(USS BATAAN) Attachment S-3 PPI Responses BQs - A0004.pdf
PDF 124 KB Posted
- Solicitation number
- N0002423R4418
About this file
This document contains questions and answers related to a solicitation for the USS BATAAN (LHD 5) FY24 Docking Selected Restricted Availability.
The solicitation is for ship repair and maintenance services on the USS BATAAN including work items for preservation, inspection, and repair of various ship systems and components. It involves over 6000 line items of material and significant work associated with Joint Strike Fighter ship alterations. Subcontractors raised concerns about the number of items and long lead materials impacting their ability to provide accurate pricing within the response timeframe, especially with delays in receiving errata drawings and references from the Navy. While an extension was requested, the Navy was unable to grant additional time due to drydocking constraints and the ship's operational schedule after the availability.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question # Question Area Work Item Number(s) (if applicable)
Work Item Title(s) (if applicable)
Paragraph Reference(s) (if applicable) Contractor Question Government Response
4 551-53-002 3.7
Para 3.7 states to accomplish a 009-113 for each motor in 1.3.1.1.. These motors are not seal insulated systems. We recommend changing para 3.7 to read 009- 17 or 009-33. Concur. NSI changed to 009-17. See Errata 4.
6 992-11-010 3.1
Para 3.1 directs contractors to remove 650 each Decking Panels and 270 each Batterboards. Currently the package has two items already directing the contractor to remove all decking and batterboards in the well deck for structural inspection and repairs ( 120-11-001 and 130-11-001). We recommend this item, 992-11-010 be deleted since its already covered.
Do not concur. Each WI addresses a separate area of the well deck. WI 120-11-001 covers the Well Deck Wing Walls; WI 130-11-001 covers Well Deck Plate repairs; WI 992-11-010 covers the Well Deck Overhead.
11 863-50-001
This item is accomplished by the Ships Force and is usually deleted from the specifications in past avails. There is an item 992-11-009 where the contractors will provide T-1 Line for Computer Network. Recommend deleting 863-50-001. Work item canceled. See Errata 3.
26 Attachment J-10
Please confirm paragraph numbers in the Attachment J-10 for the following work items: 163-11-001, 163-11-003, 169-11-001, 311-11-001, 311-12-001, 311- 13-002, 311-14-001, 505-11-001, 584-13-001, 631-13-005, 631-31-001, 634-21-001. The updated J-10 is provided with Amendment 0004.
27 RFP
Non-Price Factor 2, Subfactor A – Manpower, Manpower Narrative, paragraph (v) requires: “Should the Offeror propose subcontracted resources for the solicited availability, the Offeror must explain which requirements the prime contractor will complete and which work the subcontractor will complete, including the work item, trade, and duration of each subcontracted requirement.” To successfully fulfil the level of detail required offerors would need to build resource loaded production schedules in support of their bid.
During the February 28, 2023 NAVSEA Industry Day, the Government indicated its intent to remove the requirement for offerors to build and submit fully resource loaded schedules as part of the bidding process and instead move toward offerors providing narratives that outline their logic and execution approach, acknowledging the time and resources associated with creating with these deliverables. USS Bataan solicitation contains the revised requirements detailed at the NAVSEA Industry Day in Non-Price Factor 3 – Schedule and Execution Approach.
We respectfully request this requirement be revised to remove the level of detail related to work item, trade, and duration from “identification which work the subcontractor will complete including the work item, trade, and duration of each subcontracted requirement” language in the solicitation as it creates an undue burden for offerors that is not closely related to the stated evaluation criteria of this section.
Change reflected in upcoming amendment. Maybe the answer is to remove the duration element, going from “which work the subcontractor will complete, including the work item, trade, and duration of each subcontracted requirement” To “which work the subcontractor will complete, including the work item and trade of each subcontracted requirement”
38 Attachment J-1 633-21-001 Impressed Current Cathodic
Protection
There are two issues with this item. 1) There is no requirement for an Evoqua Tech Rep to accomplish the inspections of the CAPAC System. 2) There is no requirement to remove and or reinstall the dielectric shields. Both of these are normally called out in the specification. Please confirm or revise the spec to include these 2 omitted requirements.
Q1. The requirement for OEM is needed and will be added in Errata 5. Q2. Dieletric shields do not have to be removed because they are already addressed in the Underwater Hull Item in Para. 3.12 of WI 361-31-001.
