SEE ADDENDUM
(No Collect Calls) N0002418R2209
b. TELEPHONE NUMBER 202-781-2385
8. OFFER DUE DATE/LOCAL TIME
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Govt. Use Only)
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
N00024 9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
BRENDAN P BYRNE
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
N0002418NR53091
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR: SET ASIDE: UNRESTRICTED OR X
SMALL BUSINESS X
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
NAVAL SEA SYSTEMS COMMAND (HQ)
1333 ISAAC HULL AVE SE
WASHINGTON NAVY YARD DC 20376-2020
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE 15. DELIVER TO CODE N4523A 16. ADMINISTERED BY
12. DISCOUNT TERMS 11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFP X
PUGET SOUND NAVAL SHIPYARD CODE 400
RAY YARNELL
2000 WEST MARINE VIEW DR CODE 440
EVERETT WA 98207-2400
TEL: 360 535 2750 FAX: (425) 304-4028
FAX:
TEL: SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
NAICS:
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICES ITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24. 22. 21. 19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINAL PARTIAL COMPLETE
36. PAYMENT 35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT 41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
N0002418R2209
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
CLIN
Number
1 Each
65 Ft Dive Support Boat
FFP
The production and outfitting of a nominally 65 Ft x 22 Ft Dive Support Boat in accordance with requirements Specification. To include Initial Spares, Crew
Familiarization at Destination for up to (10) for a minimum (2) full days, and warranty.
FOB: Destination
PURCHASE REQUEST NUMBER: N0002418NR53091
PSC CD: 1940
NET AMT
Delivery
FFP
Delivery to Everett Naval Station.
FOB: Destination
PURCHASE REQUEST NUMBER: N0002418NR53091
OPTION Provisioned Items Orders (PIO)
FFP
The contractor shall provide spares and items ordered in accordance with Section C
CLAUSES INCORPORATED BY FULL TEXT
HQ B-2-0004 EXPEDITING CONTRACT CLOSEOUT (NAVSEA) (DEC 1995)
(a) As part of the negotiated fixed price or total estimated amount of this contact, both the Government and the
Contractor have agreed to waive any entitlement that otherwise might accrue to either party in any residual dollar amount of $500 or less at the time of final contract closeout. The term “residual dollar amount” shall include all money that would otherwise be owed to either party at the end of the contract, except that, amounts connected in any way with taxation, allegations of fraud and/or antitrust violations shall be excluded. For purposes of determining residual dollar amounts, offsets of money owed by one party against money that would otherwise be paid by that party may be considered to the extent permitted by law.
(b) This agreement to waive entitlement to residual dollar amounts has been considered by both parties. It is agreed that the administrative costs for either party associated with collecting such small dollar amounts could exceed the amount to be recovered.
HQ B-2-0017 REFUNDS (SPARES AND SUPPORT EQUIPMENT) (NAVSEA) (SEP 1990)
(a) In the event that the price of a spare part or item of support equipment delivered under this contract significantly exceeds its intrinsic value, the Contractor agrees to refund the difference. Refunds will only be made for the difference between the intrinsic value of the item at the time an agreement on price was reached and the contract price. Refunds will not be made to recoup the amount of cost decreases that occur over time due to productivity gains (beyond economic purchase quantity considerations) or changes in market conditions.
(b) For purposes of this requirement, the intrinsic value of an item is defined as follows:
(1) If the item is one which is sold or is substantially similar or functionally equivalent to one that is sold in substantial quantities to the general public, intrinsic value is the established catalog or market price, plus the value of any unique requirements, including delivery terms, inspection, packaging, or labeling.
(2) If there is no comparable item sold in substantial quantities to the general public, intrinsic value is defined as the price an individual would expect to pay for the item based upon an economic purchase quantity as defined in
FAR 52.207-4, plus the value of any unique requirements, including delivery terms, inspection, packaging or labeling.
(c) At any time up to two years after delivery of a spare part or item of support equipment, the Contracting Officer may notify the Contractor that based on all information available at the time of the notice, the price of the part or item apparently exceeds its intrinsic value.
(d) If notified in accordance with paragraph (c) above, the Contractor agrees to enter into good faith negotiations with the Government to determine if, and in what amount, the Government is entitled to a refund.
(e) If agreement pursuant to paragraph (d) above cannot be reached, and the Navy's return of the new or unused item to the Contractor is practical, the Navy, subject to the Contractor's agreement, may elect to return the item to the Contractor. Upon return of the item to its original point of Government acceptance, the Contractor shall refund in full the price paid. If no agreement pursuant to paragraph (d) above is reached, and return of the item by the Navy is impractical, the Contracting Officer may, with the approval of the Head of the Contracting Activity, issue a
Contracting Officer's final decision on the matter, subject to Contractor appeal as provided in the "DISPUTES" clause (FAR 52.233-1).
(f) The Contractor will make refunds, as required under this requirement, in accordance with instructions from the
Contracting Officer.
