N00024-19-R-4442_BQ__3_23MAY2019.pdf
PDF 118 KB Posted
- Attached to
- Ship Repair IDIQ-MAC for Hawaii CNO Availabilities, Emergent Maintence and Continuous Maintenance
- Solicitation number
- N00024-19-R-4442
About this file
This document contains a solicitation for ship repair Indefinite Delivery Indefinite Quantity-Multiple Award Contracts (IDIQ-MACs) for the Naval Sea Systems Command (NAVSEA). The solicitation seeks to award multiple contracts for complex and non-complex emergent maintenance and continuous maintenance, as well as Chief of Naval Operations scheduled availabilities for homeported and visiting ships in Hawaii. The requirement is separated into two lots: Lot 1 includes complex availabilities and will be solicited on an unrestricted basis. Lot 2 includes non-complex work and is set aside for small business. The contracts will include a base year and four option periods. This solicitation is for firm fixed price contracts. The supply being procured is the repaired, mission-ready vessel returned to service within the Fleet.
Bidders Questions #3.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATE OF REQUEST: Thursday, May 23, 2019 HULLS/TITLE: Hawaii MAC IDIQ
SOLICITATION NO: N00024-19-R-4442
NAVSEA POCs:
Martha Bello Zachary Tucker
NAVSEA POC E-MAIL:
Martha.Bello@navy.mil Zachary.M.Tucker@navy.mil
NAVSEA POC #:
Martha Bello: 202-781-3864 Zachary Tucker: 202-781-4234
# Question Area Para # Date Received Contractor Question Government Response
32 Hazardous Waste Generator Number
Para 1.2 & 5.0, Page No.
20 & 93 11-Apr-19
The Contractor’s experience with similar Lot 2 work has been that all Hazardous Material/Waste is produced within the Shipyard/on board ships and disposed of in accordance with Shipyard policies, therefore a hazardous waste generator number is not required. Would the Government consider revising the requirements on pages 20 and 93 to remove the requirement for the offeror to provide a hazardous waste generator number?
The Contractor is not required to obtain or maintain a hazardous waste generator number; instead, the Contractor will use the Pearl Harbor Naval Shipyard hazardous waste generator number. The Government has removed the requirement for the offeror to provide a hazardous waste generator number via Amendment 0002.
Section M - Evaluation Factors for Award. 3.0 Evaluation Factors / Volume II - Non-
Price Proposal.
Factor 5 -
Management and Technical
Experience.
RFP Page No.
17-Apr-19
Page 107 of Section M in the RFP provides the below characteristics for a typical CNO availability and for a CMAV:
For Complex Lot 1, the proposed Technical experience event must be similar in scope to managing one (1) Selected Restricted Availability. A typical CNO
Availability has the following characteristics:
o Include approximately 18,000 man-days worth of maintenance, modernization and repair include work covering multiple trades and systems o Reflects the Navy’s average historical craft/trade labor experienced on previous CNO Availabilities provided in Section L, Factor 3.
o Reflects the Navy’s average historical work distribution across systems experienced on previous CNO Availabilities provided in Section L, Factor 3.
For Non-Complex Lot 2, the proposed Technical experience event must be similar in scope to managing two (2) concurrent Continuous Maintenance Availabilities (CMAV) work packages to be relevant. A typical CMAV has the following characteristics:
o Include approximately 1,000 man-days worth of maintenance, modernization and repair include work covering multiple trades and systems o Reflects the Navy’s average historical craft/trade labor experienced on previous Continuous Maintenance Availabilities provided in Section L, Factor 3.
o Reflects the Navy’s average historical work distribution across systems experienced on previous Continuous Maintenance Availabilities provided in Section L, Factor 3.
Question: While this provides an approximate number of mandays, it does not provide a production duration to associate with the number of mandays to enable a determination of the number of resources required to complete the work. Request the government provide an approximate production duration for a typical CMAV and typical CNO availability in conjunction with the mandays provided.