51 Attachment J-1 123-10-001 Tank and Void Cleaning and
Pumping; accomplish 3.1
For estimating purposes the Contractor requests the Govt. provide the quantities of petroleum products that will require removal and disposal?
The specific amounts of fluid in the tanks is unknown. Per para. 3.2.1.1, the sounding information of each tank will be provide by the supervisor prior to the start of each pumping operation. The following reference (801-6859466) has been added to assist Offeror in determining petroleum product, and ballast water amounts that will be required to meet the requirements of the work specification. Please be aware that some tanks will be required to have ballast water and fuel for power generation while entering dry-docking.
63 Attachment J-1 992-11-005 ERRATA 2 Ship Towing Service; provide 3.1
This item requires contractor to provide tug service, licensed pilot, and waterbore security to tow the ship from Naval Station Norfolk to repair facility and back to Naval Station Norfolk. Naval Station Norfolk will not allow contractor to tow ships to or from that facility that are being repaired locally. Item 992-11-002 paragrph 3.1 has contractor receiving and returning the ship, to the outer limits of the harbor (Hospital Point), this is the regular process for ships homeported / repaired in Norfolk. Will this item be revised to read for out of homeport bidders only?
There is no WI 992-11-002 in the work package. WI has been worded to capture requirement for all locations, per para 3.1, "when directed by the supervisor". Please price accordingly.
69 Attachment J-1 992-11-007 Temporary Service; provide 3.12
Paragraph 3.12 requires contractor to provide 3,500 gallons of fuel for ship's force. For estimating purposes what type of fuel? Will the fuel be required all at once or throughout the availability? Will the ship need a Fuel Cell and if so for what duration? Will the contractor be responsable for fueling ship's force equipment?
This question was previously answered. Reference was provided by SEA02.
79 Section L N/A N/A N/A
Section L, Paragraph IV Proposal Format requirements state that all pages shall be formatted to 8.5x11 inch paper with one inch margins.Will the Government allow up to 11x17 inch paper for the Factor 3, Emphasis Area B, Overarching Schedule? Previously answered. See response to question #5.
80 Attachment J-1 138-90-001 SA 82042K JSF MOD 2.34 LAR 82042-LHD5-HIPPY-0103-23 RLAR 82042/LHD5/D017 is missing from the package. Please provide these References LAR number referenced believed to be incorrect, correct number believed to be 82042-LHD5-HIIPY-0109-23, RLAR 82042/LHD5/D017. Missing reference provided by SEA02.
81 Attachment J-1 512-90-001 SA 82038K JSF MOD 2.15 LAR 82038-LHD5-DO35--HIPPY-0173-23 is missing from the package. Please provide this Reference References provided by SEA02.
82 Attachment J-1 721-90-001 SA 82035K JSF MOD 2.11, 2.55, 2.56, Drawing 8906898, 8906897, LAR 82035-LHD5-DO28-HIPPY-0160-23 are missing from the Package. Please provide these References References provided by SEA02.
83 Attachment J-1 772-90-001 SA 71563K JSF MOD 2.64 LAR 71563-LHD5-HIPPY-0113-23 is missing. Please provide this reference References provided by SEA02.
84 311-90-001 SHIPALT LHD-81159K 3.1.12
Para 3.1.12 requires foundation bolt holes to be reamed. In ref 2.5 note S-1 requires that all existing fasteners be discarded and new fasteners will be supplied with equipment. Confirm if new mounting bolts will be required for the newly reamed foundation bolt holes. Concur. New mounting bolts are required and are provided with the generator.
85 311-90-001 SHIPALT LHD-81159K 3.17 & 3.18
Para 3.17 states that the Ssystem Operational Verification Testing ( SOVT) for the Generator Upgrades will be the responsibilty of NSWCPD. Para 3.18 States to provide one load bank for testing 24 hours a day for 21 days, the requirement makes no mention of test cables or load bank operator. Is it the responsibility of NSWCPD to operate the load banks or is it desired that shipyard personnel be made availble to install the cabling and operate the test equipment (load bank)?
Paragraphs 3.18.3 and 3.18.5 have been updated to clarify requirement for LMA to provide, install and remove when directed by the SUPERVISOR all cabling required to support load bank operation during testing. Para 3.18 already contains verbiage about the requirement for a 24 hour load bank operator to be provided. See Errata 5.