(g) The Contractor shall not be liable for a refund if the Contractor advised the Contracting Officer in a timely manner that the price it would propose for a spare part or item of support equipment exceeded its intrinsic value, and with such advice, specified the estimated proposed price, the estimated intrinsic value and known alternative sources or item, if any, that can meet the requirement.
(h) This requirement does not apply to any spare parts or items of support equipment whose price is determined through adequate price competition. This requirement also does not apply to any spare part or item of support equipment with a unit price in excess of $100,000; or in excess of $25,000 if the Contractor submitted, and certified the currency, accuracy and completeness of, cost or pricing data applicable to the item.
HQ B-2-0022 CONTRACT SUMMARY FOR PAYMENT OFFICE (FIXED PRICE) (FEB 1997)
This entire contract is fixed price.
NOTES
Applicable to CLIN 0003: It is understood and agreed that the Government has no obligation under this contract to issue any orders hereunder. Orders will be placed in accordance with the terms and conditions of Section C “C-217-H003
Provisioned Items Orders – Alternate II”. Funding will be provided with each order that is placed.
Section C - Descriptions and Specifications
SECTION C
Introduction
1.1 Scope
This Statement of Work (SOW) is for a procurement of a 65’Dive Support Boat for use supporting dive operations at Puget Sound Naval Shipyard, Bremerton, WA. The boat is desired to provide enhanced performance of current capabilities. The Custodian has one 65’ Dive Support Boat, equipped with a crane. The existing boat is in high demand and a second, similar boat is needed to meet mission requirements. The contractor will be responsible for following their standardized manufacturing processes to procure, develop, test, and deliver final end items to the
Government. This SOW outlines the specific responsibilities and deliverables of this contract.
2.0 Requirements
2.1 Program Management
Roles and Responsibilities
(a) The Contractor shall establish a project management structure that ensures overall quality of the boat components, consistent with their selected engineering and manufacturing approach.
(b) The Contractor’s primary interface for contract performance and execution shall be with the Program Office, Support Ships, Boats and Craft (PMS 325) on all activities related to successful performance of the contract. An
Assistant Program Manager (APM) will be the Government representative to the Contractor for day-to-day operations.
(c) The Government’s Contracting Officer (KO) from NAVSEA 02 is the contract owner and the only person authorized to make changes to this contract on behalf of the Government and should be contacted with any requests for change or deviation in the contract.
(d) The Government Technical Point of Contact (TPOC) is the Naval Surface Warfare Center, Carderock Division
(NSWCCD), Combatant Craft Division (CCD), and should be contacted for questions related to technical implementation of boat design requirements.
Post-Award Conference (PAC)
The contractor shall schedule a PAC no-later than thirty (30) calendar days after award of contract. The PAC shall be held at the Contractor’s facility, or an alternate facility approved by the Government and shall be attended by a
Government representative(s). Topics will include, but are not limited to, documentation review, the Contractor’s understanding of the technical requirements, and production/delivery schedule.
Design Maturity Review
The Contractor shall schedule and host Government personnel for a Design Maturity Review prior to construction.
The purpose of the Design Maturity Review is to demonstrate that the design is sufficiently mature to start construction and that the status of material ordering and delivery will support the proposed build schedule. Any potential risk areas shall be identified and mitigation plans discussed. The Government should be satisfied that all requirements in the 65 DS Specification (Attachment 1) have been incorporated into the design. The Government will notify the Contractor within seven (7) days of the Design Maturity Review whether or not the start of construction is authorized. The following shall be provided for the Design Maturity Review:
1. Updated Design, Production, and Delivery Schedule,
2. Material and purchased parts status, including but not limited to:
a. hull and deck materials,
b. major equipment,
c. long lead time items.
3. Preliminary construction drawings, including but not limited to:
a. Arrangement Drawings (e.g. general arrangements, inboard and outboard arrangements, console arrangement, etc.)
b. Structural drawings (e.g. structural arrangements, hull and bulkhead penetrations, etc.),
c. Notional Functional Schematics (e.g. steering hydraulics and controls, crane hydraulics and controls, HVAC arrangement and ducting, auxiliary seawater systems, electrical one-line diagram,
4. Updated weight estimate and stability analysis,
5. Structural analyses (reviewed and approved by Government TPOC),
6. Weld schedule and Quality Assurance (QA) process,
7. Other preliminary analyses (e.g. updated EPLA, voltage drop, HVAC, etc.),
8. Preliminary test plan(s),
9. Construction facilities: the Contractor shall provide evidence of the facilities readiness,
10. Production Manning: The Contractor shall provide evidence that manning resources are available to support planned production,
11. Requests For Variance (RFV): There shall be no open RFVs. Contract Problem Identification Reports
(CPIRs) shall have a documented resolution.
12. Risk Assessment: an assessment of risk and the risk management approach to eliminate or mitigate those risks.
Additional Progress Reviews
Other progress reviews or meetings shall be held, as requested by the Contractor, to support the production schedule including (but not limited to) progress reviews and engineering reviews. The meetings shall be held at the
Contractor’s facility, an alternate facility approved by the Government, or by phone depending upon the technical complexity and/or schedule and shall be attended by a Government representative(s).
