Question 52 - 54.doc
DOC document 23 KB Posted
- Attached to
- Air Vehicle Modification and Instrumentation (AVMI) Federal contract opportunity
- Solicitation number
- N00421-11-R-0055
About this file
Questions and Answers 5 - Questions 52-54
View the file
Other files for this federal contract opportunity
Show all 50
Air Vehicle Modification and Instrumentation (AVMI) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AVMI – SOLICITATION N00421-11-R-0055 – QUESTION COMPILATION
08 Aug 2012
52. Reference Attachment P2 Workforce Hour Matrix
-Ref the “FAR 52.217-8 Option to Extend Services - If invoked” column. Is there a set %, Hours, months, etc that should be entered in this column? The instructions do not cover this.
Clause 52.217-8 refers to an extension not to exceed 6 months.
- is the Option Year 4 column necessary?
53. Reference Clause 52.217-9—Option to extend the term of the contract.
Should para (c) read …shall not exceed 54 months?
Government Response: Attachment P-2 has been revised to delete columns referencing Option Yr IV and Option to Extend. FAR Clause 52.217-8 addresses the six (6) months in question. FAR Clause 52.217-9 paragraph (c) is correct as stated.
54. The changes to Amendment 2 in section L’s Table I with labor hours matrix are not consistent with P6.
Government Response: Table I has been revised to conform to Attachment P6
File details come from the government source that posted it. Updated .