Quality Assurance Provisions

View the file

Other files

File Type Posted
Amendment0001.pdf PDF
GWSRP_-_PERSONNEL_QUALIFICATIONS.docx DOCX document
DD254N0017416R0001.pdf PDF
PastPerformanceQuestionnaireSept2013.doc DOC document
GWSRP_-_CSF_rev2.xlsx XLSX spreadsheet
SanDiegoWGD.pdf PDF
Appendix_H_TS9090-310G_Approved_2015-2-12.pdf PDF
ContractAdministrationPlanSolicitation.doc DOC document
MIL-STD-31000.pdf PDF
Waterfront_Services_-_GWSRP_CDRLS_7-13-12_S.pdf PDF
MIL-STD-129P_Military_Marking_for_Shipment_ _Storage.pdf PDF
N0017416R0001Final.pdf PDF
PastPerformanceMatrixrev3.doc DOC document
NorfolkWGD.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

H. Quality Assurance Surveillance Plan (QASP)

1. PURPOSE

This Quality Assurance Surveillance Plan (QASP) is a Government developed and applied document used to ensure systematic quality assurance methods are used in this performance based service contract. The Contractor shall perform in accordance with the QASP performance metrics, and the Government shall receive the quality of services identified in the contract. A properly executed QASP will assist the Government in achieving the objectives of this acquisition.

This contract provides labor, material, and services required to support the Gun Weapon System Repair Program (GWSRP) in removal, installation, refurbishment, Fleet Technical Assistance and Fleet Maintenance, and Modernization of various Gun Weapon System (GWS) Equipment, Ancillary/Support Equipment under the cognizance of the GWSRP Program. The resulting performance based contract will have cost plus fixed fee Labor CLINs, and cost only Other Direct Cost (ODC) CLINs. The period of performance for this contract will cover a base period and two (2) option periods for a total of three (3) years. A properly executed QASP will assist the Government in achieving the overall objectives of this procurement.

2. AUTHORITY

Authority for issuance of this QASP is provided under Contract Section E – Inspection and Acceptance, which provides for inspection and acceptance of the services and documentation called for in service contracts, to be executed by the Contracting Officer or a duly authorized representative.

3. SCOPE

The QASP is put in place to provide Government surveillance and oversight of the Contractor’s efforts to assure that they are timely, effective and are delivering the results specified in the contract.

The Contractor’s performance on this contract will be evaluated by the Government as described below and summarized in the Contractor Self-Assessment Milestone Chart. The first evaluation will cover the period ending six months after date of contract award, with successive evaluations being performed for each twelve month period thereafter, until the Contractor completes performance under this contract. The evaluation will encompass all work performed by the Contractor during the assessment period, but will not include cumulative information from prior assessments. The Contractor will complete a self-assessment of the work performed, to be delivered to the Contracting Officer’s Representative (COR) and the Contract Administrator, as identified in the contract, No Later Than (NLT) 60 days after the end of the assessment period. The self-assessment shall cover all areas of the Government QASP. Based on the evaluation results, provided by the COR and the Contract Administrator, the Contracting Officer will assign an overall performance rating. If the Contracting Officer assigns an “Unsatisfactory” performance rating for the period evaluated, the next option period will not be exercised. A final assessment shall be completed by the Government within four months of the completion date of the contract (inclusive of all exercised options).

CONTRACTOR SELF-ASSESSMENT MILESTONE CHART

BASE

OPTION I

OPTION II

CLOSE

Month 1
*PD 1
Month 1
PD 2
Month 1
PD 3
PD 4
Month 1

Month 2

Month 2

Month 2

Month 2

Month 3

Month 3

Month 3

Month 4

Month 4

Month 4

Month 5

Month 5

Month 5

Month 6

Month 6

Month 6

Month 7
PD 2
Month 7
PD 3
Month 7
PD 4

Month 8

Month 8

Month 8

Month 9

Month 9

Month 9

Month 10

Month 10

Month 10

Month 11

Month 11

Month 11

Month 12

Month 12

Month 12

Contractor Self Assessment Reporting Due Date

*PD = Period

4. GOVERNMENT RESOURCES AND RESPONSIBILITIES

The following Government resources shall have responsibility for the implementation of this QASP:

Procurement Contracting Officer – The Procurement Contracting Officer (PCO) ensures performance of all necessary actions for effective contracting, ensures compliance with the terms of the contract and safeguards the interest of the United States in the contractual relationship. It is the PCO that assures the Contractor receives impartial, fair and equitable treatment under the contract. The PCO is ultimately responsible for the final determination of the adequacy of the Contractor’s performance. The PCO for this contract is identified in Section G.