2.2 Technical Data
The Contractor shall refer to Attachment 1 Specification Item 085(Technical Data Package (TDP)), for identification and criteria for data required for delivery under this Contract. The Contractor shall contact the Government with any questions of scope or content required to meet data needs.
Rights in Technical Data
It is the Government's desire that all non-commercial Technical Data (TD) be included in the TDP
(baseline or as modified by any Engineering Change Proposals (ECPs)) be delivered with a minimum of
Government Purpose Rights (GPR)(as defined in DFARS 252.227-7013 and -7014). If the Offeror proposes to deliver commercial TD, it is the Government’s desire to obtain a license to the commercial TD that would grant the
Government the equivalent of Government Purpose Rights as a minimum. All TDP deliverables shall be marked with appropriate data rights legends per DFARS 252.227-7013 and -7014 as applicable.
The Contractor shall submit Data Rights Attachments (Attachment 10: Technical Data Rights Assertions (Non-
Commercial) and Attachment 11: Technical Data Rights Assertions (Commercial)).
2.3 Production
Pre-Delivery Inspection and Trials (PDIT)
The Contractor shall perform Pre-Delivery Inspection and Trials (PDIT) for the boat delivered under
CLIN 001. Description of PDIT is provided under Attachment 1, Item No. 094-2. The Contractor must notify the
Government in writing of any delay in PDIT prior to the Government’s planned arrival for PDIT. Such notification shall include a request for extension to perform PDIT. If, upon the Government’s arrival for PDIT, the
Government and the Contractor are unable to satisfactorily perform PDITs outlined in Attachment 1 Item No. 094-2, the Contractor may be held financially responsible for cost reimbursement of Government and/or Government representative's travel and labor associated with PDITs. If the Contractor cannot meet the delivery order delivery date, as a result of PDIT delay or other delays resulting from PDIT delay, the Contractor may also be held responsible for providing consideration for late delivery.
Unique Item Identification (UID)
Item(s) delivered shall comply with the Unique Item Identification (UID) requirements detailed in the UID Clause attached hereto as Attachment 5 and in compliance with DFARs 252.211-7003, Item Unique Identification and
Valuation (Mar 2016). Pricing is to be included in Attachment 1, Item No. 813.
Delivery
Packaging and delivery of all items in the Contract shall adhere to the requirements in Section D and Section F.
Warranty
The Contractor shall provide a Builder's Warranty for the boat and all installed equipment per Attachment 8.
Crew Familiarization
The Contractor shall provide a minimum of two full days of crew familiarization training for up to ten (10)
Government/Contractor user personnel at the delivery destination. Scope should include familiarization on boat and main equipment operations and on-board maintenance and at least 4 hours of underway time.
Initial Spares
The Contractor shall identify recommended initial spares using Attachment 13. The Contractor shall supply initial spares with the boat upon Government approval of the recommended spares.
Engineering Changes/Requests for Variance
Upon discovery, the Contractor shall notify the Government of any issue with obsolete components that impacts system performance or production schedule. Routine one-for-one replacements shall be documented in a Request for Variance, DD1694. A complex change that impacts the contract baseline shall be documented in an ECP.
The Contractor shall submit an ECP for any proposed configuration change to the contract specification and drawings baseline. Such changes shall be in accordance with DD1693 format and should only be submitted to resolve design or configuration issues.
CONTRACT LINE ITEM DESCRIPTION
CLIN 0001: 65’ Dive Support Boat – Quantity One (1) –The production and outfitting of a nominally 65 Ft x 22 Ft
Dive Support Boat in accordance with requirements Specification. To include Initial Spares, Crew Familiarization at
Destination for up to (10) ten for a minimum (2) two full days, and warranty.
CLIN 0002: Delivery – Quantity One (1) - The Contractor shall deliver the 65’ Dive Support Boat to the location as defined in Section F of the contract.
Item 0003: Provisioned Items Order Spares (Option): The contractor shall provide spares and repair parts, special tools, test equipment, materials and related support not envisioned at time of award in accordance with Section C.
C-222-H001 DEPARTMENT OF LABOR SAFETY AND HEALTH STANDARDS FOR SHIPBUILDING
(NAVSEA) (APR 2018)
Attention of the Contractor is directed to Public Law 91 596, approved December 29, 1970 (84 Stat. 1590, 29 USC
655) known as the "OCCUPATIONAL SAFETY AND HEALTH ACT OF 1970" and to the "OCCUPATIONAL
SAFETY AND HEALTH STANDARDS FOR SHIPYARD EMPLOYMENT" promulgated thereunder by the
Secretary of Labor (29 CFR. 1910 and 1915). These regulations apply to all shipbuilding and related work, as defined in the regulations. Nothing contained in this contract shall be construed as relieving the Contractor from any obligations which it may have for compliance with the aforesaid regulations.