Section L, Factor 3 Lot 1 and Lot 2 has been revised via Amendment A0002 to state, "Approximate Production Duration: CMAV: 25 Days and Selected Restricted
Availability: 158 Days"
Section B - Note B - Fixed Ship Repair Labor & Material
Burden Rates (Ceiling Rates)
RFP Page No.
14-15
18-Apr-19
Ref NOTE B (pages 14-15) provides guidance on development of a Fully Burdened Man Day Rate. Paragraph 3 on p. 15 states “ fully burdened ship repair labor rate is a fixed hourly rate that includes all wages (e.g.straight time, overtime, shift differential, holiday time, standby time, etc.) overhead, general, and administrative expenses, Facilities Capital Cost of Money (FCCOM) and profit. The fully burdened ship repair labor rate represents the ceiling for the blended rate to be performed by the offeror, including labor transferred between divisions, subsidiaries, or affiliates of the offeror under a common control.”
Question: Traditionally, large CNO availabilities executed in Pearl Harbor have required some level of off-island trade resources to travel to Hawaii to support the scheduled scope of work. However, no travel is included in the pricing submission as part of this solicitation. What is the Government’s intention to compensate the contractor for the travel costs associated with traveling personnel from the mainland? Should the contractor include travel costs in the burdened hourly rate in our proposal? Would the government consider including an unpriced travel line that could be evaluated on a delivery order by delivery order basis as a competitive price discriminator for award of each availability?
The Statement of Work has been updated to include Travel. Additionally, travel CLINs with an estimated value have been added to Section B and Attachment J-1. The offeror shall not include travel costs within the Fully Burdened Man Day Rate. A not-to-exceed amount will be issued on each delivery order.
Solicitation, Section L, Para. 5.0 Proposal Content
Factor 4; Past Performance;
Scope, Page
No. 96
22-Apr-19 Under "Scope," the solicitation directs offerors to provide relevant past performance data that demonstrates "Experience in the areas defined in the
SOW." Please define the work scope that offerors are supposed to provide past performance data against.
The Offeror shall demonstrate management capability in accordance with Factor 2 to complete the type of work that corresponds to the lot proposed in Factor 3.
Section L and M have been revised via Amendment A0002.
Pre-Proposal Information (PPI)
The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.
QUESTION #/ DETAILS QUESTION/ ANSWER
36 Solicitation:
Section H
Page No. 57 22-Apr-19
1. Section H includes a ROLLING ADMISSIONS FOR FUTURE ADDITIONAL IDIQ-MAC HOLDERS, which states, "The Government reserves the right to determine whether it would be appropriate to announce a new competition for the purpose of adding additional IDIQ-MAC holders. Periodically, the Government will assess the quality of performance by each IDIQ-MAC holder, the number, value and complexity of work assigned to each holder and amount of competition achieved."
Please clarify the word "Periodically”. Does this mean annually, semi-annually or other period?
2. SECTION H includes ROLLING ADMISSIONS FOR FUTURE ADDITIONAL IDIQ-MAC HOLDERS, which states, "Periodically, the Government will assess the quality of performance by each IDIQ-MAC holder, the number, value and complexity of work assigned to each holder and amount of competition achieved."
Please clarify in what form these "periodic reviews" will take place. Would this periodic review be in addition to the annual CPAR assessment and review?
3. SECTION H includes ROLLING ADMISSIONS FOR FUTURE ADDITIONAL IDIQ-MAC HOLDERS, which states, "In addition, the Government will assess the internal transaction cost for issuing each delivery order and whether revisions are needed to the scope of the Statement of Work (SOW)."
Please clarify what is meant by "assess the internal transaction cost" and what will be expected from the successful awardees in relation to this statement?
1. In accordance with Section H Clause, “The Government reserves the right to determine whether it would be appropriate to announce a new competition for the purpose of adding additional IDIQ-MAC holders.”
