DRAFT J-2 DRLs 26MAR2024.docx
DOCX document 231 KB Posted
- Attached to
- N00024-24-R-2227 - P-TSVRON Draft Solicitation
- Solicitation number
- N00024-24-R-2227
About this file
This document is a Data Requirements List (DRL) that identifies the required data items and their submittal requirements in support of the acquisition and conversion of the Pacific Training Support Vessel (P-TSV).
The DRL covers a wide range of data items including meeting agendas and minutes, schedules, ship damage reports, documentation related to regulatory bodies and certifications, hazardous materials lists, technical manuals and drawings, test procedures and reports, pre-delivery inspection and trials, seakeeping performance, electrical load analysis, and other engineering documentation. The data items must be submitted according to specified schedules, with the government retaining the right to review and comment on the submittals. The DRL provides detailed descriptions of the content and format requirements for each data item. Overall, this DRL establishes the documentation deliverables required from the contractor throughout the P-TSV acquisition and conversion process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| J-12 Technical Data Package Status List.xlsx | XLSX spreadsheet | |
| DRAFT J-6 P-TSV Maintenance SOWv1.docx | DOCX document | |
| DRAFT J-10 Preservation Instructions v1.docx | DOCX document | |
| DRAFT J-1 P-TSV Specification 3_28_24.docx | DOCX document | |
| Industry Questionnaire.xlsx | XLSX spreadsheet | |
| N0002424R2227_Draft RFP_1APR2024_SAM Posting.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Data Requirements List, Attachment J-2 Solicitation: N0002424R2227
CUI
PACIFIC TRAINING SUPPORT VESSEL (P-TSV)
Data Requirements List Attachment J-2
26 March 2024
Prepared by Naval Sea Systems Command 1333 Isaac Hull Ave. SE Washington Navy Yard, DC 20376-2101
DISTRIBUTION STATEMENT D: Distribution authorized to the Department of Defense and U.S. DoD Contractors only (Critical Technology, 12 May 2023). Other requests for this document shall be referred to PEO USC PMS300, Washington Navy Yard, 1333 Isaac Hull Ave. SE, Washington, DC 20376-2101.
WARNING – This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec. 2751, et seq.) or the Export Administration Act of 1979 (Title 50, U.S.C., App. 2401 et seq.), as amended. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.
DESTRUCTION NOTICE – Controlled Information, destroy in accordance with the SECNAV M-5510.36, DON Information Security Program, June 2006, or DoD Manual 5220.22-M, National Industrial Security Program Operating Manual (February 2006 with Change 1 of March 28, 2013). Controlled Unclassified Information (CUI), (e.g., FOUO, Distribution Statement controlled) shall be destroyed by any methods that will prevent disclosure of contents or reconstruction of the document.
FOREWORD
The Data Requirements List (DRL) identifies Contractor Data Item requirements in support of the acquisition and conversion of the Pacific Training Support Vessel (P-TSV). This foreword provides direction to clarify administrative and procedural questions. Emergent issues that are not addressed herein or otherwise provided for in source documents should be referred to Program Executive Office Ships PMS300G.
I. CONTENT AND FORMAT OF SUBMITTALS
All submittals shall be prepared in the Contractor's format unless otherwise specified in the specific data item. Data item submittals shall be clear, legible, and prepared in the English language. Engineering drawings and associated lists shall be as identified in Engineering Drawing and Related Documentation Practices, American Society of Mechanical Engineers (ASME) Y14.100; Types and Applications of Engineering Drawings, ASME Y14.24 Associated Lists, ASME Y14.34 and Revision of Engineering Drawings and Associated Documents, Y14.35M. Calculations and design data shall be provided in metric standard units or in the inch- pound system; the convention for units of measure shall be consistent throughout the documentation.
Data Items shall be assigned a sequential one-character alphabet designation in the Revision Block to signify a change from the previous submittal. Revision letter designations shall be in alphabetical order. The first submittal of any data item shall be identified as Revision "-".
Revisions of submittals shall include a change log or be prepared in a "red line" format to allow for identification of changes from the previous submittal.
Electronic media and digital files shall be compatible with computers using Windows 10™ operating system, or latest available version, unless otherwise specified. The latest available versions of the following software products shall be utilized in the generation of data items, unless otherwise specified: Microsoft Office™ including Microsoft Project™, Adobe Acrobat™, WinZip™, or IGES™. Schedules shall be Microsoft Project compatible. Alternative software or versions of software may be used if mutually agreed between the Contractor and the Government. Electronic files shall not be password protected. All textual PDF files shall be searchable.
Documents shall not be submitted in PDF format unless specified in the specific data item. For documents with no electronic original available, the original document shall be prepared electronically in PDF format. Drawings shall be submitted in the latest version of AutoCAD™ compatible format and PDF format, unless otherwise specified, and shall not be in "read only" format.
The first three characters of each digital filename shall be the Contractor's name or acronym. The filename shall include the applicable Data Item number and a Contractor determined designation, followed by a one-character revision letter, as applicable. Each file extension shall be the three or four-character default extension automatically assigned by the applicable software when a document is saved. If the software does not automatically assign the three or four-character extension, the Contractor shall assign a three or four-character extension and specify the file’s applicable software and version in the letter of transmittal. Electronic files shall not be password protected.
All data deliveries shall include a Department of Defense (DoD) Distribution Statement in accordance with DoD Instruction 5230.24. The Contractor shall determine which statement is applicable for the data being delivered.
Each data item submittal shall include the following export restriction:
" WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02."
All submittals shall be provided with a cover sheet. Each data item shall be submitted with a separate letter of transmittal. The cover sheet shall provide the following information:
· Ship Acronym and applicable Hull Numbers
· Contractor's name, correspondence serial number, and actual date of transmittal.
· The Contract Number, Data Item Number, and Data Item Title.
· Applicable revision letter and revision date.
· Electronic media or digital file name and respective file date.
· A brief explanation of the submittal, the reason for a document's change, or a more detailed discussion in the content of the submittal.
· Distribution and quantity of copies being sent (not applicable to data provided at a shared location).
II. SUBMISSION SCHEDULE
The Contractor shall deliver all data requirements in accordance with the DRL.
III QUALITY CONTROL
The Contractor shall maintain internal quality control to ensure submittals are complete and adequate and should not rely on Government review comments to ensure the technical accuracy of data. The Contractor shall review submittals to ensure accuracy of language, flow, overall readability, as well as proofreading for grammar, spelling, and typographical errors.
IV ACRONYMS
An alphabetical list of acronyms follows. The list includes those acronyms used most frequently in the Data Requirements List.