ITEM(S) 0039 C-217-H003 PROVISIONED ITEMS ORDERS--ALTERNATE II (NAVSEA) (APR 2018)
(a) General. The Contractor agrees that it will furnish the supplies or services ordered by the Government in accordance with the procedures specified herein. Orders may be placed by the Contracting Officer, Provisioning
Activity or Administrative Contracting Officer as unilateral or bilateral modifications to this contract on SF 30, Amendment of Solicitation/Modification of Contract. Any amounts shown in Section B at time of award of the initial contract for each provisioned line item are estimated amounts only and are subject to upward or downward adjustment by the issuing activity. If no amounts are shown, funding will be obligated before or at time of order issuance. It is understood and agreed that the Government has no obligation under this contract to issue any orders hereunder.
(b) Priced Orders. For each proposed order, the Contractor agrees that it will submit such cost or pricing data as the
Contracting Officer may require. Promptly thereafter, the Contractor and the Contracting Officer shall negotiate the price and delivery schedule for the proposed order. Upon execution and receipt of the priced order, the Contractor shall promptly commence the work specified in the order.
(c) Undefinitized Orders. Whenever the Contracting Officer determines that urgent demands or requirements prevent the issuance of a priced order, he/she may issue an unpriced order. Such order may be unilateral or bilateral and shall establish a limitation on Government liability, a maximum ceiling amount, and a schedule for definitization, as described in subparagraph (e)(2) below. Upon request the Contractor shall submit a maximum ceiling amount proposal before the undefinitized order is issued. The maximum ceiling amount is the maximum price at which the order may be definitized. The Contractor shall begin performing the undefinitized order upon receipt, except as provided in paragraph (d) below. The clause entitled "Contract Definitization" (DFARS 252.2l7-
7027) shall be included in any undefinitized order.
(d) Unilateral Undefinitized Orders. (1) For a unilateral undefinitized order, the Contractor shall within ten calendar days of receipt of the order notify the Contracting Officer in writing if it takes exception to the ceiling amount and/or the delivery schedule and shall propose a revised ceiling amount and/or a revised delivery schedule at that time. For unilateral undefinitized orders to which the Contractor takes no exception, the Contractor is obligated to perform just as if it were a fully definitized order.
(2) After receipt of the Contractor's Proposal to establish the revised ceiling amount and/or the revised delivery schedule, the Contracting Officer shall: (1) adjust the ceiling amount and/or revise the delivery schedule; (2) advise the Contractor that the order will be adjusted in a different amount than proposed by the Contractor; or (3) advise the
Contractor that no adjustment will be made. In the event the Contractor has taken exception to the ceiling amount and/or the delivery schedule and has submitted a timely proposal in accordance with the preceding requirement and the Contracting Officer has not accepted the Contractor's proposal, the Contractor shall not be obligated to perform the order beyond the point at which it would be entitled to be compensated in an amount in excess of the
Government's limitation of liability contained in the unilateral order.
(e) Definitization of Undefinitized Orders. (l) The Contractor agrees that following the issuance of an undefinitized order, it will promptly begin negotiating with the Contracting Officer the price and terms of a definitive order that will include: (A) all clauses required by regulation on the date of the order; (B) all clauses required by law on the date of execution of the definitive order; and, (C) any other mutually agreeable clauses, terms and conditions. No later than sixty (60) days after the undefinitized order is issued, the contractor agrees to submit a cost proposal with sufficient data to support the accuracy and derivation of its price; and, when required by FAR, cost or pricing data. If additional cost information is available prior to the conclusion of negotiations, the Contractor shall provide that information to the Contracting Officer. The price agreed upon shall be set forth in a bilateral modification to the order. In no event shall the price exceed the maximum ceiling amount specified in the undefinitized order.
(2) Each undefinitized order shall contain a schedule for definitization which shall include a target date for definitization and dates for submission of a qualifying proposal, beginning of negotiations and, if appropriate, submission of make-or-buy and subcontracting plans and cost or pricing data. Submission of a qualifying proposal in accordance with the definitization schedule is a material element of the order. The schedule shall provide for definitization of the order by the earlier of:
(i) a specified target date which is not more than l80 days after the issuance of the undefinitized order. However, that target date may be extended by the Contracting Officer for up to l80 days after the Contractor submits a qualifying proposal as defined in DFARS 2l7.740l; or
(ii) the date on which the amount of funds obligated by the Government under the undefinitized order exceed fifty percent (50%) of the order's maximum ceiling amount, except as provided in subparagraph (f)(3) below.
(3) If agreement on a definitive order is not reached within the time provided pursuant to subparagraph (e)(2) above, the Contracting Officer may, with the approval of the Head of the Contracting Activity, determine a reasonable price in accordance with Subpart l5.4 and Part 3l of the FAR, and issue a unilateral order subject to
Contractor appeal as provided in the "Disputes" clause (FAR 52.233-1). In any event, the Contractor shall proceed with completion of the order, subject to the "Limitation of Government Liability" clause (FAR 52.216-24).