2. The government reserves the right to assess the performance of the contractor at any point (in addition to CPARS) to ensure this is in the best interest of the government.
3. Section H has been revised via Amendment A0002 to remove this language.
37 Solicitation:
Section I
FAR 52.211-
11. Page No.
22-Apr-19
Section I calls out "FAR 52.211-11 Liquidated Damages . . . (End of Clause) *To be specified in each Delivery Orders, as applicable."
1. Please clarify why the Government chose not to include such factors during the competitive MAC IDIQ solicitation as that would allow a potential offeror to assess a financial business risk to determine whether a pursuit is a viable business option.
2. Will the Government include a ceiling limit on total liquidated damages that a successful offeror would be assessed?
1. The Government chose not to include such factors during the competitive MAC IDIQ solicitation because the liquidated damage factors are ship and availability specific.
2. FAR 52.211-11 has been revised via Amendment A0002 to state,"The sum of liquidated damages shall not exceed 10% of the awarded price of each Availability, including all Base and Option Items."
38 CDRL A001
Block 10 and
22-Apr-19
Per Blocks 10 and 13 - this CDRL requires a "final report" to be submitted "NLT 60 after end of availability (EOA)". The award will be a competitive MAC IDIQ FFP award with individual Delivery Orders awarded as FFP with a specific period of performance (POP). If all contractor work is deemed complete at the completion of the FFP effort, then no further work is required past that period of performance. Please modify this CDRL to remove the reporting requirement that requires contractor to continue work performance past the (POP).
In accordance with FAR 52.219-9(l), "A report must be completed within 30 days of contract completion." The CDRL has been amended to reflect 30 days vice 60.
39 CDRL A005
DID DI-
MGMT-
81616
22-Apr-19 CDRL A005, Block 4, references DID "DI-MGMT-81616" which does not exist in the Assist Database. Please provide this DID "DI-MGMT-81616" or confirm that no DID should be referenced in Block 4, or confirm the correct reference DID that should be in Block 4.
CDRL A005, Block 4, has been modified with the correct DID reference "DI-MISC-
81616".
40 CDRL A008
DID "DI-MISC-
81794", Exhibit A
22-Apr-19 CDRL A008, Block 4, references DID "DI-MISC-81794" which does not exist in the Assist Database. Please provide this DID "DI-MISC-81794" or confirm that
Block 4 should reference DID DI-QCIC-81794 on the CDRL.
CDRL A008, Block 4, has been modified with the correct DID reference "DI-QCIC-
81794".
CDRLs B001, B002, B003, B004, B005, B008, and B009
DID "DI-
MGMT-
81806", Exhibit B; DID
"DI-SESS-
81759", Exhibit B; DID
"DI-SESS-
81758", Exhibit B
22-Apr-19
1. CDRL B009, Block 4, references DID "DI-MGMT-81806" which is no longer in effect. DID DI-MGMT-81806 was superseded by DI-MGMT-81806B. Please confirm the correct DID referenced in Block 4 on the CDRL and revise the CDRL.
2. CDRLs B001, B002, B003, B005 and B009 Block 4, references DID "DI-SESS-81759" which is no longer in effect. DID DI-SESS-81759 was superseded by DI- SESS-81759A. Please confirm the correct DID referenced in Block 4 on each CDRL and revise each CDRL.
3. CDRLs B004 and B008, Block 4, references DID "DI-SESS-81758" which is no longer in effect. DID DI-SESS-81758 was superseded by DI-SESS-81758A.
Please confirm the correct DID referenced in Block 4 on the CDRL and revise the CDRLs.
1. CDRL B009, Block 4, has been modified with the correct DID reference "DI-MGMT- 81806B".
2. CDRLs B001, B002, B003 and B005, Block 4, has been modified with the correct DID reference "DI-SESS-81759A".
3. CDRLs B004 and B008, Block 4, has been modified with the correct DID reference
"DI-SESS-81758A".
BQ #3