86 311-90-001 SHIPALT LHD-81159K 3.17
Is there a test memo that will be invoked for the testing of the new generator sets? Will there be a checkpoint called out for this operational/load test?
There is not a test memo invoked in the work item.
ISEA will have an AIT rep on board to help with the testing evolution, including any wiring issues found from the installation. There is no checkpoint for testing.
87 RFP
This bid has been out for a month with 3 sets of questions submitted. The Government has not responded to any questions or provided missing references.
Without this information, it presents an extreme burden on all parties, including disadvantaged small business subcontractors, to provide full & complete proposals to present the Governnment with a Best Value and accurate proposal in the amount of time allowed. Again the Contractor request the Government provide this missing information ASAP and extend the bid date at least 3 weeks.
Due to the drydocking constraints in the region, as well as the strict operational schedule of the ship post-availability, we are unable to grant an extension.
88 Section L N/A N/A N/A
Section L, Volume II, Non-Price Proposal requirements state: Do not include cost or price information in this volume. In Section L, Non-Price Factor 2, Subfactor B, paragraph a states that the narrative shall…clearly describe the Offeror's understanding...and approach...and participation of small business in terms of the total acquisition expressed both in dollars and percentage." Please clarify if the dollar values of small businesses are to be disclosed in the technical volume to meet this requirement, or percentages only.
Small Business Participation should be described as a percentage of the total contract value only. Dollars should not be disclosed in the technical volume.
USS BATAAN (LHD 5) FY24 Docking Selected Restricted Availability N00024-23-R-4418
NAVSEA POC:
Jon Pagnucco, jonathan.p.pagnucco.mil@us.navy.mil
Hannah Bourassa, hannah.e.bourassa.civ@us.navy.mil
90 Attachment J-1 529-61-001 No. 1, 4 and 5 Deballast compressor; replace para. 3.2 Are the existing Deballast Compressors going to be overhauled. The Spec item does not address this. No, the compressors are not being overhauled, they are being replaced. See para 5.1.1. for replacement compressor information.
91 Attachment J-1 437-90-003 (E1) ShipAlt LHD1-92190K, Ballast and Damage Control Upgrade;
REF: 2.32, 4720-LHD5-FY24-SA92190,
Ship Alteration Material Summary
(4720/3)
Missing document # 2.32, 4720-LHD5-FY24-SA92190, Ship Alteration Material Summary (4720/3); GFM listing for this item was not included in the references. Please provide. 4720 document provided by SEA02.
92 Attachment J-1 997-11-001 Drydocking and Undocking;
accomplish 2.4 Please provide reference 2.4 S9086-7G-STM-010/CH-997 Rev 3 References provided by SEA02.
93 Attachment J-1 512-90-001
ShipAlt LHD7-82038K, Joint Strike Fighter (JSF) Topside
Mods:
HVAC Supply Vent Mods;
accomplish 2.15
Please provide reference 2.15 LAR 82038-LHD5-D035-HIIPY-0173-23 References provided by SEA02.
94 Attachment J-1 721-90-001
ShipAlt LHD1-82035K, Joint Strike Fighter (JSF) Topside
Modification: Warfare System;
accomplish 2.56
Please provide reference 2.56 LAR 82035-LHD5-D028-HIIPY-0160-23 References provided by SEA02.
95 Attachment J-1 772-90-001
ShipAlt LHD1-71563K, Joint Strike Fighter Weapon and
Staging Area; accomplish 2.64
Please provide reference 2.64 LAR 71563-LHD5-HIIPY-0113-23 References provided by SEA02.
96 Attachment J-1 484-90-001
ShipAlt LHD1-98552K, Ship Self Defense System (SSDS) MK 2
LHD
Upgrade Advanced Combat
Direction System (ACDS) Block 0 TO MK 2 Mod 3E;
accomplish (OPTION ITEM) 2.22 & 2.23
Please provide reference 2.22 411-8906839, ShipAlt LHD1-98552 SSDS Mk 2 Mod 3E Removal Blk Wrg Diag, 2.23 4720-LHD5-FY24-SA98552, Ship Alteration Material Summary (4720/3) References provided by SEA02.