Contract Administrator – An individual assigned by the PCO to assist in the daily administration of the contract. The Contract Administrator also provides input to the PCO and the COR as to the quality of performance for areas addressed in this QASP. The Contract Administrator for this contract is identified in Section G.

Contracting Officer’s Representative – The Contracting Officer’s Representative (COR) is responsible for technical administration of the contract and assures proper Government surveillance of the Contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any changes on the Government’s behalf. Any changes that the Contractor deems may affect contract price, terms or conditions shall be referred to the PCO for action.

Government Technical Point of Contact – The COR designates an individual Government Technical Point of Contact (TPOC) to assist in administering specific projects under the contract. The Government TPOC is responsible for assisting in administering a specific project under the contract. A Government TPOC cannot, in any manner, alter the scope of the contract, make commitments or authorize any changes on the Government’s behalf.

5. METHODS OF QA SURVEILLANCE

a. QASP – The below listed methods of surveillance shall be used by the COR in the technical administration and the PCO/Contract Specialist in non-technical administration of this QASP. The QASP will be the prime determinant in exercising the option.

b. Contractor Performance Assessment Report System (CPARS) – The market place for information technology, engineering, and management support services is very competitive. As such, the successful offeror has a vested interest in the Government generated CPARS under this contract. Additionally, an evaluation using the CPARS format will be performed at the end of each year of performance. This evaluation will be one determinant in exercising an option. For this procurement, the Government will address the quality of product or service, schedule, cost control, business relations, management, and other important areas. As this information may affect future source selections throughout DoD, and the continuation of the contract, the annual Government assessment will be used appropriately as an additional performance oversight and communication tool with the QASP.

6. DOCUMENTATION

In addition to providing annual reports to the Contracting Officer, the COR will maintain a complete Quality Assurance file. The file will contain copies of all reports, evaluations, recommendations, and any actions related to the Government’s performance of the quality assurance function. The COR shall forward these records to the Contracting Officer at termination or completion of the contract.

7. SURVEILLANCE

The tables below set forth the performance ratings, standards, outcome and surveillance methods to document the results of the surveillance on an annual basis, as well as interim and informal reviews (i.e., In-Process Reviews (IPRs)) on a more frequent basis.

(a) Performance Ratings: The Government will evaluate the Contractor’s performance of the Performance Work Statement (PWS) and the Contracting Officer will assign one of the following ratings:

(1) Excellent

(2) Satisfactory

(3) Unsatisfactory

The standards associated with these ratings are given in the following Table 1:

Table 1: Overall Performance Ratings

Overall Performance Rating
Standard
Excellent
“Excellent” ratings for all performance evaluation criteria.
Satisfactory
A minimum of “Satisfactory” ratings for all performance evaluation criteria.
Unsatisfactory
A rating of “Unsatisfactory” for one or more performance evaluation criteria.

(b) Objectives/Determination

1. Interim/Informal

Interim/Informal performance evaluations will be provided to assess performance at each IPR.

2. Annual

The PCO will make a performance determination at the end of each evaluation period. The determination will be based upon the COR’s recommendations, the Contractor’s comments, including any Self-Evaluation Report, and any other information deemed relevant by the PCO. The PCO shall resolve disagreements between the COR’s recommendations and the Contractor’s comments/report regarding the evaluation. The PCO’s performance determination is unilateral and final. The PCO will document the determination and provide a copy to the Contractor within 30 days of receipt of the Contractor’s self-assessment.

