1003_A_SLIDING_BLOCK_RUBBER_BUMPER_REPLACEMENT.doc

DOC document 37 KB Posted

Attached to
USNS MEDGAR EVERS (T-AKE 13) REGULAR OVERHAUL/DRYDOCKING (ROH/DD) Federal contract opportunity
Solicitation number
N32205-14-R-3004
Issued by
Department of the Navy Military Sealift Command

About this file

WI 1003

View the file

Other files for this federal contract opportunity

Other files attached to USNS MEDGAR EVERS (T-AKE 13) REGULAR OVERHAUL/DRYDOCKING (ROH/DD), newest first.
File Type Posted
14-R-3004_Amend_0006.doc DOC document
0021_A__AMENDMENT_CLEAN_AND_GAS_FREE_TANKS_VOIDS_AND_COFFERDAMS_REV_OCT_2012.doc DOC document
N322205-14-R-3004_Amend_0005.doc DOC document
0302_A_HV-SS-EMERGENCY_SWITCHBOARD_CLEANING_Rev_1.doc DOC document
JA_N104-14-R-3004_USNS_MEDGAR_EVERS_ROHDD_Amend_00005.doc DOC document
JA_N104-14-R-3004_USNS_MEDGAR_EVERS_ROHDD_Amend_0001_Redacted.pdf PDF
N32205-14-R-3004_USNS_MEDGAR_EVERS_ROHDD_WORK_ITEM_INDEX_REV_2.doc DOC document
N32205-14-R-3004_0004.doc DOC document
J-2_Category_A_Items_Rev_2.xls XLS spreadsheet
N32205-14-R-3004_0003.doc DOC document
0519_A_ANCHOR_WINDLASS_SHAFT_BUSHING_REPLACEMENT.doc DOC document
J-3_Category_B_Items_Rev_2.xlsx XLSX spreadsheet
J-2_Category_A_Items_Rev_1.xls XLS spreadsheet
N32205-14-R-3004_0002.doc DOC document
Q_AND_A_No._3.docx DOCX document
0902_A__PROPELLER_SHAFT_AND_STERN_TUBE_INSPECTION_Rev_1.doc DOC document
N32205-14-R-3004_0001.doc DOC document
INDEX_-DRYDOCK_USNS_MEDGAR_-Aug__2014_Rev_1.doc DOC document
J_-_3_Category_B_Items_Rev_1.xlsx XLSX spreadsheet
Q_AND_A_No._2.docx DOCX document
Q_AND_A_No._1.docx DOCX document
N32205-14-R-3004_Work_Items_1-16.zip ZIP file
N32205-14-R-3004_Work_Items.zip ZIP file
J_ATTACHMENTS_N32205-14-R-3004.zip ZIP file
JA_N104-14-R-3004_USNS_MEDGAR_EVERS_ROHDD_Redacted.pdf PDF
N32205-14-R-3004.doc DOC document
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS MEDGAR EVERS

(T-AKE 13)

UNREP GEAR

N32205-14-R-3004 17 Apr 2014

ITEM NO. 1003 CATEGORY “A” NSWCPHD/WCS/BVV

SLIDING BLOCK RUBBER BUMPER REPLACEMENT

1.0

ABSTRACT

1.1 This item describes the replacement of the sliding block transfer head rubber bumpers.

2.0

REFERENCES:

2.1 NAVSEA DWG 5363357, Bumper, Transfer Head

2.2 NAVSEA DWG 5210545, Standard Painting Procedures for UNREP Equipment

3.0

ITEM LOCATION/DESCRIPTION

3.1

LOCATION/QUANTITY

3.1.1 Location: Station 2, AND 6

3.1.2 Quantity: 4 Rubber Bumpers

4.0 CONTRACTOR FURNISHED EQUIPMENT/MATERIAL/SERVICES:

4.1 Contractor Furnished Equipment (CFE): None

4.2 Contractor Furnished Material (CFM):

Part Part No./NSN

QTY

BUMPER 5363357/5340-01-325-7090 4

NUT, SELF-LOCKING, HEX MS17830-8C/5310-00-411-4385 20

WASHER, FLAT

MS15795-818/5310-01-465-0892 20

5.0 NOTES:

5.1 The contractor and all subcontractors regardless of tier shall consult the General Technical Requirements (GTR) to determine their effect on the work items in this work package, which may be effected by the requirements of this item.

5.2 The contractor and all subcontractors, regardless of tier, are advised to review the other Work Items under this contract to determine their effect on the work required under this Work Item.

6.0 QUALITY ASSURANCE REQUIREMENTS: None additional.

7.0

STATEMENT OF WORK REQUIRED

7.1 Arrangement/Outfitting:

7.1.1 Position the sliding blocks at lower stop position using the control booth sliding block master control.

7.2 Structural: None additional

7.3 Mechanical/Fluid:

7.3.1 Remove sliding block transfer head rubber bumpers from transfer head rubber bumper retainers.

7.3.2 Drill and cut each bumper in accordance with reference 2.1

7.3.3 Remove and replace all missing or deteriorated mounting studs. Expect 30% of studs will require replacement.

7.3.4 Mechanically clean to SSPC-SP 3 and paint bumper channels and surrounding areas in accordance with reference 2.2.

7.3.5 Install new rubber bumpers using new fasteners.

7.4 Electrical:

7.4.1 Turn sliding block motor controller circuit breaker switch to OFF position and tag controller "OUT OF SERVICE".

7.4.2 Upon completion of this item switch sliding block motor controller circuit to ON position and remove "OUT OF SERVICE" tag.

7.5 Electronics: None additional.

7.6 Preparation of Drawings: None additional.

7.7 Inspection/Test:

7.7.1 Final inspection shall be conducted by MSC Representative.

7.8 Painting:

7.8.1 Scale, prime and finish paint area underneath each bumper assembly. Paint all new and disturbed areas to match surrounding surfaces.

7.9 Marking: None additional.

7.10 Manufacturers Representative: None

8.0 GENERAL REQUIREMENTS: None additional.

1003-1