97 Attachment J-1 665-90-001
ShipAlt LHD1-82046K, JSF Joint Strike Fighter (JSF) Shops and
Services; accomplish 2.28, 2.29, 2.30
Please provide reference 2.28 183-8739604, ShipAlt LHD1-82046 Mod to Fdns, Reference 2.29 LAR 82046-LHD5-D021-HIIPY-0057-23, Ametek/Magnetrol Cannot Produce Flow Sensor W/Tee Assembly Per (P/N 052-7201-S16), and reference 2.30 4720-LHD5-FY24-SA82046, Ship Alteration Material Summary (4720/3)
References provided by SEA02.
98 Attachment J-1 665-90-002
ShipAlt LHD1-71836K, JSF Airborne Expendable
Countermeasures (AECM) Prep; accomplish 2.24, 2.25
Please provide reference 2.24 LAR 71836-LHD5-N/A-HIIPY-0060-23, ShipAlt 71836, Joint Strike Fighter AECM Prep Room, Door Schedule/LOM Contradiction, RLAR 71836/LHD5/D006 and reference 2.25 LAR 71836-LHD5-HIIPY-0158-23, Joint Strike Fighter AECM Prep Room References provided by SEA02.
99 Attachment J-1 700-90-001
ShipAlt LHD1-82876K, Common Munitions BIT/Reprogramming
Equipment (CMBRE); accomplish 2.9
Please provide reference 2.9 4720-LHD5-FY24-SA82876, Ship Alteration Material Summary (4720/3) 4720 document provided by SEA02.
100 Attachment J-1 763-90-001
ShipAlt LHD1-92217K, Navy Amphibious Baseline (NAB)
LHD/LHA
Armory Modernization;
accomplish 2.22, 2.24, 2.26
Please provide reference 2.22 602-8802493, reference 2.24 631-8802495, and reference 2.26 665-8802497 References provided by SEA02.
101 Attachment J-1 251-80-001
ShipAlt LHD1-81746, Port Use Fan Actuator Upgrade;
accomplish 2.9 Please provide Reference 2.9 LAR 11746-LHD5-HIIPY-0165-23, Revision of SIDS for SCD 11746 on LHD5 References provided by SEA02.
102 Attachment J-1 255-80-001
ShipAlt LHD1-94288D, Feedwater Control Valve and
Positioner Replacement; accomplish 2.5
Please provide reference 2.5 LAR 94288-LHD5-D011-HIIPY-0084-23, Commercial Pressure Gage Used for Grade "A" Feed-Water Control Valve References provided by SEA02.
103 Attachment J-1 311-90-001
ShipAlt LHD1-81159K, LHD1 Class SSTG Generator Upgrade;
accomplish 2.43 Please provide reference 2.43 LAR 811599-LHD5-D010-HIIPY-0072-23, SSTG Generator & Voltage Reg References provided by SEA02.
104 Attachment J-1 313-90-001
ShipAlt LHD1-83220K, Lithium- Ion Battery Shop to Support Joint Strike Fighter (JSF);
accomplish 2.36, 2.37, 2.38
Please provide reference 2.36 LAR 13220-LHD5-D015-HIIPY-0101-23, LHD5 - Lithium-Ion Battery Shop To Support JSF - Bell Obsolescence, reference
2.37 LAR 83220-LHD5-D032-HIIPY-0166-23, Lithium-Ion Battery Shop to Support JSF, and reference 2.38 4720-LHD5-FY24-SA83220, Ship Alteration Material Summary (4720/3)
References provided by SEA02.
105 Attachment J-1 436-90-001
ShipAlt LHD1-92216K, Advanced Damage Control
System (ADCS) Installation; accomplish 2.11- 2.14
Please provide reference 2.11 LAR 92216-LHD5-D016-HIIPY-0107-23, LHD5 ADCS LAN Terminations Missing DCRS 2A 1-54-2-A in SID Package, reference 2.12 LAR 22216-LHD5-002-NSWCPD-0187-23, LHD5 ADCS LAN Terminations Missing DCRS 2A 1-54-2-A in SID Package, reference 2.13 LAR 22216-LHD5-001-NSWCPD-0515-22, Incorrect Location of Flat Panel Display in Damage Control Central for ADCS, and reference 2.14 4720-LHD5- FY24-SA 92216, Ship Alteration Material Summary (4720/3)
References provided by SEA02.
106 Attachment J-1 612-90-001
ShipAlt LHD1-82047K, Joint Strike Fighter (JSF) Safety Net, Life Rail and Guard Line Modification; accomplish TIER 2 FROM PARA. 2.4
TIER 2 REQUEST OFF DRAWING # 612-8906477. A vendor is requesting drawing # 6126366 Drawing in question is not referenced in WI 612-90-001.
