
| Running Gear – Crankshaft |
| Crankshaft: measure crankshaft deflection |
| 000.10 |
| Engine # 1 |
| 122 |
| Main Bearing: |
| Locating bearing: Check axial clearance |
| 021.01 |
| Engine # 1 |
| 123 |
| Main Bearing: |
| Lower one bearing cap and inspect bearing shell. Check bolt loosening pressure |
| 021.01 |
| Engine # 1 |
| 142 |
| Big-End Bearing |
| Remove and check one bearing shell. Check bolt loosening pressure. |
| 030.02 |
| Engine # 1 |
| 153 |
| Piston/Piston Pin |
| Remove, clean and check all Pistons. Measure Rings Grooves. Replace all piston rings |
| 034.01 |
034.02 050.05 -All cylinders Engine # 1.
| 154 |
| Piston/Piston Pin |
| Remove one piston pin. Check piston bush, measure the clearance |
| 034.03 |
| -One Piston, Engine # 1 |
| 155 |
| Piston/Piston Pin |
| Disassemble one piston. Clean components. Check cooling spaces and cooling passages for coke deposits. If thickness of layer exceeds 1mm, disassemble all Pistons. |
| 034.02 |
034.03 034.04 -One Piston, Engine # 1
| 163 |
| Cylinder Liner |
| Measure and rehone all cylinder liners |
| 050.02 |
050.05 -All Cylinders Engine # 1
| 172 |
| Cylinder Head |
| Remove, clean and check all cylinder heads |
| 055.02 |
| -All Cylinders Engine # 1 |
| 182 |
| Safety Valves |
| Safety Valves in Crankcase covers: Check all valves for ease of movement |
| 073.01 |
| -All cylinders MDG # 1 |
| 183 |
| Safety Valves |
| Safety valves in the cylinder heads: Remove and clean all valves. Check opening pressure |
| None |
| -All cylinders MDG #1 |
| 202 |
| Camshaft Drive |
| Check gearwheels, measure the backlash |
| 100.01 |
| Engine # 1 |
| 216 |
| Camshaft - Camshaft bearing - Cam Follower |
| Check Cams, rollers and cam follower (visually) |
| 112.02, 209.01 |
| Engine # 1 |
| 217 |
| Camshaft - Camshaft bearing - Cam Follower |
| Check bushes of cam follower on one cylinder |
| 112.02 |
| Engine # 1 |
| 218 |
| Camshaft/Camshaft bearing/Cam Follower |
| Remove two camshaft bearings, check running surface. Check pressure for loosening bearing bolts |
| 000.11 |
102.01 -Two Camshafts Bearings MDG#1
| 223 |
| Rocker arm |
| Check rocker arm bushes on two cylinders |
| 111.02 |
| -Two cylinders MDG #1 |
| 235 |
| Inlet and Exhaust Valves |
| Remove all inlet valves. Check valve rotators, replace worn parts. Check valve guides |
| 113.01 |
113.02 113.03 113.04 113.05
-All cylinder MDG #1
| 243 |
| Inlet and Exhaust Valves |
| Remove all exhaust valves. Check and regrind valve seats. Check valve guides. |
| 113.03 |
113.04 113.05 114.01 114.02
-All Cylinders MDG #1
| 263 |
| Speed Governor |
| Mechanical governor and booster servo-motor: replace oil and oil filter |
| 140.01 |
140.02 Engine # 1
| 264 |
| Speed Governor |
| Mechanical governor: Check governor drive (drive shaft and gears) |
| 140.01 |
140.02 140.03 Engine # 1
| 265 |
| Speed Governor |
| Mechanical governor: Have the governor overhauled by a special workshop |
| 140.01 |
140.02 140.03 Engine # 1
| 266 |
| Speed Governor |
| Electronic governor: check pulse transmitter for dirt and verify that spacing is correct |
| 140.01 |
140.02 140.03 Engine # 1
| 272 |
| Starting Air Pilot Valve/Starting Valve/Main Starting Valve |
| Remove and overhaul all starting air pilot valves |
| 160.01 |
| - Engine #1 |
| 274 |
| Starting Air Pilot Valve/Starting Valve/Main Starting Valve |
| Remove and overhaul all starting valves |
| 161.01 |
161.02
- Engine #1
| 275 |
| Starting Air Pilot Valve/Starting Valve/Main Starting Valve |
| Remove and overhaul main starting valve |
| 162.01 |
| Engine #1 |
| 303 |
| Fuel Injection Pump |
| Detach, disassemble and check all injection pumps together with drive and cam follower |
| 112.02 |
200.01 201.01 Engine # 1
| 305 |
| Fuel Injection Pump |
| Remove and replace all baffle screws |
| 200.01 |
200.05 Engine # 1
| 322 |
| Fuel Injection Valve |
| Remove all injection valves and check nozzle elements. Replace if necessary |
| 221.01 |
221.02 221.03 221.04 Engine # 1
7.5 Accomplish the requirements associated with 24,000 operating hours as found in reference 2.3, volume C1, section 4.7, as listed below in table 209 – 2. Work cards are available in reference 2.3 volume C2.