ACRONYMS
| ABS |
| American Bureau of Shipping |
| ASME |
| American Society of Mechanical Engineers |
| CLIN |
| Contract Line Item Number |
| DAC |
| Days After Contract Award |
| DARC |
| Days After Receipt of Comments |
| DI |
| Data Item(s) |
| DoD |
| Department of Defense |
| DPT |
| Days Prior To |
| DR |
| Design Review |
| DRL |
| Data Requirements List |
| ECP |
| Engineering Change Proposal |
| HVAC |
| Heating, Ventilation, and Air Conditioning |
| MCCS |
| Machinery Centralized Control System |
| MTHLY |
| Monthly |
| MVR |
| Marine Vessel Rules |
| NECP |
| Non-Engineering Change Proposal |
| O&M |
| Operation and Maintenance |
| OEM |
| Original Equipment Manufacturer |
| OPNAVINST |
| Office of the Chief of Naval Operations Instruction |
| PAC |
| Post Award Conference |
| PLC |
| Programmable Logic Controller |
| PO |
| Purchase Order |
| PR |
| Purchase Request |
| R/ASR |
| Revisions as Required |
| RFV |
| Request for Variance |
| SD |
| Ship Delivery |
| SDS |
| Safety Data Sheet |
| SHML |
| Ship Hazardous Materials List |
| SOW |
| Statement of Work |
| SWBS |
| Ship Work Breakdown Structure |
| T&S |
| Trim and Stability |
| TM |
| Technical Manual |
| TMI |
| Technical Manual Index |
| VRS |
| Vendor Recommended Spares |
PACIFIC TRAINING SUPPORT VESSEL
DATA REQUIREMENTS
CONTRACT NO.: N000XX-XX-X-XXXX CONTRACTOR: TBD
ix DISTRIBUTION STATEMENT D: Distribution authorized to the Department of Defense and U.S. DoD Contractors only (Critical Technology, 12 May 2023). Other requests for this document shall be referred to PEO Ships PMS300, Washington Navy Yard, 1333 Isaac Hull Ave. SE, Washington, DC 20376-2101.
V. GLOSSARY
The items listed below are explanations of the headings and blocks on the Data Requirements List (DRL).
1. PROGRAM NAME: The name of the program.
2. CONTRACT NO.: The Procurement Instrument Identification Number (i.e., the contract number, Purchase Request (PR) number, the Request for Proposal number, or other appropriate designator).
3. CLIN: The Contract Line Item Number (CLIN) that is associated with the DRL.
4. CONTRACTOR: The Contractor's name.
5. PREPARED AND APPROVED BY: The name and organization responsible for preparation and approval of the Data Items.
6. DATE: The date the Data Item was approved.
7. BLOCK 1 -DATA ITEM NO.: An identification number to support data item identified in the Statement of Work or Contract.
8. BLOCK 2-DATA ITEM TITLE: The title of the Data Item.
9. BLOCK 3-REFERENCE: The specific location within the Statement of Work or Contract that contains the tasking that generates a requirement for the data.
10. BLOCK 4-DATA DESCRIPTION: Details regarding the Data Item’s content characteristics and format requirements, if applicable.
11. BLOCK 5- APPROVAL/REVIEW REQUIREMENTS: The Government will review the Contractor’s submittal as indicated. The time period required for Government review will be as specified. The Government will comment on Data Items that require Government comment within the timeframe noted. The Government reserves the right to comment on all deliverables. The time period for Government review, identified in the data requirements list, commences at receipt of the data by the Government.
12. BLOCK 6-SUBMITTAL SCHEDULE: The scheduled date for initial data submission, incremental submittals, and resubmittals, as specified. In addition, details regarding Data Item submittal requirements are included. Submittal dates are often based on Contract events. Days identified are calendar days unless otherwise identified. Where scheduled date for data submission falls on a Saturday, Sunday or Federal Government holiday, the submission due date shall be the following Government working day. Revisions and subsequent periodic submissions shall incorporate the resolution of Government comments
13.
14. BLOCK 7-DISTRIBUTION: Unless otherwise stated, all deliveries shall be in digital format and posted to a shared electronic location or submitted to PMS300G and SEA 05D4 via E-Mail distribution. If deliverables are distributed by posting at a shared location, an E-Mail notification shall be submitted to PMS300G and SEA 05D4. Data provided at a shared location shall meet the requirements for digital copies identified herein. Specific formats and unique delivery requirements are identified in the individual data items.
| ADDRESSEE |
| COMPLETE ADDRESS |
PMS300G
Assistant Program Manager Naval Sea Systems Command Peter Herrman, PMS 300G 1333 Isaac Hull Ave, S.E. MS Washington Navy Yard, DC 20376 Email: peter.c.herrman.civ@us.navy.mil
SEA 05D4
Ship Design Manager Naval Sea Systems Command Andrew Rogers, NAVSEA 05D4 1333 Isaac Hull Ave, S.E.
Washington Navy Yard, DC 20376 Email: andrew.d.rogers16.civ@us.navy.mil
Table of Contents and List of Effective Changes
| Data Item No. |
| Contract |
Reference Data Item Titles And Subtitles Change Status
| DI-001 |
| SOW C-3.042a |
| AGENDAS |
| BASIC |
| DI-002 |
| SOW C-3.042a |
| MEETING MINUTES |
| BASIC |
| DI-003 |
| SOW C-3.042b |
| MASTER SCHEDULE |
| BASIC |
| DI-004 |
| SOW C-3.042e |
| SHIP DAMAGE REPORT |
| BASIC |
| DI-005 |
| SOW C-3.070b |
| CLASSIFICATION SOCIETY OR REGULATORY BODY |
COMMUNICATIONS
BASIC
| DI-006 |
| SOW C-3.070b |
| CLASSIFICATION SOCIETY AND REGULATORY |
BODY CERTIFICATES
BASIC
| DI-007 |
| SOW C-3.070c |
| INTACT AND DAMAGE STABILITY REPORT |
| BASIC |
| DI-008 |
| SOW C-3.077 |
| SHIP HAZARDOUS MATERIAL LIST |
| BASIC |
| DI-009 |
| SOW C-3.077 |
| SAFETY DATA SHEETS |
| BASIC |
| DI-010 |
| SOW C-3.077 |
| LITHIUM BATTERY REPORT |
| BASIC |