Amendment 0002 cancelled CLIN 0025, it also cancelled the growth work associated with that item, (CLIN 0100). This changed the amount of Growth manhours and material on the J-4 Workbook. However, the Government did not change Section B of the soliictation to reflect the Change to J-4. Please update Section B of the Solicitation page 102 to match J-4.
Concur. Change will be reflected in an upcoming amendment.
110 RFP
We’ve provided our subcontractor base the Government responses received to-date and are now fielding concerns on their ability to provide full & complete proposals in this limited time frame, given the number of references, line items, and the fact that many missing references were only just received under Amendment 0001. Further, errata 3 was just received 9/12/23 and 9 additional LARs were added to the package without the Government providing the LAR's.
The Allup 4720 was just recieved 9/13/23. Government Responses indicate an errata 4 & 5 are forthcoming but not issued yet. The Government cannot possibly expect contractors to be able to provide a good proposal in this short time frame without the required information. We respectfully request a minimum 3 week extension to help ensure the best possible proposal product in support of this solicitation.
Due to the drydocking constraints in the region, as well as the strict operational schedule of the ship post-availability, we are unable to grant an extension.
111 Attachment J-1 313-90-001 SA 83220K 2.38 LAR 83220-LHD5-HIPPY-0200-23 was not received with A0002. When can the contractor expect to receive these missing references References provided by SEA 02.
112 Attachment J-1 437-90-001 SA 91999K 2.9 LAR 91999-LHD5-D040-HIPPY-0185-23 was not received with A0002. When can the contractor expect to receive these missing references References provided by SEA 02.
113 Attachment J-1 437-90-002 SA 981818K 2.27 LAR 81818-LHD5-D037-HIPPY-0192-23 was not received with A0002. When can the contractor expect to receive these missing references References provided by SEA 02.
114 Attachment J-1 437-90-003 SA 92190K 2.32, 2.33. 2.34
LAR 22190-LHD5-D049-HIPPY-0195-23, LAR 92190-LHD5-D037-HIPPY-0198-23 & LAR 92190-LHD5-D036-HIIPY-0180-23 were not received with A0002. When can the contractor expect to receive these missing references References provided by SEA 02.
115 Attachment J-1 438-90-001 SA 85154K 2.22 LAR 85154-LHD5-D043-HIPPY-0188-23 was not received with A0002. When can the contractor expect to receive these missing references References provided by SEA 02.
116 Attachment J-1 663-90-001 SA 82483K 2.53 LAR 82483-LHD5-N/A-HIPPY-0186-23 was not received with A0002. When can the contractor expect to receive these missing references References provided by SEA 02.
117 Attachment J-1 721-90-001 SA 82035K 2.57 LAR 82035-LHD5-NA-HIPPY-0193-23 was not received with A0002. When can the contractor expect to receive these missing references References provided by SEA 02.
118 RFP
Set No 4 is the last set of questions to be submitted. With the pending errata 4, 5 and responses from the Government, these are likely to cause the need for more clarification. We would ask the Government to add an additional set.
The contractor is not precluded from submitting additional questions, however, per Section L, para I.C, "The Government reserves the right to not answer any more than four sets of PPI requests per contractor, in accordance with the deadlines identified herein."
119 RFP
Mulitple Subcontractors have idetnified that the number of items, including significant JSF ShipALTs items and over 6000 line items of material that need to obtain accurate pricing as well as identify long lead time/problematic material is compounded by the delays in receiving ERRATA drawings. Due to the size and scope of thework pacakge, the number of days to provide a comprehensive bid package is insufficient for our vendors, especially the small, firm fiexed subcontractors. Contractor respectfully requests an additional 2 weeks until 10/24/23 to provide a response to this RFP.
Due to the drydocking constraints in the region, as well as the strict operational schedule of the ship post-availability, we are unable to grant an extension.
120 Attachment J-1 631-31-002 Underwater Hull Preservation 3.2.5 Does Prime intend to provide paint for staboard side test patch GFM ? Also who is responsible for bringing in the paint manufacture’s tech ? Contractor is responsible for all test patch paint procurement. NSWCCD is responsible for providing paint OEM reps.
121 Attachment J-1 631-41-001 Freeboard; preserve 3.4-3.4.1 The kearsaerge requested 2 Line 53 for this same work item and not Table 2 line 54. Was this an error ? Will a correction be released if so ? The FY 24 CSWT for Freeboard preservation calls out line 54 as directed by SURFMEPP engineering. No change required.