Table 2: Objectives

Assessment Period
Acceptable Performance Definition
Assessment Method
Outcome
First 6 Months of the Base Period of the contract (Period 1)
All measurement areas rated at least “Satisfactory”
Using the QASP evaluation criteria set forth in the contract.
(+) Meets the acceptable performance definition as condition for exercise of Option 1.*

(-) Does not meet the acceptable performance definition as a condition for exercise of Option I.*

Last 6 months of Base Period and the first 6 months of Option I (Period 2)
All measurement areas rated at least “Satisfactory”
Using the QASP evaluation criteria set forth in the contract.
(+) Meets the acceptable performance definition as condition for exercise of Option 2.*

(-) Does not meet the acceptable performance definition as a condition for exercise of Option II.*

Last 6 months of Option I and all of Option II

(Period 3)

All measurement areas rated at least “Satisfactory”
Using the QASP evaluation criteria set forth in the contract.
Final QASP Rating

*The Government will not exercise the next option period term unless the Contractor meets the acceptable performance definition.

(c) Performance Evaluation Criteria. The Contractor’s performance will be evaluated using the criteria and standards provided for each objective and identified in Tables 3 through 5 of this contract QASP.

(d) Organization. The performance evaluation organization consists of the PCO, who will serve as the

Determining Official, and the COR. In some instances, a TPOC will be assigned to the contract in addition to the COR.

(e) This performance evaluation does not replace any other requirement for evaluating Contractor performance that may be required by this contract such as a Contractor Performance Assessment Reporting System (CPARS) report or other required reports.

Table 3: Task Performance Evaluation Criteria and Standards

Criterion
Unsatisfactory
Satisfactory
Excellent
Task Performance
Work product fails to meet Acceptable Quality Levels (AQLs) defined in Performance Requirements Summary Table (4).
Work product routinely meets Acceptable Quality Levels (AQLs) defined in Performance Requirements Summary Table 4.
Work product frequently exceeds Acceptable Quality Levels (AQLs) defined in Performance Requirements Summary Table 4.
Staffing
Contractor provides marginally qualified or unqualified personnel. Lapses in coverage occur regularly.
Contractor provides qualified personnel. Lapses in coverage may occasionally occur and are managed per individual contract policy.
Contractor provides highly qualified personnel. Contractor reassigns personnel to ensure proper coverage. Actual lapses in coverage occur very rarely, if ever, and are managed per contract policy. Contractor ensures staff training remains current.
Timeliness
Contractor frequently misses deadlines, schedules, or is slow to respond to government requests or is non-responsive to government requests.
Contractor routinely meets deadlines, schedules, and responds quickly to government requests.
Contractor always meets deadlines, schedules, and responds immediately to government requests.
Customer Satisfaction
Fails to meet customer expectations.
Meets customer expectations.
Exceeds customer expectations to the benefit of the overall tasking.

Table 4: Performance Requirements Summary Table

SOW Task Area

Performance Objective

Performance Standard

Acceptable Quality Level

Quality Assurance Surveillance Plan Typical Monitoring Methods

4.1

SCHEDULE AND WORK SITES

The Contractor shall provide qualified personnel for specific periods or intermittently as scheduled by the Gun Weapon System Repair Program (GWSRP) PM. Specific periods are defined as those periods during the ship’s scheduled availability, in which work may be accomplished. Intermittently is defined as those periods requiring an as needed basis, not limited to the scheduled availability. The actual work windows for work package accomplishments will be coordinated with the Contractor after they are made available to the GWSRP PM. Contractor personnel shall be available to work in a private/public shipyard, pier-side or at sea underway.
Availability and responsiveness of Contractor personnel meets or exceeds GWSRP requirements. Support delivered IAW agreed upon schedules.
Personnel availability and responsiveness requires no more than two (2) review/comment/approval cycles, to meet acceptance. 90% include comprehensive recommendations proposed to allow for expeditious Government action. 95% completed by due date.
Government oversight of review/comment/ approval process, timeliness and review of availability and responsiveness.

4.2

REFURBISH-MENT

Contractor personnel shall assist the GWSRP representatives, (SSA) or RMC Team Leaders in the removal/installation, refurbishment, fleet technical assistance/maintenance, and fleet modernization of the various weapon systems and equipment within the cognizance of the GWSRP program.

Refurbishment includes adequate skill and ability to clearly identify and execute required maintenance. Current DoD policy and/or industry standards are followed. Results delivered IAW agreed upon schedules.
Refurbishment requires no more than two (2) review/comment/approval cycles, to meet acceptance. 90% include comprehensive recommendations proposed to allow for expeditious Government action. 95% completed by due date.
Government oversight of review/comment/ approval process, timeliness and review of methods, procedures and resultant maintenance and upgrades.