| DI-011 |
| SOW C-3.085a |
| CONVERSION DRAWINGS AND DOCUMENTATION |
| BASIC |
| DI-012 |
| SOW C-3.085b |
| TECHNICAL DATA PACKAGE |
| BASIC |
| DI-012-01 |
| SOW C-3.085b |
| HULL LINES AND BODY PLAN |
| BASIC |
| DI-012-02 |
| SOW C-3.085b |
| MIDSHIP AND TYPICAL SECTIONS DRAWING |
| BASIC |
| DI-012-03 |
| SOW C-3.085b |
| SCANTLING PLANS, DECKS, AND PROFILES |
| BASIC |
| DI-012-04 |
| SOW C-3.085b |
| SHELL EXPANSION DRAWING |
| BASIC |
| DI-012-05 |
| SOW C-3.085b |
| MAIN ENGINES, GENERATORS, AND |
MISCELLANEOUS FOUNDATIONS
BASIC
| DI-012-06 |
| SOW C-3.085b |
| PROPELLER, SHAFT, AND RUDDER OR Z-DRIVE ARRANGEMENT AND REMOVAL DRAWING |
| BASIC |
| DI-012-07 |
| SOW C-3.085b |
| PROPELLER DRAWING |
| BASIC |
| DI-012-08 |
| SOW C-3.085b |
| MAIN CONTROL CONSOLE AND SHIP CONTROL |
CONSOLE ARRANGEMENTS
BASIC
| DI-012-09 |
| SOW C-3.085b |
| INPUT/OUTPUT SIGNAL LIST |
| BASIC |
| DI-012-10 |
| SOW C-3.085b |
| TOPSIDE ARRANGEMENT DRAWING |
| BASIC |
| DI-012-11 |
| SOW C-3.085b |
| RUNNING, ANCHOR, AND SEARCHLIGHTS PLAN |
| BASIC |
| DI-012-12 |
| SOW C-3.085b |
| ANCHOR HANDLING AND STOWAGE |
| BASIC |
| DI-012-13 |
| SOW C-3.085b |
| MOORING AND TOWING ARRANGEMENT |
| BASIC |
| DI-012-14 |
| SOW C-3.085b |
| STEERING GEAR ARRANGEMENT AND DETAILS |
| BASIC |
| DI-012-15 |
| SOW C-3.085b |
| RUDDER AND RUDDER STOCK ARRANGEMENT AND DETAILS |
| BASIC |
| DI-012-16 |
| SOW C-3.085b |
| THRUSTER ARRANGEMENT AND DETAILS |
| BASIC |
| DI-012-17 |
| SOW C-3.085b |
| COMPARTMENT ARRANGEMENT AND OUTFITTING |
DRAWINGS
BASIC
| DI-012-18 |
| SOW C-3.085b |
| DOOR, WINDOW, AND HATCH SCHEDULE |
| BASIC |
| DI-012-19 |
| SOW C-3.085b |
| FLOOR GRATING ARRANGEMENT AND DETAILS |
| BASIC |
| DI-012-20 |
| SOW C-3.085b |
| RAILINGS, STAIRS, AND LADDERS ARRANGEMENT |
AND DETAILS
BASIC
| DI-012-21 |
| SOW C-3.085b |
| MACHINERY CENTRALIZED Machinery |
DESCRIPTION OF OPERATIONS
BASIC
| DI-012-22 |
| SOW C-3.085b |
| TELEPHONE DIRECTORY |
| BASIC |
| DI-012-23 |
| SOW C-3.085b |
| LIST OF LUBRICANTS |
| BASIC |
| DI-012-24 |
| SOW C-3.085b |
| KEY TAG INDEX |
| BASIC |
| DI-012-25 |
| SOW C-3.085b |
| INSULATION SCHEDULE |
| BASIC |
| DI-012-26 |
| SOW C-3.085b |
| DAMAGE CONTROL DISPLAY PLANS |
| BASIC |
| DI-012-27 |
| SOW C-3.085b |
| PERIODIC SAFETY TEST PROCEDURES |
| BASIC |
| DI-012-28 |
| SOW C-3.085b |
| TRIM AND STABILITY BOOKLET |
| BASIC |
| DI-012-29 |
| SOW C-3.085b |
| BOOKLET OF TANK CAPACITY AND SOUNDING TABLES |
| BASIC |
| DI-012-30 |
| SOW C-3.085b |
| SHIP DRAWING INDEX |
| BASIC |
| DI-012-31 |
| SOW C-3.085b |
| GENERAL ARRANGEMENT OF DECKS |
| BASIC |
| DI-012-32 |
| SOW C-3.085b |
| INBOARD AND OUTBOARD PROFILES |
| BASIC |
| DI-012-33 |
| SOW C-3.085b |
| MACHINERY ARRANGEMENT PLANS |
| BASIC |
| DI-012-34 |
| SOW C-3.085b |
| ELECTRICAL DISTRIBUTION SYSTEM ONE-LINE |
DIAGRAM
BASIC
| DI-012-35 |
| SOW C-3.085b |
| MAIN AND EMERGENCY SWITCHBOARD ONE-LINE |
DIAGRAM
BASIC
| DI-012-36 |
| SOW C-3.085b |
| INTERIOR COMMUNICATION SYSTEM BLOCK |
WIRING DIAGRAMS SRD
BASIC
| DI-012-37 |
| SOW C-3.085b |
| RADIO COMMUNICATIONS BLOCK DIAGRAM SRD |
| BASIC |
| DI-012-38 |
| SOW C-3.085b |
| ELECTRICAL CABLEWAYS AND PENETRATIONS |
| BASIC |
| DI-012-39 |
| SOW C-3.085b |
| NAVIGATION AND COMMUNICATIONS SYSTEM |
BLOCK DIAGRAM
BASIC
| DI-012-40 |
| SOW C-3.085b |
| MACHINERY ALARM AND MONITORING BLOCK DIAGRAM |
| BASIC |
| DI-012-41 |
| SOW C-3.085b |
| MACHINERY VENTILATION DIAGRAM AND |
DETAILS
BASIC
| DI-012-42 |
| SOW C-3.085b |
| HVAC DIAGRAMMATIC PLAN AND EQUIPMENT |
LIST
BASIC
| DI-012-43 |
| SOW C-3.085b |
| HVAC CALCULATIONS |
| BASIC |
| DI-012-44 |
| SOW C-3.085b |
| PIPING SYSTEMS DIAGRAMS |
| BASIC |
| DI-012-45 |
| SOW C-3.085b |
| TECHNICAL MANUAL INDEX |
| BASIC |
| DI-012-46 |
| SOW C-3.085b |
| OEM TECHNICAL MANUALS |
| BASIC |
| DI-012-47 |
| SOW C-3.085b |
| APPLICABLE MARPOL 73/75 PROCEDURES, |
ARRANGEMENTS AND MANAGEMENT MANUALS
BASIC
| DI-012-48 |
| SOW C-3.085b |
| MISSION SPACES ARRANGEMENT |
| BASIC |
| DI-012-49 |
| SOW C-3.085b |
| NETWORKS SYSTEM BLOCK DIAGRAM |
| BASIC |
| DI-012-50 |
| SOW C-3.085b |
| CCTV SYSTEM BLOCK DIAGRAM |
| BASIC |
| DI-012-51 |
| SOW C-3.085b |
| LIGHTING SYSTEM ONE-LINE DIAGRAM |
| BASIC |
| DI-012-52 |
| SOW C-3.085b |
| ORIGINAL EQUIPMENT MANUFACTURER (OEM) COMMERCIAL WARRANTY SHEETS AND REGISTRATION FORMS |
| BASIC |
| DI-012-53 |
| SOW C-3.085b |
| FIRE STRUCTURAL PROTECTION DRAWING |
| BASIC |
| DI-012-54 |
| SOW C-3.085b |
| SEAKEEPING PERFORMANCE REPORT |
| BASIC |
| DI-012-55 |
| SOW C-3.085b |
| ELECTRICAL POWER LOAD ANALYSIS |
| BASIC |
| DI-012-56 |
| SOW C-3.085b |
| ELECTRICAL POWER SYSTEM DIAGRAM |
| BASIC |
| DI-012-57 |
| SOW C-3.085b |
| NAVIGATIONAL LIGHTS DRAWING |
| BASIC |
| DI-012-58 |
| SOW C-3.085b |
| ALARM SYSTEM DRAWING |
| BASIC |
| DI-012-59 |
| SOW C-3.085b |
| FIRE CONTROL AND SAFETY PLANS |
| BASIC |
| DI-012-60 |
| SOW C-3.085b |
| PAINT SCHEDULE |
| BASIC |
| DI-012-61 |
| SOW C-3.085b |
| DOCKING PLAN |
| BASIC |
| DI-012-62 |
| SOW C-3.085b |
| DECK FITTINGS AND ANCHOR HANDLING ARRANGEMENT DRAWINGS |
| BASIC |
| DI-012-63 |
| SOW C-3.085b |
| MAST ARRANGEMENT AND DETAILS DRAWING |
| BASIC |
| DI-012-64 |
| SOW C-3.085b |
| 24VDC SYSTEM DIAGRAM |
BASIC
| DI-013 |
| SOW C-3.085c |
| CRANE FABRICATION DRAWINGS |
| BASIC |
| DI-014 |
| SOW C-3.085d |
| AS-BUILT REVISIONS OF GFI DRAWINGS |
| BASIC |
| DI-015 |
| SOW C-3.092 |
| TEST PROCEDURES |
| BASIC |
| DI-016 |
| SOW C-3.092 |
| TEST REPORTS |
| BASIC |
| DI-017 |
| SOW C-3.094 |
| PRE-DELIVERY INSPECTION AND TRIALS (PDIT) |
AGENDAS
BASIC