(f) Limitation of Government Liability. (l) Each undefinitized order shall set forth the limitation of Government liability, which shall be the maximum amount that the Government will be obligated to pay the Contractor for performance of the order until the order is definitized. The Contractor is not authorized to make expenditures or incur obligations exceeding the limitation of Government liability set forth in the order. If such expenditures are made, or if such obligations are incurred, they will be at the Contractor's sole risk and expense. Further, the limitation of liability shall be the maximum Government liability if the order is terminated. The "Limitation of
Government Liability" clause shall be included in any undefinitized order.
(2) Except for undefinitized orders for Foreign Military Sales; purchases of less than $25,000; special access programs; and Congressionally-mandated long-lead procurements; and except as otherwise provided in subparagraph (f)(3) below, the limitation of Government liability shall not exceed fifty percent (50%) of the ceiling amount of an undefinitized order. In the case of orders within these excepted categories, however, the procedures set forth herein shall be followed to the maximum extent practical.
(3) If the Contractor submits a qualifying proposal (as defined in DFARS 2l7.740l) to definitize an order before the Government has obligated fifty percent (50%) of the ceiling amount, the Contracting Officer may increase the limitation of Government liability to up to seventy-five percent (75%) of the maximum ceiling amount or up to seventy-five percent (75%) of the price proposed by the Contractor, whichever is less.
(4) If at any time the Contractor believes that its expenditure under an undefinitized order will exceed the limitation of Government liability, the Contractor shall so notify the Contracting Officer, in writing, and propose an appropriate increase in the limitation of Government liability of such order. Within thirty (30) days of such notice, the Contracting Officer will either (i) notify the Contractor in writing of such appropriate increase, or (ii) instruct the
Contractor how and to what extent the work shall be continued; provided, however, that in no event shall the
Contractor be obligated to proceed with work on an undefinitized order beyond the point where its costs incurred plus a reasonable profit thereon exceed the limitation of Government liability, and provided also that in no event shall the Government be obligated to pay the Contractor any amount in excess of the limitation of Government liability specified in any such order prior to establishment of firm prices.
(g) Initial Spares. The limitations set forth in paragraph (c) and subparagraphs (e)(2), (f)(2) and (f)(3) do not apply to undefinitized orders for the purchase of initial spares.
(h) Terminal Date for Placement of Orders. The Contractor shall not be obligated to accept any orders placed hereunder beyond the guaranty period set forth in the clause entitled "Guaranty Period" for the last article under the applicable item called for in Section B hereof for which the supplies or services are being acquired, provided, however, that deliveries or performance of such supplies or services shall be completed not later than the expiration of said guaranty period.
(i) Segregation of Costs. The Contractor shall segregate the costs of performance of each undefinitized order from the cost of performance of any other work performed by the Contractor.
(j) Ordering. The cognizant ordering activities are designated below:
NAVAL SEA SYSTEMS COMMAND
CLAUSES INCORPORATED BY REFERENCE
HQ C-2-0033 LIMITATION OF LIABILITY - HIGH VALUE ITEMS
(NAVSEA) (JUN 1992)
MAR 2003
HQ C-2-0004 ACCESS TO THE VESSEL(S) (NAVSEA) (SEP 2016)
Officers, employees and associates of other prime Contractors with the Government and their subcontractors, shall, as authorized by the Supervisor, have, at all reasonable times, admission to the plant, access to the vessel(s) where and as required, and be permitted, within the plant and on the vessel(s) required, to perform and fulfill their respective obligations to the Government. The Contractor shall make reasonable arrangements with the Government or Contractors of the Government, as shall have been identified and authorized by the Supervisor to be given admission to the plant and access to the vessel(s) for office space, work areas, storage or shop areas, or other facilities and services, necessary for the performance of the respective responsibilities involved, and reasonable to their performance.
HQ C-2-0012 CONFIGURATION MANAGEMENT (NAVSEA) (APR 2015)
(a) Baseline Definition - For configuration control purposes, all contractual documentation in effect at the time of contract award shall constitute the Contract Baseline which shall be considered incorporated in the baseline documentation.
(b) General Requirement - (1) The Contractor shall maintain a Configuration Control Program to assure that all detail level work being performed under this contract is in compliance with appropriate baseline documentation.
The Contractor shall prepare a Configuration Management Plan in accordance with the requirements of the contract for approval by the Government.
(2) Whenever a situation arises wherein the Contractor cannot comply with a baseline document, or whenever intent of such documentation is significantly changed by detail level documentation, the Contractor shall submit change documents to modify baseline documents to resolve the conflict or to allow non-compliance.
Whenever the cost of implementing a proposed change is less than the threshold requiring certified cost or pricing data, the Contractor shall provide documentation explaining the nature of related costs as shown on the change document. Whenever the contract cost changes by an amount greater than the threshold requiring certified cost or pricing data, the Contractor shall complete such cost and pricing data as the Contracting Officer shall require detailing all related costs, and attach it to the change document. Requirements for cost and pricing data shall be determined by the gross amount of the change unless otherwise directed by the contracting officer. Change documentation shall be submitted to the Contracting Officer in accordance with the Contract Data Requirements List
(CDRL), and as described in paragraphs (c) through (f) below.
