J-3_Contractor_Price_Breakdown_CAT_B_WIs.xlsx

XLSX spreadsheet 27 KB Posted

Attached to
USNS ZEUS FY19 ROH/DD AVAILABILITY Federal contract opportunity
Solicitation number
N3220518R4151
Issued by
Department of the Navy Military Sealift Command

About this file

J-3 Contractor Price Breakdown CAT B WIs

View the file

Other files for this federal contract opportunity

Other files attached to USNS ZEUS FY19 ROH/DD AVAILABILITY, newest first.
File Type Posted
J-2_Contractor_Price_Breakdown_Cat_A_WIs_Rev_4.xlsx XLSX spreadsheet
N3220518R4151_Amendment_00008.docx DOCX document
J-3_Contractor_Price_Breakdown_CAT_B_WIs_Rev_2.xlsx XLSX spreadsheet
N3220518R4151_Amendment_0007.docx DOCX document
J-3_Contractor_Price_Breakdown_CAT_B_WIs_Rev_2.xlsx XLSX spreadsheet
N3220518R4151_AMENDMENT_0006.docx DOCX document
N3220518R4151_Amendment_0006_Conform_Copy.docx DOCX document
N3220518R4151_Amendment_0005.docx DOCX document
N3220518R4151-0003.docx.pdf PDF
N3220518R4151-0002.pdf PDF
N3220518R4151-0001.pdf PDF
CDRL,_SWI-0012.pdf PDF
USNS_ZEUS_FY19_ROH_JA_Redacted.pdf PDF
CDRL,_SWI-0017.pdf PDF
CDRL,_SWI-0016.pdf PDF
CDRL,_SWI-0010.pdf PDF
CDRL,_SWI-004.pdf PDF
CDRL,_SWI-0014.pdf PDF
CDRL,_SWI-0015.pdf PDF
J-11_Dry_Dock_Evaluation_Form.docx DOCX document
J_-_9_Disclosure_of_Lobbying_Activities.doc DOC document
CDRL,_SWI-006.pdf PDF
CDRL,_SWI-0018.pdf PDF
CDRL,_SWI-0020.pdf PDF
J-14_Technical_Data_Non-Disclosure.docx DOCX document
CDRL,_SWI-001.pdf PDF
J-7_MSC_Ship_Repair_Facility_Survey.docx DOCX document
J-4_GFM_List.pdf PDF
J-13_Past_Performance_Questionnaire.docx DOCX document
CDRL,_SWI-0013.pdf PDF
J_-_8_Request_for_Specification_Clarification.doc DOC document
J-15_Non-Mariner_Maintenance_Contractor_Vetting_Sheet_(Rev_8_(v4)_20_Sep_2017).xlsx XLSX spreadsheet
CDRL,_SWI-0021.pdf PDF
J12_Past_Performance_Data.doc DOC document
CDRL,_SWI-0022.pdf PDF
J-2_Contractor_Price_Breakdown_Cat_A_WIs.xlsx XLSX spreadsheet
CDRL,_SWI-0024.pdf PDF
J-10_Interport_Differentials.docx DOCX document
N3220518R4151_.pdf PDF
CDRL,_SWI-0023.pdf PDF
CDRL,_SWI-0019.pdf PDF
ZEUS_ROH_-_SOURCES_SOUGHT.doc DOC document
Show all 42

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cat B Items

USNS ZEUS (T-ARC 7) CONTRACTOR PRICE BREAKDOWN N32205-18-R-4151

CATEGORY “B” ITEMS
GENERAL REQUIREMENTPrice / TankQTYUIUnit PriceTotalPRIME ContractorSUB ContractorGovt Mandated Tech Rep / SubOTHER COSTSTOTAL PRICE
ITEM NO.TITLE CAT B ITEMPRIME L/HLABOR PRICEMATERIAL PRICESUB L/HLABOR PRICEMATERIAL PRICEGovt Mand TR/Sub PriceOTHER COSTSTOTAL LABOR HOURSTOTAL MATERIAL
CATEGORY "B" ITEMS
25PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY
7.11COST TO ESTABLISH PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY IN FORCE PROTECTION CONDITION CHARLIE1DAY
7.12COST TO ESTABLISH PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY IN FORCE PROTECTION CONDITION DELTA1DAY
7.11COST TO MAINTAIN PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY IN FORCE PROTECTION CONDITION CHARLIE1DAY
7.12COST TO MAINTAIN PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY IN FORCE PROTECTION CONDITION DELTA1DAY
WI 025 SUBTOTAL
30CONTINUATION OF SERVICES
7.1Overhaul Management Team15DAY
7.2General Services For The Ship15DAY
7.3Telephone Services15DAY
7.4Project Planning and Monitoring15DAY
7.5Fire Protection and Ship's Safety15DAY
7.6Shipboard Access and Security15DAY
7.7Gas Free Certificates15DAY
WI 030 SUBTOTAL
113Misc Steel Replacement
911Dry Dock Extension
7.1Submit unit price per day up to a maximum of fourteen (14) days to conitnue services in accordance with WI 90114DAY
913Propulsion Shaft Bearing Inspection

Total Category "B" Items - 0 $0.00 $0.00 - 0 - 0 - 0 - 0 - 0 - 0 - 0 - 0

USNS ZEUST (T-ARC 7)CONTRACTOR PRICE BREAKDOWN
&"Arial,Bold"CATEGORY "A" ITEMSN32205-19-R-4151

ATTACHMENT J-2

Sheet1

302$ 62,880
303$ 54,200
503$ 74,080
509$ 20,880
510$ 2,022
514$ 17,200
602$ 59,540
$ 290,802
701Crane, Forklift, Rigging and JLG Support Services$ 47,280
702Replace Horizontal Roller$ 37,200
703Bow Trolley Hoist Removal to Replace$ 20,400
704Relocate ISO Container Pads$ 16,080
705Antenna Mast Mods (T-Alt$ 215,000
706Splice Shop Upgrades (T-Alt-T-ARC-16-010)$ 192,605
707Install Line Conditioner in 460V$ 11,050
708Refurbish Umbulical Chutes$ 16,650
709HIPAP Upgrade (T-Alt-T-ARC-18-XXX)$ 469,850
710ADCP Removal and Install$ 47,100
711Sponsor Communictions Network Upgrade Support$ 37,100
SPONSOR AGR HOURS 1,000 HOURS @ $55.00/HR1800$ 99,00001800099000
SPONSOR ADDITIONAL ODC$ 50,0000500000050000
18% MARKUP ON ODC$ 9,00009000009000
Total$ 1,268,315