| DI-018 |
| SOW C-3.094 |
| PRE-DELIVERY INSPECTION AND TRIALS (PDIT) REPORTS |
| BASIC |
| DI-019 |
| SOW C-3.095 |
| STABILITY TEST REPORT |
| BASIC |
| DI-020 |
| SOW C-3.095 |
| INFRARED ELECTRICAL SYSTEM SURVEY REPORT |
| BASIC |
| DI-021 |
| SOW C-3.096 |
| ELECTROMAGNETIC ENVIRONMENTAL EFFECTS (E3) PROGRAM REPORTS |
| BASIC |
| DI-021-01 |
| SOW C-3.096 |
| RADHAZ/HERO/HERF/HERP ANALYSIS REPORT |
| BASIC |
| DI-021-02 |
| SOW C-3.096 |
| RADHAZ AREA DRAWING |
| BASIC |
| DI-021-03 |
| SOW C-3.096 |
| ELECTROMAGNETIC COMPATABILITY (EMC) ANALYSIS REPORT |
| BASIC |
| DI-021-04 |
| SOW C-3096 |
| E3 TEST REPORTS |
| BASIC |
| DI-022 |
| SOW C-3.096 |
| WEIGHTS |
| BASIC |
| DI-022-01 |
| SOW C-3.096 |
| ACCEPTED WEIGHT ESTIMATE |
| BASIC |
| DI-022-02 |
| SOW C-3.096 |
| ACCEPTED WEIGHT ESTIMATE SUPPLEMENTAL AGREEMENT |
| BASIC |
| DI-022-03 |
| SOW C-3.096 |
| INTERIM WEIGHT REPORT |
| BASIC |
| DI-022-04 |
| SOW C-3.096 |
| WEIGHT CONTROL REPORT |
| BASIC |
| DI-022-05 |
| SOW C-3.096 |
| FINAL WEIGHT REPORT |
| BASIC |
| DI-023 |
| SOW C-3.402 |
| CYBERSECURITY INFORMATION FOR CONTROL |
SYSTEMS
BASIC
| DI-024 |
| SOW C-222-H001 |
| ACCESS CONTROL PLAN |
| BASIC |
| DI-025 |
| SOW C-243-H003 |
| ENGINEERING CHANGE PROPOSALS |
| BASIC |
| DI-026 |
| SOW C-243-H003 |
| NON-ENGINEERING CHANGE PROPOSALS |
| BASIC |
| DI-027 |
| SOW C-243-H003 |
| REQUEST FOR DEVIATION/WAIVER (RFD/RFW) |
| BASIC |
| DI-028 |
| SOW C-243-H001 |
| CONTRACT PROBLEM IDENTIFICATION REPORT |
| BASIC |
| DI-029 |
| SOW C-211-H005 |
| PLANT PROTECTION PLAN |
| BASIC |
| DI-030 |
| SOW C-3.083 |
| VENDOR RECOMMENDED SPARES LISTING |
| BASIC |
| DI-031 |
| SOW C-3.070a |
| SUPPLY CHAIN RISK MANAGEMENT (SCRM) |
| BASIC |
| DI-032 |
| SOW C-3.045d |
| FIRE AND FLOODING PREVENTION PLAN |
| BASIC |
| DI-033 |
| SOW C-3.042c |
| DRY DOCKING FACILITIES CERTIFICATION REPORT |
| BASIC |
| DI-034 |
| SOW C-3.042d |
| DOCKING PLAN AND CALCULATIONS |
| BASIC |
| DI-035 |
| SOW C-3.077 |
| HAZARDOUS MATERIAL WAIVER REQUEST |
| BASIC |
| DI-036 |
| SOW C-3.085g |
| INSPECTION REPORTS |
| BASIC |
| BLOCK 1-DATA ITEM NO.: |
| DI-001 |
| BLOCK 2-DATA ITEM TITLE: |
| AGENDAS |
| BLOCK 3-REFERENCE: |
| SOW C-3.042a |
BLOCK 4-DATA DESCRIPTION:
1. The Agendas for conferences, reviews, working groups, and other meetings with the Government shall include the following general requirements:
a. Meeting name, date, time, and location
b. Sequential listing of each topic discussed
c. Discussion topics shall include, as applicable:
1) Schedule
2) Progress data
3) Design status
4) Staffing status
5) Regulatory Body approval status
6) Material status
7) Logistics status
8) Engineering change status
9) Test status
10) DRL delivery status
11) Vendor Recommended Spare Listing (VRS) status
12) Problems/recommendations
13) Action Item status
2. The Post Award Conference (PAC) agenda shall include the same general agenda content listed above with the exception of unique topics shall also be included:
a. Personnel Introductions
b. Organization Overview
1) Contractor Organization Discussion
2) Roles and Responsibilities and Points of Contact
3) Communication – Authorized Contractor Representatives
c. Facilities Overview
1) Site Layout
2) Security and Access Control
d. Planned Detail Design and Conversion Approach
e. Regulatory Bodies Involvement
f. Near Term Schedule
1) Key Events
2) Conferences and Reviews
3) Deliverables
g. DRL Review
h. Questions
i. Government topics:
1) Personnel Introductions
2) Organization Overview
i. Major Organizations involved in the contract
ii. Roles and Responsibilities and Points of Contact
PACIFIC TRAINING SUPPORT VESSEL
DATA REQUIREMENTS
CONTRACT NO.: N00024-19-R-2205 CONTRACTOR: TBD
DISTRIBUTION STATEMENT D: Distribution authorized to the Department of Defense and U.S. DoD Contractors only (Critical Technology, 12 May 2023). Other requests for this document shall be referred to PEO Ships PMS300, Washington Navy Yard, 1333 Isaac Hull Ave. SE, Washington, DC 20376-2101.
| BLOCK 1-DATA ITEM NO.: |
| DI-001 (Continued) |
| BLOCK 2-DATA ITEM TITLE: |
| AGENDAS |
BLOCK 4-DATA DESCRIPTION: (Continued)
3) Program Overview
i. Program Specifics, Contract and Technical Highlights
ii. Government Furnished Property
iii. Government expectations including the demonstration of production readiness
iv. Proprietary information/data
4) Communications
i. Authorized Government Representatives
ii. Web Based Project Management System
iii. Email and letter correspondence
iv. Regulatory Body correspondence
v. Submission of data
j. Questions
3. A copy of each final presentation shall be included.
BLOCK 5-APPROVAL/REVIEW REQ.:
Allow 3 business days for Government review and comment.
BLOCK 6-SUBMITTAL SCHEDULE:
7 DPT each conference, review, or meeting with the Government; R/ASR 2 DARC.
| BLOCK 7-DISTRIBUTION: |
| Addressee |
| QTY |
| PMS300G |
| 1* |
| SEA 05D4 |
| 1 |
*Hard copies of presentation materials shall also be provided for each attendee at the meeting.
| BLOCK 1-DATA ITEM NO.: |
| DI-002 |
| BLOCK 2-DATA ITEM TITLE: |
| MEETING MINUTES |
| BLOCK 3-REFERENCE: |
| SOW C-3.042a |
1. The Meeting Minutes for conferences, reviews, working groups, and other meetings with the Government shall include:
a. Meeting name, date, time, and location
b. Attendees with contact information
c. Chronological listing of each topic discussed
d. Applicable discussions and concerns
e. Action Items with due date and assignee
f. Listing of documents discussed by document name, document revision, document date, and the digital file name and date.