122 Attachment J-1 721-90-001 E-1
ShipAlt LHD1-82035K, Joint Strike Fighter (JSF) Topside
Modification: Warfare System Accomplish REF: 2.57
Missing document # 2.57, 4720-LHD5-FY24-SA82035, Ship Alteration Material Summary (4720/3); GFM listing for this item is not available please provide.4720 document provided by SEA 02.
123 Attachment J-1 634-11-002 Chemical-Resistant Floor Covering System; install 2 Contractor requests a drawing to estimate square footage for 009-26 or for customer to specify square footage. There are no references specified. References provided by SEA 02.
124 Attachment J-1 634-11-003 Terrazzo Deck Covering System;
install 2 Contractor requests a drawing to estimate square footage for 009-26 or for customer to specify square footage. There are no references specified. References provided by SEA 02.
125 Attachment J-1 634-11-005
Deck Covering, Electrical Grade Sheeting Replacement;
accomplish 2 Contractor requests a drawing to estimate square footage for 009-26 or for customer to specify square footage. There are no references specified. References provided by SEA 02.
126 Attachment J-1 634-11-006 Porcelain Tile Deck Covering
System; install 2 Contractor requests a drawing to estimate square footage for 009-26 or for customer to specify square footage. There are no references specified. References provided by SEA 02.
127 Attachment J-1 313-90-001
ShipAlt LHD1-83220K, Lithium- Ion Battery Shop to Support Joint Strike Fighter (JSF); accomplish 2.38
2.38 LAR-83220-LHD5-HIIPY-0200-23, Lithium-Ion Battery Shop to Support JSF, Material Change, RLAR 83220/LHD5/ References provided by SEA 02.
128 Attachment J-1 437-90-001
ShipAlt LHD1-91999K, Salinity Indication System (SIS);
accomplish 2.9 & 2.10
2.9 LAR-91999-LHD5-D040_HIIPY-0185-23 Rev A, Correct Detail 14-B and Remove Connectors from PLC & 2.10 4720-LHD5-FY24-SA91999, Ship Alteration Material Summary (4720/3) References provided by SEA 02.
129 Attachment J-1 437-90-002
ShipAlt LHD1-81818K, Propulsion-Auxiliary-Damage
Control Upgrade; accomplish 2.27
2.27 LAR-81818-LHD5-D037_HIIPY-0192-23, Cat-5E Exceeds Maximum Length Requirement References provided by SEA 02.
130 Attachment J-1 437-90-003 ShipAlt LHD1-92190K, Ballast and Damage Control Upgrade 2.32 - 2.35
2.32 LAR-22190-LHD5-D049_HIIPY-0195-23, LHD5 Ballast and Damage Control Console Replacement-Legacy DC Console Assembly, 2.33 LAR-92190-LHD5-D038_HIIPY-0198-23, LHD Ballast and Damage Control Console Replacement, 2.34 LAR-92190-LHD5-D036_HIIPY-0180-23, ASW Thermowell Part Number, 2.35 4720-LHD5-FY24-SA92190, Ship Alteration Material Summary (4720/3)
References provided by SEA 02.
131 Attachment J-1 438-90-001
ShipAlt LHD1-85154K, Integrated Ship Control
Installation 2.22
2.22 LAR-85154-LHD5-D043_HIIPY-0188-23, Replace an Obsolete Part Number with an Active Number References provided by SEA 02.
132 Attachment J-1 663-90-001 ShipAlt LHD1-82483K, Capstone Space Arrangement; accomplish 2.53 & 2.54
2.53 LAR-82483-LHD5-N/A_HIIPY-0186-23, SA 82483 Console Foundation Cover Plate & 2.54 4720-LHD5-FY24-SA82483, Ship Alteration Material Summary (4720/3) References provided by SEA 02.
133 Attachment J-1 721-90-001
ShipAlt LHD1-82035K, Joint Strike Fighter (JSF) Topside
Modification: Warfare System;
accomplish 2.57 & 2.58
2.57 LAR-82035-LHD5-NA_HIIPY-0193-23, S/A 82035 JSF Topside Mods: Warfare Systems, Incorrect Lom Description, Rlar 82035/LHD5/D048 & 2.58 4720-LHD5-FY24-SA82035, Ship Alteration Material Summary (4720/3) References provided by SEA 02.