(c) Engineering Change Proposals (ECPs) - ECPs shall be prepared in accordance with the approved configuration management plan and the requirements of the contract. DI-SESS-80639D approved 7 April 2015 and MIL-HDBK-
61A of 7 Feb 2001 apply. An ECP should be submitted whenever the detail level physical configuration, material quality, operational or functional performance of equipment or installed systems will not be in compliance with baseline design-related documents (Specifications, Contract Drawings, etc.), and a change to the baseline document is considered an appropriate means of resolving a design-related issue. Documentation shall be developed in sufficient detail to enable Government review and evaluation of the merits of the proposed change, including cost and scheduling impact, ship class impact, and consequences if disapproved. All existing drawings and technical manuals impacted by the change shall be listed along with a brief narrative explanation of needed changes to incorporate the ECP if approved. Weight and moment data incidental to the change shall be provided. The
Contractor shall also prepare applicable baseline document insert sheets, with specific word changes or proposed re-write, to facilitate baseline documentation changes.
(d) Non-Engineering Change Proposals (NECPs) – An NECP should be submitted whenever necessary to document administrative, procedural, scheduling, or documentation changes that do not directly impact the physical configuration of the equipment. The NECP shall explain the nature of the problem, identify the applicable baseline document (i.e., Contract Data Requirement List (CDRL), Contract Clause, etc.) and provide a detailed explanation justifying the proposed course of action desired to resolve the problem. Insert sheets for applicable documents shall also be attached to facilitate change action in the event the NECP is approved.
(e) Deviations and Waivers - In the event that a baseline design-related document requirement cannot be met, and a change to the baseline document is considered inappropriate, the Contractor shall submit a Request for Variance.
DI-SESS-80640D approved 7 April 2015 and MIL-HDBK-61A of 7 Feb 2001 apply. The explanation of "need for deviation" should provide detailed justification and consequences of approval, to include technical details explaining the degree of non-compliance or effect on ship equipment or system operation constraints. In a similar manner, a waiver shall document an "as built" configuration that departs from baseline documentation and should include any proposed corrections or modifications to better meet the intent of the baseline document.
(f) Equitable Adjustments for Change Documentation Preparations - For its effort expended in preparing ECPs, NECPs, Deviations and Waivers, the Contractor shall receive equitable adjustment under the following circumstances:
(1) In the event the Contractor, on its own initiative, and without written request from the Contracting
Officer, develops a change document that is later disapproved by the Government, the Contractor shall bear the cost of this effort.
(2) To avoid such loss, and at its option, the Contractor may submit a "preliminary" document that outlines intent, but without detailed supporting documentation and request the Contracting Officer's approval for expenditure of effort to complete the detailed supporting documentation. In the event the Contracting Officer denies this request, the Contractor will bear the cost of development of the "preliminary" document, and shall make no further effort to complete detailed supporting documentation.
(3) In the event the Contracting Officer approves the Contractor's request to develop supporting documentation, the Contractor shall be equitably compensated for its effort for both the "preliminary" and "final" documentation, regardless of whether or not the change document is later approved.
(4) In the event the Contracting Officer requests in writing that the Contractor develop change documentation, the effort expended by the Contractor in developing such documentation shall be subject to equitable adjustment, regardless of whether or not the change document is later approved.
(5) In the event the Contractor, on its own initiative, and without written request from the Government, develops a change document that is later approved by the Contracting Officer, the cost of developing such documentation shall be incorporated in the contract modification that implements the change.
(6) Failure to agree to such equitable adjustment in contract price shall constitute a dispute, and shall be adjudicated in accordance with the requirements of the clause entitled "DISPUTES" (FAR 52.233-1).
(g) Any cost reduction proposal submitted pursuant to the clause entitled "VALUE ENGINEERING" (FAR
52.248-1) shall be submitted as a Code V Engineering Change Proposal (VECP). DI-SESS-80639D approved 7
April 2015 and MIL-HDBK-61A of 7 Feb 2001 apply. Information required by the "VALUE ENGINEERING" clause shall also be submitted as part of the change request.
HQ C-2-0013 CONTRACTOR PROBLEM IDENTIFICATION REPORTS (NAVSEA) (MAY 1993)
(a) Contract Problem Identification Reports (CPIRs) shall be used by the Contractor for the purpose of alerting the
Government to actual or potential contract problems and of establishing an early dialogue between the Contractor and the Government with regard thereto.
(b) A "contract problem" is a fact or circumstance of which the Contractor is aware that does, will or reasonably is anticipated to (1) have a significant or substantial impact on the delivery schedule or completion of contract performance or the cost of performance of the contract (increase or decrease) or (2) requires modification to the contract or specification(s). The terms "significant" and "substantial" shall be interpreted in the same manner as they would be interpreted by a reasonably prudent business person under the relevant circumstances.