2. Copies of each presentation and document reviewed shall also be included.
BLOCK 5-APPROVAL/REVIEW REQ.:
Allow 7 days for Government review and comment.
BLOCK 6-SUBMITTAL SCHEDULE:
7 days after each meeting, review, or conference; R/ASR 7 DARC.
| BLOCK 7-DISTRIBUTION: |
| Addressee |
| QTY |
| PMS300G |
| 1 |
| SEA 05D4 |
| 1 |
| BLOCK 1-DATA ITEM NO.: |
| DI-003 |
| BLOCK 2-DATA ITEM TITLE: |
| MASTER SCHEDULE |
| BLOCK 3-REFERENCE: |
| SOW C-3.042b |
1. The Master Schedule (MS) shall present the overall plan for the design, modification and construction, verification, testing, outfitting, and delivery of the ship. The information will be used to verify attainability of program objectives and evaluate progress. The MS shall depict all activities required for the performance of this Contract. The MS schedule shall present key events, milestones, and the critical path.
2. The MS shall include all efforts required to complete milestones. The MS shall portray in chronological sequence, the actions, events, and requirements with corresponding planned start and completion dates and the actual start and completion dates, which shall be retained on each issue of MS. The MS shall be kept current with schedule modifications and completed tasks. As appropriate, a column, line or space shall be provided for comments, explanation of problems encountered, and any remarks providing clarification shall also be identified.
3. The MS shall be highlighted to show changes from the previous submittal.
4. The MS shall be provided a legend for abbreviations.
BLOCK 5-APPROVAL/REVIEW REQ
Allow 14 days for Government review and comment.
BLOCK 6-SUBMITTAL SCHEDULE:
30 DAC; Updates shall be provided every two weeks.
| BLOCK 7-DISTRIBUTION: | Addressee | QTY |
| PMS300G | 1 | |
| SEA 05D4 | 1 |
| BLOCK 1-DATA ITEM NO.: |
| DI-004 |
| BLOCK 2-DATA ITEM TITLE: |
| SHIP DAMAGE REPORT |
| BLOCK 3-REFERENCE: |
| SOW C-3.042e |
A Ship Damage Report shall document the occurrence, assessment of the cause, damage sustained, personnel injuries, proposed corrective action, and effects on the ship's delivery schedule. Preliminary assessment of possible ship damage below the waterline shall be supported by underwater inspection and documented in the Ship Damage Report.
BLOCK 5-APPROVAL/REVIEW REQ.:
Allow 3 days for Government review and comment.
BLOCK 6-SUBMITTAL SCHEDULE:
Notification 24 hours after each incident; via Email to PCO and PMS300G, submit detailed report 7 days after each incident.
| BLOCK 7-DISTRIBUTION: |
| Addressee |
| QTY |
| PMS300G |
| 1 |
| SEA 05D4 |
| 1 |
| BLOCK 1-DATA ITEM NO.: |
| DI-005 |
| BLOCK 2-DATA ITEM TITLE: |
| CLASSIFICATION SOCIETY OR REGULATORY BODY COMMUNICATIONS |
| BLOCK 3-REFERENCE: |
| SOW C-3.070b |
1. Provide copies of all incoming and outgoing communications on technical matters, including attachments/enclosures, between the Classification Society or Regulatory Bodies and the Contractor or their Subcontractors. Communications shall include letters, emails, and conversation notes. Attachments/enclosures include drawings, sketches, photographs, slides, viewgraphs, presentations, specifications, manuals, studies, calculations, analyses, requests for change, applications for inspection, contracts, scopes of work, and related communication.
2. Communications shall be assigned serial numbers and shall be indexed by the serial numbers and applicable dates. A cross-reference shall be made from Contractor assigned serial numbers to actual incoming communication’s serial numbers, where applicable.
BLOCK 5-APPROVAL/REVIEW REQ.:
Allow 14 days for Government review and comment.
BLOCK 6-SUBMITTAL SCHEDULE:
3 days after incoming or outgoing communications have occurred.
| BLOCK 7-DISTRIBUTION: |
| Addressee |
| QTY |
| PMS300G |
| 1 |
| SEA 05D4 |
| 1 |
| BLOCK 1-DATA ITEM NO.: |
| DI-006 |
| BLOCK 2-DATA ITEM TITLE: |
| CLASSIFICATION SOCIETY AND REGULATORY BODY CERTIFICATES |
| BLOCK 3-REFERENCE: |
| SOW C-3.070b |
1. Classification Society and Regulatory Body Certificates, Statements of Fact, DoD/Navy Certifications and certificates of compliance shall contain the Contract number, a statement that identifies the purpose, applicability of this certification, and verification that the Contractor has complied with the Contract requirements.
2. Where Classification Society and Regulatory Body Certificates of compliance are presented as evidence of quality, such certificates shall indicate that the material or equipment was previously tested and met all performance requirements and shall contain verification data, refer to witnessing inspectors or present other verifiable quality data.
BLOCK 5-APPROVAL/REVIEW REQ.:
Allow 14 days for Government review and comment.
BLOCK 6-SUBMITTAL SCHEDULE:
Copies of certificates shall be submitted 7 days after receipt; original certificates shall be provided 10 DPT SD. Certification verification data shall be submitted 10 days after request from the Government for copy of the verification of equipment/ test certification.
| BLOCK 7-DISTRIBUTION: | Addressee | QTY |
| PMS300G | 1 | |
| SEA 05D4 | 1 |
SHIP (via NAVSEA Authorized Representative) 1*
* Originals shall be mounted onboard the ship
| BLOCK 1-DATA ITEM NO.: |
| DI-007 |
| BLOCK 2-DATA ITEM TITLE: |
| INTACT AND DAMAGE STABILITY REPORT |
| BLOCK 3-REFERENCE: |
| SOW C-3.070c |
The Intact and Damage Stability Report shall include all calculations required to support the derivation of the intact and damaged allowable KG curves. At a minimum the report shall include the following:
1. Definition of applicable stability criteria in accordance with the Contract.
2. Descriptions and data for the following:
a. Hull form
b. Hydrostatic properties
c. Watertight boundaries and compartmentation
d. Compartment permeabilities
e. Margin line and down flooding point locations
f. Compartments included in each flooding case
g. Cross-flooding arrangements for any cross-connected spaces
3. Operating restrictions and allowable draft and trim range.
4. The maximum allowable KG (or minimum required GM) vs. draft curves to meet intact and damaged stability criteria.
5. Supporting calculations in appendices.
BLOCK 5-APPROVAL/REVIEW REQ.:
Allow 7 days for Government review and approval.
