1003_A_SLIDING_BLOCK_RUBBER_BUMPER_REPLACEMENT.doc
DOC document 37 KB Posted
- Attached to
- USNS MEDGAR EVERS (T-AKE 13) REGULAR OVERHAUL/DRYDOCKING (ROH/DD) Federal contract opportunity
- Solicitation number
- N32205-14-R-3004
About this file
WI 1003
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USNS MEDGAR EVERS
(T-AKE 13)
UNREP GEAR
N32205-14-R-3004 17 Apr 2014
ITEM NO. 1003 CATEGORY “A” NSWCPHD/WCS/BVV
SLIDING BLOCK RUBBER BUMPER REPLACEMENT
1.0
ABSTRACT
1.1 This item describes the replacement of the sliding block transfer head rubber bumpers.
2.0
REFERENCES:
2.1 NAVSEA DWG 5363357, Bumper, Transfer Head
2.2 NAVSEA DWG 5210545, Standard Painting Procedures for UNREP Equipment
3.0
ITEM LOCATION/DESCRIPTION
3.1
LOCATION/QUANTITY
3.1.1 Location: Station 2, AND 6
3.1.2 Quantity: 4 Rubber Bumpers
4.0 CONTRACTOR FURNISHED EQUIPMENT/MATERIAL/SERVICES:
4.1 Contractor Furnished Equipment (CFE): None
4.2 Contractor Furnished Material (CFM):
Part Part No./NSN
QTY
BUMPER 5363357/5340-01-325-7090 4
NUT, SELF-LOCKING, HEX MS17830-8C/5310-00-411-4385 20
WASHER, FLAT
MS15795-818/5310-01-465-0892 20
5.0 NOTES:
5.1 The contractor and all subcontractors regardless of tier shall consult the General Technical Requirements (GTR) to determine their effect on the work items in this work package, which may be effected by the requirements of this item.
5.2 The contractor and all subcontractors, regardless of tier, are advised to review the other Work Items under this contract to determine their effect on the work required under this Work Item.
6.0 QUALITY ASSURANCE REQUIREMENTS: None additional.
7.0
STATEMENT OF WORK REQUIRED
7.1 Arrangement/Outfitting:
7.1.1 Position the sliding blocks at lower stop position using the control booth sliding block master control.
7.2 Structural: None additional
7.3 Mechanical/Fluid:
7.3.1 Remove sliding block transfer head rubber bumpers from transfer head rubber bumper retainers.
7.3.2 Drill and cut each bumper in accordance with reference 2.1
7.3.3 Remove and replace all missing or deteriorated mounting studs. Expect 30% of studs will require replacement.
7.3.4 Mechanically clean to SSPC-SP 3 and paint bumper channels and surrounding areas in accordance with reference 2.2.
7.3.5 Install new rubber bumpers using new fasteners.
7.4 Electrical:
7.4.1 Turn sliding block motor controller circuit breaker switch to OFF position and tag controller "OUT OF SERVICE".
7.4.2 Upon completion of this item switch sliding block motor controller circuit to ON position and remove "OUT OF SERVICE" tag.
7.5 Electronics: None additional.
7.6 Preparation of Drawings: None additional.
7.7 Inspection/Test:
7.7.1 Final inspection shall be conducted by MSC Representative.
7.8 Painting:
7.8.1 Scale, prime and finish paint area underneath each bumper assembly. Paint all new and disturbed areas to match surrounding surfaces.
7.9 Marking: None additional.
7.10 Manufacturers Representative: None
8.0 GENERAL REQUIREMENTS: None additional.