(c) The Contractor shall report each contract problem promptly and in no event later than ten (10) calendar days, after the Contractor identifies such contract problem. A written CPIR shall be transmitted via the Administrating
Contracting Officer (ACO) to the Procuring Contracting Officer and to the cognizant technical code. Each CPIR shall be entitled "Contract Problem Identification Report", shall be dated, numbered sequentially and shall set forth the following based on the best and most complete information then known or available to the Contractor:
(1) The nature of the contract problem;
(2) The date on which the contract problem arose and the date on which the contract problem was identified as such;
(3) The anticipated direct and consequential effects of the contract problem upon the delivery schedule or completion of contract performance or the cost of performance of the contract;
(4) Identification of the supplies and/or services which are or may be affected; and
(5) The Contractor's recommended solution to the reported contract problem.
(d) Follow up status reports of each contract problem, identified by the original CPIR number, shall be furnished monthly or more frequently as required by the Contracting Officer. A final follow up report shall be furnished immediately following resolution of each contract problem.
(e) CPIRs shall not be submitted when notice of the same contract problem is required to be furnished to the
Government pursuant to any other requirement of this contract. The submission of a CPIR, however, does not relieve the Contractor of its obligations to provide notice required under any other requirement of this contract.
HQ C-2-0014 CONTRACTOR'S PROPOSAL (NAVSEA) (MAR 2001)
a) Performance of this contract by the Contractor shall be conducted and performed in accordance with detailed obligations to which the Contractor committed itself in Proposal * dated * in response to NAVSEA Solicitation No.
N00024-18-R-2209.
(b) Certain parts of the technical volume(s) of the Contractor's proposal are incorporated in this contract and hereby made subject to the provisions of the "ORDER OF PRECEDENCE" (FAR 52.215-8) clause of this contract. Under the "ORDER OF PRECEDENCE" clause, those parts of the technical volume referenced have been incorporated into the attachments listed in Section J and is hereby designated as item (f) of the clause, following "the specification" in the order of precedence.
HQ C-2-0023 EXCLUSION OF MERCURY (NAVSEA) (MAY 1998)
Mercury or mercury containing compounds shall not be intentionally added or come in direct contact with hardware or supplies furnished under this contract.
HQ C-2-0030 INFORMATION AND DATA FURNISHED BY THE GOVERNMENT (FIXED-PRICE) (NAVSEA)
(SEP 2009)
(a) Contract Specifications. The Government will furnish, if not included as an attachment to the contract, any unique contract specifications set forth in Section C.
(b) Contract Drawings and Data. The Government will furnish contract drawings, design agent drawings, ship construction drawings, and/or other design or alteration data cited or referenced in Section C or in the contract specification as mandatory for use or for contract performance.
(c) Government Furnished Information (GFI). GFI is defined as that information essential for the installation, test, operation, and interface support of all Government Furnished Material enumerated on NAVSEA Form 4205/19 or
Schedule A, as applicable, attached to the contract. The Government shall furnish only the GFI identified on the
NAVSEA Form 4340/2 or Schedule C, as applicable, attached to the contract. The GFI furnished to the contractor need not be in any particular format. Further, the Government reserves the right to revise the listing of GFI on the
NAVSEA Form 4340/2 or Schedule C, as applicable, as follows:
(1) The Contracting Officer may at any time by written order:
(i) delete, supersede, or revise, in whole or in part, data listed or specifically referenced in NAVSEA
Form 4340/2 or Schedule C, as applicable; or
(ii) add items of data or information to NAVSEA Form 4340/2 or Schedule C, as applicable; or
(iii) establish or revise due dates for items of data or information in NAVSEA Form 4340/2 or Schedule
C, as applicable.
(2) If any action taken by the Contracting Officer pursuant to subparagraph (1) immediately above causes an increase or decrease in the costs of, or the time required for, performance of any part of the work under this contract, the contractor may be entitled to an equitable adjustment in the contract price and delivery schedule in accordance with the procedures provided for in the clause of this contract entitled "CHANGES--FIXED-PRICE"
(FAR 52.243-1).
(d) Except for the Government information and data specified by paragraphs (a), (b), and (c) above, the
Government will not be obligated to furnish the Contractor any specification, standard, drawing, technical documentation, or other publication, notwithstanding anything to the contrary in the contract specifications, the GFI listed on the NAVSEA Form 4340/2 or Schedule C, as applicable, the clause of this contract entitled
"GOVERNMENT PROPERTY" (FAR 52.245-1) or "GOVERNMENT PROPERTY INSTALLATION
OPERATION SERVICES " (FAR 52.245-2), as applicable, or any other term or condition of this contract.
(e) Referenced Documentation. The Government will not be obligated to furnish Government specifications and standards, including Navy standard and type drawings and other technical documentation, which are referenced directly or indirectly in the contract specifications set forth in Section C and which are applicable to this contract as specifications. Such referenced documentation may be obtained:
(1) From the ASSIST database via the internet at http://assist.dla.mil/
; or
(2) By submitting a request to the
Department of Defense Single Stock Point (DoDSSP)
Building 4, Section D
700 Robbins Avenue
Philadelphia, Pennsylvania 19111-5094
Telephone (215) 697-6396
Facsimile (215) 697-9398.