BLOCK 6-SUBMITTAL SCHEDULE:
30 DPT DR; R/ASR 30 DARC and when the need for change is identified.
| BLOCK 7-DISTRIBUTION: |
| Addressee |
| QTY |
| PMS300G |
| 1 |
| SEA 05D4 |
| 1 |
| BLOCK 1-DATA ITEM NO.: |
| DI-008 |
| BLOCK 2-DATA ITEM TITLE: |
| SHIP HAZARDOUS MATERIAL LIST |
| BLOCK 3-REFERENCE: |
| SOW C-3.077 |
A Ship Hazardous Materials List (SHML) shall be developed including materials used for conversion and Operation and Maintenance (O&M). The construction materials shall include a detailed summary of all materials (hazardous or otherwise regulated) selected for ship conversion. The O&M materials shall include a detailed summary of all materials (hazardous or otherwise regulated) required to be used during ship operation and maintenance. All consumables to be carried on board ship shall be documented in the P-TSV SHML and include types and quantities of each material. The SHML shall identify where all selected materials are used, why the materials were selected, the potential hazards/impacts associated with the materials, the regulations governing the distribution in commerce, transportation, use, and ultimate disposal of the materials and associated wastes, and the quantity and distribution of the materials on board ship. The final SHML shall identify the finalized list of all hazardous or otherwise regulated materials used in the conversion, operation, and maintenance of the ship.
BLOCK 5-APPROVAL/REVIEW REQ.:
Allow 14 days for Government review and comment.
BLOCK 6-SUBMITTAL SCHEDULE:
Initial 30 DPT DR; R/ASR 14 DARC and when the need for change is identified. Final submittal shall be at SD.
| BLOCK 7-DISTRIBUTION: | Addressee | QTY |
| PMS300G | 1 | |
| SEA 05D4 | 1 | |
| SHIP (via NAVSEA Authorized Representative) | 1 |
| BLOCK 1-DATA ITEM NO.: |
| DI-009 |
| BLOCK 2-DATA ITEM TITLE: |
| SAFETY DATA SHEETS |
| BLOCK 3-REFERENCE: |
| SOW C-3.077 |
1. All Safety Data Sheets for hazardous materials utilized in the conversion and for operation and maintenance shall be provided.
2. The Safety Data Sheets shall be included in a booklet at sea trials.
BLOCK 5-APPROVAL/REVIEW REQ.:
Allow 14 days for Government review and comment.
BLOCK 6-SUBMITTAL SCHEDULE:
Individual Safety Data Sheets due 3 days after receipt from vendor. Deliver booklet to the ship NLT 3 DPT Trials.
| BLOCK 7-DISTRIBUTION: | Addressee | QTY | |
| PMS300 | 1 | ||
| SEA05D4 | 1 |
SHIP (via NAVSEA Authorized Representative) 1*
* Booklet only
| BLOCK 1-DATA ITEM NO.: |
| DI-010 |
| BLOCK 2-DATA ITEM TITLE: |
| BATTERY REPORT |
| BLOCK 3-REFERENCE: |
| SOW C-3.077 |
The Battery Records provide a listing of all ship batteries, including ship’s boats, material handling equipment, and interruptible power supplies (UPS). The list shall include all pertinent data including shipboard location, weight, type, voltage, ampere-hour ratings, specific gravity, number of cells and all other related life cycle data. Further information shall be provided to indicate how they will be connected and recharged (where applicable). The following information shall be provided for lithium batteries:
1. For Category A and Category B lithium batteries, which are defined below, the Lithium Battery Procurement Report shall identify:
a. Battery manufacturer/brand name
b. Model identification (name and number)
c. Electrical description (voltage, ampere-hours capacity, and nominal load profile)
d. Use scenario/environment (e.g., office computer or test set, surface ship)
Category A lithium batteries are batteries that meet the following criteria:
1) Non-rechargeable lithium coin cells;
2) Unmodified, commercial item;
3) Used in a single-cell configuration;
4) Maximum nominal output of 3 Volts; and
5) Maximum rated capacity of 1 ampere-hours (Ah).
Category B lithium batteries are batteries that meet the following criteria:
1) Rechargeable (i.e. secondary) lithium ion batteries;
2) Unmodified, commercial battery for use in electronics and equipment;
3) Used in the device as recommended by the manufacturer;
4) Recharged only by devices expressly designed for recharge of the specific battery in use;
5) No more than four cells in series (less than or equal to 18-Volt output); and
6) Rated for no more than 100 Watt-hours, as listed in the manufacturer’s specification or as calculated by multiplying the capacity in Ah by the maximum working (nominal performance) voltage.
2. For all other lithium batteries that do not meet the criteria of Category A or Category B, the Lithium Battery Procurement Report shall identify the following items:
a. The Proposed Cell/Battery Design Data :
1) Manufacturer (name, address, phone number)
2) Model number and/or part number
3) Electrical description (voltage, ampere-hour (Ah) capacity, and nominal load profile)
4) Electrical safety devices integral to the cell/battery
5) Cell/battery configuration (cells/batteries in parallel or series)
6) Operating life (shelf life and functional life)
7) Physical dimensions and description (weight, size, geometry, number of cells, battery housing description)
8) Marking indicating battery chemistry
9) Cell and/or battery yield pressure (if unvented, battery/housing room ambient yield pressure)
10) All applicable Safety Data Sheets, Product Information Sheets or equivalent document
11) Cell failure mode (indicating whether a single cell failure can cascade into multiple cell failures
12) Discharge rate
13) Rated cycle-life (versus depth of discharge) and the mean-time-between failures for the cell/battery. This data is only required for batteries that designed to be recharged after use.
14) Discharge and recharge rates including the limiting discharge/charge rates. This data is only required for batteries that designed to be recharged after use.
| BLOCK 1-DATA ITEM NO.: |
| DI-010 (Continued) |
| BLOCK 2-DATA ITEM TITLE: |
| BATTERY REPORT |
b. Lithium Battery-Powered System Description:
1) Description of system purpose or function
2) Manufacturer (name, address, phone number)
3) Model number and/or part number and device name
4) Diagram of the system’s overall mechanical interfaces showing battery proximity to other equipment and energetic devices
5) Battery installation (mounting, seals, electrical connectors)
6) Battery housing/container, strength, and free volume
7) Safety features of venting mechanisms (description and estimate of operational venting pressure
8) Current drain (load profile of the system)
9) Block diagram of system interfaces to the battery (electrical and physical)
10) Electrical schematic (showing fuses, blocking diodes, and external power interface)
11) Description of the charger and charge control mechanism, if applicable. (Are cells individually equilibrated, or is the battery charged as a series/parallel string?) Provide information for large form lithium batteries sufficient to support evaluation that features of the charging system related to charging safety have been included in the design, validated, and tested.
12) Description of other controls or mechanisms to enhance battery safety, such as a Battery Management System, software shutdown mechanism, etc.
c. Logistical and Operational Use Data:
1) Packaging. How will system/battery be packaged?
2) Storage facilities. How will system/battery be stored from delivery to disposal?
3) Transportation methods
4) Disposal information
5) Operational use scenario, including:
i. A complete description of how the system/batteries will be handled and used
ii. Location of recharging operations, if applicable
iii. Recovery operations, ashore and afloat, if applicable
iv. Number of units anticipated to be used
v. The sequence of events before the system use/activation/deployment, if applicable
6) Description of the battery change out/replacement plan including the number of batteries needed to support system during deployment and in what storage configuration.
d. Address all safety hazards to co-located systems, platforms, and personnel from operations and carriage identifying and mitigating the risks involved.
BLOCK 5-APPROVAL/REVIEW REQ.:
Allow 14 days for Government review and comment.