Table 209 - 2
| Ref 2.3 Maintenance Task Serial Number |
| Category |
| Job Description |
| Work Card |
| Scope of Work |
| 931 |
| Turbocharger |
| Clean and visually check the compressor casing, insert, diffuser and compressor wheel |
| 500.10 |
500.14 Engine # 1
7.6 All parts that are required to be IMO certified for IAPP shall be procured directly from the OEM to meet IMO requirements. These parts shall be noted and included in the service report.
7.7 Inspection/Test
7.7.1 Accomplish the requirements of section 3.4.4 (Engine Running-in) of reference 2.1.
7.7.2 Following requirements of 7.7.1, complete a 100% load test on each engine repaired for one hour.
7.8 Paint/Lagging:
7.8.1 Renew lagging where old lagging was removed. Paint all new and disturbed surfaces to match surrounding surfaces.
7.9 Preparation of Drawings:
7.9.1 Contractor shall provide both the Chief Engineer and the Port Engineer with an electronic Service Report no more than fourteen (14) days after the completion of all work. The report shall contain the following as minimum:
a Engine operating hours and Serial number.
b Photographs of the engine condition at disassembly and any unusual conditions.
c Description of any abnormal or usual conditions found during maintenance.
d Measurements taken and recorded. Both the specified value and the recorded value shall be listed in the report.
e Include comments on any defects found in arrangements for removals and lifting of engine components.
f Include a listing of any additional special tools found to be needed for successful maintenance on engine.
g Include a listing of all parts used during maintenance. The parts list shall include the Sub-Assembly drawing number and part number, the FME part number .
h Include a listing of all parts included in the parts kit or ordered and not used as well as items turned over to ship’s Force.
i Crankshaft Deflection readings found in maintenance task serial number 113 of table 209-1 and recorded on the Crankshaft Deflection Record Sheet.
j Photos of Main bearing lower cap condition on the one bearing per engine removed as accomplished in maintenance task serial number 123 of table 209-1 k Photos of Big-End Bearing shell condition on the one bearing per engine removed as accomplished in maintenance task serial number 142 of table 209-1 l Photos of pistons prior to disassembly and after disassembly as accomplished in maintenance task serial numbers 153, 154 and 155 of table 209-1 m Cylinder liner dimensions for all cylinder liners as accomplished in maintenance task serial numbers 163 of table 209-1 n Radial and axial play of the fuel pump drive cam follower rollers compared against permitted value as accomplished in maintenance task serial numbers 303 of table 209-1 o Fuel injection valve condition as accomplished in maintenance task serial numbers 322 of table 209-1
7.10 Manufacturer's Representative: Provide authorized service provider for Man 48/60 design engines. Suggested Source Point of Contact For OEM Services:
Fairbanks Morse Engine (FME) Gregg Bellows 1545 Tidelands Ave. Suite J National City, CA 91950 Gregg.Bellows@fairbanksmorse.com Office 619-477-3218 x104 Mobile 858-414-6996 Or Fairbanks Morse Engine (FME) Brad Clouse 981 Scott Street Norfolk, VA 23502 Brad.Clouse@fairbanksmorse.com Office 757-623-2711 x1004 Mobile 757-335-2498
8.0 GENERAL REQUIREMENTS: None additional