Commercial specifications and standards, which may be referenced in the contract specification or any sub-tier specification or standard, are not available from Government sources and should be obtained from the publishers.
HQ C-2-0043 PROTECTION OF THE SHIP DURING ADVERSE ENVIRONMENTAL CONDITIONS
(NAVSEA) (FEB 1994)
The Contractor shall ensure that the ship(s) and all related material at the Contractor's facilities are protected during conditions of heavy weather, high winds, heavy snow and icing, high water or similar adverse environmental conditions. The Contractor shall develop, maintain, and implement as necessary an "Adverse Environmental
Conditions Plan" which prescribes the actions and procedures and assigns responsibilities for action to be taken in preparation for and during the period of adverse environmental conditions. The Contractor shall furnish the plan to the Supervisor and shall make such changes in the plan as the Supervisor considers necessary to provide for adequate protection of the ship(s) and the materials and equipment to be installed therein.
HQ C-2-0044 PROTECTION OF THE VESSEL (NAVSEA) (SEP 1990)
(a) The Contractor shall exercise reasonable care, as agreed upon with the Supervisor, to protect the vessel from fire, and shall maintain a system of inspection over the activities of its welders, burners, riveters, painters, pipe fitters, and similar workers, and of its subcontractors, particularly where such activities are undertaken in the vicinity of the vessel's magazines, fuel oil tanks, or store rooms containing inflammable materials. All ammunition, fuel oil, motor fuels, and cleaning fluids shall have been off-loaded and the tanks cleaned, except as may be mutually agreed upon between the Contractor and the Supervisor prior to work on the vessel by the Contractor. Fire hose lines shall be maintained by the Contractor ready for immediate use on the vessel at all times while the vessel is berthed alongside the Contractor's pier or in dry dock. All tanks under alteration or repair shall be cleaned, washed, and steamed out or otherwise made safe to the extent necessary, and the Contractor shall furnish the vessel's Gas Free
Officer and the Supervisor with a "Gas Chemists' Certificate" before any hot work is done. The Contractor shall maintain a fire watch aboard the vessel in areas where the Contractor is working. All other fire watches aboard the vessel shall be the responsibility of the Government.
(b) Except as otherwise provided in contractually invoked technical specifications or NAVSEA furnished directives, while the vessel is at the Contractor's plant and when the temperature becomes as low as thirty-five degrees Fahrenheit, the Contractor shall assist the Government when requested in keeping all pipe-lines, fixtures, traps, tanks, and other receptacles on the vessel drained to avoid damage from freezing, or if this is not practicable, the vessel shall be kept heated to prevent such damage. The vessel's stern tube and propeller hubs shall be protected by the Contractor from frost damage by applied heat through the use of a salamander or other proper means.
(c) The work shall, whenever practicable, be performed in such manner as not to interfere with the work performed by military personnel attached to the vessel, and provisions shall be made so that personnel assigned shall have access to the vessel at all times, it being understood that such personnel will not unduly interfere with the work of the Contractor's workmen.
(d) The Contractor shall at all times keep the site of the work on the vessel free from accumulation of waste material or rubbish caused by its employees, or the work performed by the Contractor in accordance with this contract, and at the completion of such work shall remove all rubbish from and about the site of the work, and shall leave the work in its immediate vicinity "broom clean", unless more exactly specified by the Supervisor.
HQ C-2-0063 USE OF NAVY SUPPORT CONTRACTORS FOR OFFICIAL CONTRACT FILES (NAVSEA)
(APR 2004)
(a) NAVSEA may use a file room management support contractor, hereinafter referred to as "the support contractor", to manage its file room, in which all official contract files, including the official file supporting this procurement, are retained. These official files may contain information that is considered a trade secret, proprietary, business sensitive or otherwise protected pursuant to law or regulation, hereinafter referred to as “protected information”. File room management services consist of any of the following: secretarial or clerical support; data entry; document reproduction, scanning, imaging, or destruction; operation, management, or maintenance of paper-based or electronic mail rooms, file rooms, or libraries; and supervision in connection with functions listed herein.
(b) The cognizant Contracting Officer will ensure that any NAVSEA contract under which these file room management services are acquired will contain a requirement that:
(1) The support contractor not disclose any information;
(2) Individual employees are to be instructed by the support contractor regarding the sensitivity of the official contract files;
(3) The support contractor performing these services be barred from providing any other supplies and/or services, or competing to do so, to NAVSEA for the period of performance of its contract and for an additional three years thereafter unless otherwise provided by law or regulation; and,
(4) In addition to any other rights the contractor may have, it is a third party beneficiary who has the right of direct action against the support contractor, or any person to whom the support contractor has released or disclosed protected information, for the unauthorized duplication, release, or disclosure of such protected information.
(c) Execution of this contract by the contractor is considered consent to NAVSEA's…