BLOCK 6-SUBMITTAL SCHEDULE:
Preliminary list 30 DPT DR; R/ASR 14 DARC and when the need for change is identified.
| BLOCK 7-DISTRIBUTION: |
| Addressee |
| QTY |
| PMS300G |
| 1 |
| SEA 05D4 |
| 1 |
| BLOCK 1-DATA ITEM NO.: |
| DI-011 |
| BLOCK 2-DATA ITEM TITLE: |
| CONVERSION DRAWINGS AND DOCUMENTATION |
| BLOCK 3-REFERENCE: |
| SOW C-3.085a |
1. The Conversion Drawings and Documentation shall include all drawings and calculations for the reactivation (if applicable) and conversion of the ship.
2. Drawings shall provide the design information necessary for construction, installations, removals, assembly, disassembly, repair, and maintenance. The drawings shall reflect the end product and provide engineering data sufficient to support conversion of the vessel, logistics support, repair, and maintenance.
3. Drawings shall document directly or reference the following details, as applicable, when essential for conversion of the vessel, logistics support, repair, and maintenance
a. Performance Ratings
b. Dimensional Data
c. Critical Manufacturing Processes and Assembly Sequences
d. Input and Output Characteristics
e. Diagram of Mechanical and Electrical Connections
f. Physical Characteristics
g. Details of Material Identification, including Heat Treatment and Protective Coatings
h. Inspection
i. Verification, Test and Evaluation Criteria
j. Quality Assurance Requirements
k. Hardware Marking Requirements
l. Requirements for Reliability, Maintainability, Environmental Conditioning, and Other Operational or Functional Tests; and Vendor Substantiation Data when required
4. Drawing title block shall include the following:
a. Drawing Title
b. Drawing Number
c. Drawing Revision Letter
d. Applicable by 3-digit SWBS
e. Drawing Sheet Number and number of sheets
f. Ship's Hull Number
g. Approval Signatures
h. Date
i. Drawing Scale
j. Drawing Size
5. The following shall be included for each set calculations:
a. A cover that identifies the Contract Number, Data Item No., Data Item Title, Applicable Revision, Document Date, and preparing activity information, such as Contractor Name, and Address. Subcontractor reports shall give the name of the prime Contractor. Signature of the responsible company official shall also be included.
b. If approval is required, a statement that the document is being submitted for approval shall also be included in the transmittal.
c. Final submittals shall include a statement on the cover that the document is the final submittal.
d. Report data shall be sufficient to allow assessment of the methodology and verify the results.
| BLOCK 1-DATA ITEM NO.: |
| DI-011 (Continued) |
| BLOCK 2-DATA ITEM TITLE: |
| CONVERSION DRAWINGS AND DOCUMENTATION |
6. Calculations and their revisions shall include examples, computer printouts, and worksheets, if used.
7. Engineering Design Calculations and diagrams shall be numbered. Each calculation shall reference applicable drawings by drawing number, drawing revision, and title.
8. Calculations shall allow an independent reviewer to follow each step without difficulty.
9. Calculations including stress diagrams shall prove that the subject has been designed in accordance with the requirements of the Contract. These calculations shall reflect design configuration. All symbols and abbreviations shall be identified and any diagrams, with their associated components, clearly labeled. Calculations shall include the following, where applicable:
a. Assumptions used shall be stated and all references identified.
b. A listing of system and equipment requirements.
c. Applicable sections of American Bureau of Shipping (ABS) and Regulatory Body requirements.
d. Calculation methodology or calculation methodology identification.
e. A summary of calculation results, conclusions, recommendations and actual system, equipment or component sizes incorporated.
f. Design load, working load, test load, assumptions as to manner of loading, such as live, dead, and alternating; assumed friction, materials (including specification section number), maximum stresses in each part such as compressive, tensile, shearing, and torsional developed by the load, and the factor of safety in each part.
g. Information regarding characteristics under dynamic loading, where applicable, including natural frequencies of vibration, impact, ship motions, and other pertinent data.
h. Summary loads shall include utilization factors and connected loads.
i. Environmental considerations including temperature and motions.
10. Where calculations are performed using a computer program, include a description of the program, input variables, and program assumptions. An explanation of how the computer printout results are used in the design shall be provided which identifies a clear and traceable path of the analysis.
BLOCK 5-APPROVAL/REVIEW REQ.:
Allow 21 days for Government review and comment.
BLOCK 6-SUBMITTAL SCHEDULE:
NLT 30 DPT DR; R/ASR 30 DARC and when the need for change is identified.
| BLOCK 7-DISTRIBUTION: |
| Addressee |
| QTY |
| PMS300G |
| 1 |
| SEA 05D4 |
| 1 |
| BLOCK 1-DATA ITEM NO.: |
| DI-012 |
| BLOCK 2-DATA ITEM TITLE: |
| TECHNICAL DATA PACKAGE |
(See Attachment 1 to Data Item No. DI-012)
| BLOCK 3-REFERENCE: |
| SOW C-3.085b |
1. All Technical Data Package items shall reflect the as-built condition of the converted vessel.
2. The Technical Data Package items shall include the same level of content as the current ship’s drawings and data unless otherwise specified in Attachment 1.
BLOCK 5-APPROVAL/REVIEW REQ.:
Unless otherwise noted in Block 5 of Attachment 1 to this Data Item, allow 7 days for Government review and comment of the initial submittal. Allow 21 days for Government review and comment of the validated “As-Built” version.
BLOCK 6-SUBMITTAL SCHEDULE:
Unless otherwise noted in Block 6 of Attachment 1 to this Data Item, 30 DPT DR; R/ASR 30 DARC and when the need for change is identified. Validated "As-Built" version shall be provided 30 DPT Trials. Revisions shall incorporate resolution of Government comments.
| BLOCK 7-DISTRIBUTION: |
| Addressee |
| Preliminary |
| Final |
| PMS300G |
| 1 |
| 1 |
| SEA 05D4 |
| 1 |
| 1 |
SHIP (via NAVSEA Authorized Representative) 1*
*Upon completion of incorporating the Government comments to the final delivery, the Technical Data Package shall be delivered as a set in both hard-copy and on a portable hard drive to the ship (via NAVSEA Authorized Representative).
ATTACHMENT 1 TO DATA ITEM NO DI-012 TECHNICAL DATA PACKAGE
| ATTACH 1 TO DATA ITEM NO (BLOCK 1) |
| DATA ITEM TITLE AND REFERENCE (BLOCKS 2 |
AND 3)
DATA DESCRIPTION (BLOCK 4)
REVIEW/APPROVAL REQUIREMENTS (BLOCK 5)
SUBMITTAL SCHEDULE (BLOCK 6)
| DI-012-01 |
| HULL LINES AND BODY PLAN |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-02 |
| MIDSHIP AND TYPICAL SECTIONS DRAWING |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-03 |
| SCANTLING PLANS, DECKS, AND PROFILES |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-04 |
| SHELL EXPANSION DRAWING |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-05 |
| MAIN ENGINES, GENERATORS, AND MISCELLANEOUS FOUNDATIONS |
| Main Engines, Generators, and Miscellaneous Foundations shall show the details of the foundations for the main engines, generators, and miscellaneous equipment. The drawing shall identify materials and dimensions of the foundations. |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-06 |
| PROPELLER, SHAFT, AND RUDDER OR Z-DRIVE ARRANGEMENT AND REMOVAL DRAWING |
| The Propeller, Shaft, and Rudder or Z-drive Arrangement and Removal drawing shall show the arrangement and clearances and sequences for removal of propellers, shafting, and rudders (or Z-drives). The drawing shall show lifting points and the associated loads. |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-07 |
| PROPELLER DRAWING |
| The Propeller Drawing shall include all necessary information used for manufacturing and shall completely define the geometry of the propeller including blade section offsets, pitch distribution, expanded area ratio, blade outlines, rake and skew angles, edge and blade thicknesses, anti-singing edge treatments (if required), hub shape and parameters, and shaft interface details. |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-08 |
| MAIN CONTROL CONSOLE AND SHIP CONTROL CONSOLE ARRANGEMENTS |
| The Main Control Console and Ship Control Console Arrangements shall show a scale drawing of each control console including monitors, keyboards, dedicated devices and controls, and third party equipment that is installed on the consoles. Each item shall be identified, including manufacturer make and model. Construction details shall include plan elevation views, installation details, and wiring data. Wiring data shall include specification, construction standard, insulation type, temperature rating, and type of |
shielding, if provided.