4.3

REFURBISH-MENT TOOLS AND EQUIPMENT

The Contractor personnel shall supply tools and equipment normally associated with the removal, installation, and refurbishment of GWSRP GWS Equipment.
Tools and equipment are appropriate and adequate to complete required removal, installation and refurbishment. Current DoD policy and/or industry standards are followed. Hardware is delivered IAW agreed upon schedules.
Tooling requires no more than two (2) review/comment/approval cycles, to meet acceptance. 90% include comprehensive recommendations proposed to allow for expeditious Government action. 95% completed by due date.
Government oversight of review/comment/ approval process, timeliness and review of tooling appropriateness and adequacy.

4.4

HAZMAT STORAGE AND DISPOSAL

The Contractor shall be required to dispose of all hazardous waste associated with the removal, installation, and refurbishment of GWSRP GWS Equipment. The Contractor shall be required to meet all Government Regulations (Federal, State, Local Government and Ship Yard Regulations) related to storage and disposal of hazardous waste.
HAZMAT is shipped, stored and disposed of IAW applicable laws and regulations
Methods and documentation requires no more than two (2) review/comment/approval cycles, to meet acceptance. 90% completed by due date.
Government oversight of review/ comment/approval cycle.

4.5

OTHER SERVICES

The Contractor shall provide services (when they are not supplied by the Pierside or Shipyard activities via a Statement of Understanding (SOU) or similar correspondence) to include but are not limited to AC power 60/400 Hz, single or 3 phase, temporary lighting and ventilation, painting, crane lifts, shipping/receiving, packing/crating, burning/welding, and 100 psi compressed dry air.
Equipment and responsiveness of Contractor personnel meets or exceeds GWSRP requirements. Support and equipment delivered IAW agreed upon schedules and plans comply with current DoD policy and/or industry standards.
Equipment support requires no more than two (2) review/comment/approval cycles, to meet acceptance. 90% completed by due date.
Government oversight of review/ comment/approval cycle.

4.6

GWS EQUIPMENT POST REMOVAL

After the removal, temporarily or permanently, of GWS Equipment, major or minor assemblies, ancillary/support equipment, the contractor shall cover, secure, and protect all mounting bases, foundations, flanges, and support brackets as directed by GWSRP PM or designee.

Responsiveness and support meets or exceeds GWSRP requirements. Support and resultant equipment protection IAW agreed upon schedules and comply with current DoD policy and/or industry standards
Support requires no more than two (2) review/comment/approval cycles, to meet acceptance. 90% completed by due date.
Government oversight of review/ comment/approval cycle.

5.0

REPORTING REQUIREMENTS

The contractor shall deliver all CDRLs according to their individually required timeframes listed in the form 1423s.
Support is provided in a technically sound manner that complies with all Government direction, applicable regulations, CDRLs and policies.

Requirements are completed within the established timeframe.

Documentation requires no more than two (2) review/comment/approval cycles, to meet acceptance. 90% completed by due date.
Government oversight of review/ comment/approval cycle.

Table 5 entitled: “COST EFFICIENCY PERFORMANCE EVALUATION CRITERIA AND STANDARDS”, shall be included when the contract will be cost-reimbursable.

TABLE 5: COST EFFICIENCY PERFORMANCE EVALUATION CRITERIA AND STANDARDS

CRITERION
UNSATISFACTORY
SATISFACTORY
EXCELLENT
Cost Management
Contractor routinely fails to complete the effort within the originally agreed to estimated cost, i.e. cost overruns frequently occur.
Contractor routinely completes the effort within the originally agreed to estimated cost. Contractor provides measures for controlling all costs at estimated costs. Funds and resources are generally used in a cost-effective manner. No major resource management problems are apparent.
Reductions in direct costs to the Government below contract estimated costs are noteworthy. Contractor provides detailed cost analysis and recommendations to Government for resolution of problems identified. Funds and resources are optimally used to provide the maximum benefit for the funds and resources available. Documented savings are apparent.
Cost Reporting
Reports are generally late, inaccurate, incomplete or unclear.
Reports are timely, accurate, complete and clearly written. Problems and/or trends are addressed, and an analysis is also submitted.
Reports are clear, accurate, and pro-active. Problems and/or trends are addressed thoroughly, and the Contractor’s recommendations and/or corrective plans are implemented and effective.