134 Attachment J-1 763-90-001
ShipAlt LHD1-92217K, Navy Amphibious Baseline (NAB)
LHD/LHA
Armory Modernization;
accomplish 2.29 -2.30
2.29 LAR-92217-LHD5-D046_HIIPY-0191-23, Locker Interference with Existing Vac in SQN Armory (01-110-7-Q) & 2.30 4720-LHD5-FY24-SA92217, Ship Alteration Material Summary (4720/3) References provided by SEA 02.
135 Attachment J-1 321-90-001
ShipAlt LHD1-71492K, HESS (400Hz) Line Voltage Regulator
Upgrade; accomplish 2.7
Reference 2.7 320-8906235 Rev A thidentifies the cable listed for installation is 1185 ft LSYSGU-4. However, in the GFM list line item 21 list issuance of 1185 ft of LSYSGU-40 cable. Please confirm if it should be LSYSGU-40 or LSYSGU-4.
The correct item number is LSYSGU-40. A request to update the drawing has been submitted.
136 Attachment J-1 430-11-001 Fire Damaged Electrical Cable 3.1, 3.1.1
We realize this is outside the submittal date of the last set, but this issue needs to be addressed. Para 3.1 states to remove existing and install new cable listed in Attachment A. Attachment A shows 9150 ft. Then para 3.1.1 states the type and quantity listed in 1.3.3 through 1.3.5 is for estimating purposes. Those para are only listing 600 ft. of cable. Please confirm the contractor is to renew the list in Attachment A. 9150 ft. of cable.
Please install all of the cable as listed in Par 3.1.1 of the work item and the all of the cable in Attachment A, as stated in Para 3.1.
137 Attachment J-1 484-90-001 SA 98552K 2.22 We realize this is outside the submittal date of the last set, but this issue needs to be addressed. Ref. 2.22 was not received with the package. Please provide this drawing ASAP.
Reference provided by SEA02.
138 Attachment J-1 484-90-001 SA 98552K 3.1.5
, g q p install new equipment requiring rigging as specified in 2.21 LIST OF MATERIAL Item Numbers 1-6, 8, 11, 13, 14 and in 2.22 LIST OF MATERIAL TO BE REMOVED Item Numbers 101-103, 105 - 109, 112-114, 116-120, 125-129. Please confirm AIT will accomplish Ref. 2.21 and 2.22 and the contractor will unbolt and bolt equipment and provide the rigging in support of the AIT
Confirmed. AIT will execute refs 2.21 and 2.22, contractor to unbolt/bolt equipment and provide rigging in support of the AIT.
139 Attachment J-1 472-90-001 SA 80156K SLQ32 Although this is outside the Sets, this issue needs to be addressed. This item has several discrepancies Please see this list in Attachment A provided.
The LHD 5 drawings were not complete at time of solicitation and will be updated via RCC post award. Current drawings are sufficient to allow for estimating purposes.
140 Attachment J-1 221-11-001 No One Mn Propulsion Boiler 5
Year (ASI) 3.5.9.1 We realize this is outside the question period, but this issue needs to be addressed. Para 3.5.9.1 states to install new expansion joint bellow IAW 2.12. There is not enough information in para 3.5.9.1 to identify an expansion joint bellow. Please provide more information or delete this para from the spec.
The Bellows part numbers are listed as Find #'s F13 and F14 on Ref 2.12.
141 Attachment J-1 221-12-003 No Two Mn Propulsion Boiler 5
Year (ASI) 3.5.9.1 We realize this is outside the question period, but this issue needs to be addressed. Para 3.5.9.1 states to install new expansion joint bellow IAW 2.12. There is not enough information in para 3.5.9.1 to identify an expansion joint bellow. Please provide more information or delete this para from the spec.
The Bellows part numbers are listed as Find #'s F13 and F14 on Ref 2.12.
143 Attachment J-1 311-90-001
ShipAlt LHD1-81159K, LHD1 Class SSTG Generator Upgrade;
accomplish 3.1
Vendor for the replacement generators have advised that the lead time is 44-56 weeks, greatly reducing the time for the contractor to accomplish this item prior to the assigned milestone since work cannot commence unitl the generator's are in hand. The replacement generators and accessories have been provided as GFM on past avails for this class upgrade. Will the government provide these as GFM?
Concur. The generators are provided as GFM. See Errata 6.