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-09 |
| INPUT/OUTPUT SIGNAL LIST |
| The Control Console Input/Output Signal List (hardwired, discrete, analog and serial) shall be provided in Excel format. Each point in the database shall be defined in detail including as a minimum connection details (terminations, cable numbers, etc.), signal types and levels, alarm parameters, scaling parameters, units, tag names, descriptions, and protocol (for serial interfaces only). |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-10 |
| TOPSIDE ARRANGEMENT DRAWING |
| The Topside Arrangement Drawing shall include top, port and starboard sides, bow, and stern views. Each view shall depict all topside equipment including masts, stacks, radars, antennas, navigational lights, lifesaving equipment, rails, stanchions, lifelines, boats, cranes, winches, vans and deck equipment, tie-down instruments and locations. The drawing shall include a List of Antennas for radars and antennas and contain the following columns: Antenna Number, Description, Nomenclature, Meters above Baseline, From AP/FP (MM), From CL (MM), Ship Side (P/S). Antenna numbering shall be in accordance with NAVSEAINST 9405.1A Numbering Identification System for Surface Ship Antennas. |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
PACIFIC TRAINING SUPPORT VESSEL
DATA REQUIREMENTS
CONTRACT NO.: N00024-19-R-2205 CONTRACTOR: TBD
DISTRIBUTION STATEMENT D: Distribution authorized to the Department of Defense and U.S. DoD Contractors only (Critical Technology, 12 May 2023). Other requests for this document shall be referred to PEO Ships PMS300, Washington Navy Yard, 1333 Isaac Hull Ave. SE, Washington, DC 20376-2101.
ATTACHMENT 1 TO DATA ITEM NO DI-012 TECHNICAL DATA PACKAGE
| ATTACH 1 TO DATA ITEM NO (BLOCK 1) |
| DATA ITEM TITLE AND REFERENCE (BLOCKS 2 |
AND 3)
DATA DESCRIPTION (BLOCK 4)
REVIEW/APPROVAL REQUIREMENTS (BLOCK 5)
SUBMITTAL SCHEDULE (BLOCK 6)
| DI-012-11 |
| RUNNING, ANCHOR, AND SEARCHLIGHTS PLAN |
| A Running, Anchor, and Searchlights Plan shall be provided to identify: |
1. Navigation lights, distance fore/aft, and height above the uppermost continuous deck.
2. Searchlight and signal light locations, type, and size.
Any sectors, which have blockages.
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-12 |
| ANCHOR HANDLING AND STOWAGE |
| The anchor system drawing shall show the locations of anchoring machinery and associated controllers, hawse pipes, chain lockers, anchor chain path, and other fixed equipment used for anchoring. The drawing shall identify locations of anchor chain swivels and detachable links. The drawing shall include procedures for detaching the anchors from the chains. The drawing shall include a list of fixed and portable anchoring equipment and fittings. The list shall include item noun name, manufacturer and model number, size, length, weight, rating and safe working load of each item as applicable. |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-13 |
| MOORING AND TOWING ARRANGEMENT |
| The Mooring and Towing Drawing shall demonstrate the orientation of the mooring systems with storm, breast, and spring lines shown. The drawing shall also illustrate the rigging of lines, bridles, and fittings for mooring to a pier, including the operation of the accommodation ladder or brow, in all expected tidal ranges. The drawing shall list fittings and hawsers, and shall include lengths, sizes, and description of each item used for the mooring systems. |
Calculations shall be provided confirming the ability of the mooring system to withstand design loads associated with pier-side mooring under pier-side and squall mooring configurations. The document shall depict the free body arrangement of the ship to the pier in the pier-side and squall mooring configurations.
1. The mooring system drawing shall show the arrangement and rigging of mooring winches, mooring lines, fenders, and chocks to be used for the following evolutions:
a. Pier side mooring.
b. Alongside mooring.
2. The mooring drawings shall also show stowage locations for mooring lines and wires. The mooring drawings shall identify environmental limits for each mooring configuration. The drawing shall include a list of equipment, fittings, and hawsers used for each mooring configuration. The list shall include noun name, manufacturer and model number, size, length, weight, rating and safe working load for each item as applicable. Typical structural details shall be provided.
3. The towing system drawing shall show the arrangement and rigging of towing fittings, tow lines, winches, bridles and fittings, and chocks used for towing the ship from the bow and stern. The drawing shall show stowage locations for tow lines and other portable towing equipment. The drawing shall include a list of equipment, fittings, and hawsers used for towing. The drawing shall clearly show bitts, chocks, and other fittings required for Panama Canal transit. The list shall include noun name, manufacturer and model number, size, length, weight, rating and safe working load for each item as applicable. Typical structural details shall be provided.
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-14 |
| STEERING GEAR ARRANGEMENT AND DETAILS |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-15 |
| RUDDER AND RUDDER STOCK ARRANGEMENT AND DETAILS |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-16 |
| THRUSTER ARRANGEMENT AND DETAILS |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-17 |
| COMPARTMENT ARRANGEMENT AND OUTFITTING DRAWINGS |
| The Compartment Arrangement and Outfitting Drawing shall show the interior arrangements of each space except tanks and voids to include compartment arrangements, equipment, joiner work, furnishings, and outfitting. Each compartment shall be labeled with the compartment name and number. The drawing shall show the clear floor area of crew cabins, sanitary spaces, offices, mess, galley, and lounges/recreation areas. A furniture and door schedule shall be provided in the drawing. |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-18 |
| DOOR, WINDOW, AND HATCH SCHEDULE |
| The Door, Window, and Hatch Schedule shall be broken down into the following categories: |
· Manhole List
· Window List
· Door List (Steel and Joiner)
· Hatch, Scuttle, and Bolted Equipment Removal Plate List Each list shall designate type, size, purpose, design, construction materials, manufacturing information, location of item, and what compartment the closure is providing access to.
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-19 |
| FLOOR GRATING ARRANGEMENT AND DETAILS |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
| DI-012-20 |
| RAILINGS, STAIRS, AND LADDERS ARRANGEMENT AND DETAILS |
| See Block 5 of DI-012 |
| See Block 6 of DI-012 |
ATTACHMENT 1 TO DATA ITEM NO DI-012 TECHNICAL DATA PACKAGE
| ATTACH 1 TO DATA ITEM NO (BLOCK 1) |
| DATA ITEM TITLE AND REFERENCE (BLOCKS 2 |
AND 3)
DATA DESCRIPTION (BLOCK 4)
REVIEW/APPROVAL REQUIREMENTS (BLOCK 5)
SUBMITTAL SCHEDULE (BLOCK 6)
| DI-012-21 |
| MACHINERY CENTRALIZED CONTROL SYSTEM DESCRIPTION OF OPERATIONS |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .