Work Breakdown Structure
WBS Production
1.0 AN/SLQ-32(V)6 ES Antenna and Receiver Production
1.1 AN/SLQ-32(V)6 ES Antenna and Receiver Products
1.1.1 AN/SLQ-32(V)6 ES Antenna and Receiver System
1.1.1.1 System Hardware
1.1.1.1.1 Below Deck Equipment
1.1.1.1.1.1 BDE Unit 1
1.1.1.1.1.2 BDE Unit 2
1.1.1.1.1.3 Below Deck Equipment, Other
1.1.1.1.2 Above Deck Equipment
1.1.1.1.2.1 Shelter Structure
1.1.1.1.2.2 ASEA
1.1.1.1.2.3 AAPA
1.1.1.1.2.4 Above Deck Equipment, Other
1.1.1.2 System Integration, Assembly, Test and Checkout
1.1.1.2.1 System Integration, Assembly, Test and Checkout - Touch Labor
1.1.1.2.2 System Integration, Assembly, Test and Checkout - Support Labor
1.1.1.3 Factory Acceptance Test
1.1.1.3.1 Factory Acceptance Test - Touch Labor
1.1.1.3.2 Factory Acceptance Test - Support Labor
1.2 Reserved
1.3 Systems Engineering
1.4 Program Management
1.5 System Test and Evaluation
1.6 Reserved
1.7 Data
1.8 Peculiar Support Equipment
1.9 Common Support Equipment
1.10 Reserved
1.11 Reserved
1.12 Reserved
2.0 Other
NOTE
- Include major sub-systems and/or sub-components at WBS 6th level
- Offerer shall utilize WBS numbering scheme to mamixum extent practical
WBS shall be the basis for cost reporting CDRLs.
31 March 2016
N00024-16-R-5363 ATTACHMENT J-S4
WBS Element WBS Element Name WBS Element Definition
1.0 AN/SLQ-32(V)6 ES Antenna and Receiver Production This WBS Element includes the AN/SLQ-32(V)6 ES Antenna and Reviever production.
1.1 AN/SLQ-32(V)6 ES Antenna and Receiver Products This WBS Element includes the AN/SLQ-32(V)6 Antenna and Receiver Prime Mission Product (PMP).
1.1.1 AN/SLQ-32(V)6 ES Antenna and Receiver System
This WBS Element includes the procurement of hardware, manufacturing labor and support, system integration labor and support, and factory acceptance test for the system.
1.1.1.1 System Hardware This WBS Element includes the procurement of all hardware for the system.
1.1.1.1.1 Below Deck Equipment This WBS Element includes the procurement of hardware for the Below Deck Equipment (BDE).
1.1.1.1.1.1 BDE Unit 1 This WBS Element includes the procurement of hardware for Below Deck Equipment Unit 1.
1.1.1.1.1.2 BDE Unit 2 This WBS Element includes the procurement of hardware for Below Deck Equipment Unit 2.
1.1.1.1.1.3 Below Deck Equipment, Other
This WBS Element includes the procurement of hardware for all the Below Deck Equipment that is not included in either Unit 1 or
Unit 2.
1.1.1.1.2 Above Deck Equipment This WBS Element includes the procurement of hardware for the Above Deck Equipment (ADE).
1.1.1.1.2.1 Shelter Structure This WBS Element includes the procurement of hardware for the Shelter Structure.
1.1.1.1.2.2 ASEA This WBS Element includes the procurement of hardware for the ASEA.
1.1.1.1.2.3 AAPA This WBS Element includes the procurement of hardware for the AAPA.
1.1.1.1.2.4 Above Deck Equipment, Other
This WBS Element includes the procurement of hardware for all the Above Deck Equipment that is not included in the Shelter
Structure, ASEA, or AAPA.
1.1.1.2 System Integration, Assembly, Test and Checkout
This WBS Element includes manufacturing labor and support for assembly and test of the system including activities associated with the final assembly of the system as performed by the contractor. This effort includes the planning, fabrication, and assembly of the equipment.
1.1.1.2.1 System Integration, Assembly, Test and Checkout - Touch Labor This WBS Element includes manufacturing labor for assembly and test of the system.
1.1.1.2.2 System Integration, Assembly, Test and Checkout - Support Labor This WBS Element includes manufacturing program management and manufacturing support for the system. Activities include overall assembly and test oversight and management, manufacturing financial support, and manufacturing master scheduling.
1.1.1.3 Factory Acceptance Test This WBS Element includes the Factory Acceptance Test and the leadership and management of the System Test & Integration Team.
1.1.1.3.1 Factory Acceptance Test - Touch Labor This WBS Element includes the factory Acceptance Test of the system.
1.1.1.3.2 Factory Acceptance Test - Support Labor
This WBS Element includes the Factory Acceptance Test leadership and management of the System Test & Integration Team.
Activities include the overall integration management support to ensure an integrated I&T program.
1.2 Reserved
1.3 Systems Engineering
This WBS Element refers to the technical and management efforts performed by the contractor of directing and controlling a totally integrated engineering effort of a system while in production. Example system engineering activities are management of system level requirements, system optimization, producibility, modeling and simulation, information assurance, safety, human health, environmental protection, and survivability, security requirements, configuration management and configuration control, quality assurance program, HSI, etc.
1.4 Program Management
This WBS Element refers to the business and administrative planning, organizing, directing, coordinating, controlling, and approval actions designated to accomplish overall program objectives. Example program management activities are cost, schedule, performance measurement management, financial planning & reporting, risk management, warranty administration, contract management, data management, vendor liaison, subcontract management, etc.
1.5 System Test and Evaluation
This WBS Element refers to all activities associated with the test and evaluation of the system performed by the contractor. This effort includes the planning, conduct, support, data reduction, and reporting of tests on pre-production, production, or specifically fabricated equipment.
1.6 Reserved
1.7 Data
This WBS Element refers to the deliverable data required to be listed on a Contract Data Requirements List (CDRL). Specific data materials include technical publications, engineering data, management data, and support data.
1.8 Peculiar Support Equipment
This WBS Element refers to the unique items required to support and maintain the system or portions of the system while not directly engaged in the performance of its mission. Examples of support equipment are support & handling equipment and testing & measurement equipment, which allows an operator or maintenance function to evaluate operational conditions of a system or equipment by performing specific diagnostics, screening or quality assurance effort at an organizational, intermediate, or depot level of equipment support.
Production
31 March 2016
WBS Element WBS Element Name WBS Element Definition
Production
1.9 Common Support Equipment
This WBS Element refers to the common items required to support and maintain the system or portions of the system while not directly engaged in the performance of its mission. Examples of support equipment are support & handling equipment and testing & measurement equipment, which allows an operator or maintenance function to evaluate operational conditions of a system or equipment by performing specific diagnostics, screening or quality assurance effort at an organizational, intermediate, or depot level of equipment support.
1.10 Reserved
1.11 Reserved
1.12 Reserved
2.0 Other
This WBS Element is reserved for contractor support elements not currently shown in the WBS structure. This WBS level can be expanded to include additional WBS elements (as necessary) to capture all other contractor support effort for the system.