ALMDS_PreRFP_Bidders'_Questions_and_Responses.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- Airborne Laser Mine Detection System
- Solicitation number
- N00024-13-R-6318
About this file
Bidders Pre-solicitation Questions and responses
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question Number | Document | Page and/or Section Reference | Potential Offeror Question | Government Response |
| 1 | Draft RFP | Section B | Is the bidder required to propose each option as a stand-alone build, with the quantity of pods and PSE as dictated at the time the option is exercised? Specifically, will each option require multiple prices (e.g., For one or two pods, one to five sets of PSE, etc.)? | The formal RFP released 24 October 2013 addresses this question. ALMDS systems and PSE line items require stepladder pricing for both the base period and all option periods. Please refer to Section B for all stepladder quantities and reference Note A. These quantities are also reflected in Table 1 of Section L, Section 5.1.2. |
| 2 | Draft RFP | Section B | With regard to "NOTE A," can the Government clarify the discrepancy between completing the "Price Group" and "Estimated Total Price" for each CDRL when CLIN 0004 is identified as Not Separately Priced (NSP)? | The formal RFP released 24 October 2013 addresses this question. Although CLIN 0004 is Not Separately Priced (NSP), the Offeror is required to complete the "Price Group" and "Estimated Total Price" blocks for each CDRL. Please reference Section B and Note D. |
| 3 | Draft RFP | Section B | Will the Pod Shipping Containers be provided as GFE? | The formal RFP released 24 October 2013 addresses this question. Please refer to SOW Section 3.15.3. |
| 4 | Draft RFP | Section B | What is the definition of Miscellaneous Material as identified under CLIN 0003? | The formal RFP released 24 October 2013 addresses this question. Miscellaneous Material is incidental material required while performing under a Technical Instruction (TI). Please reference Section B and Note C. |
| 5 | Draft RFP | Section B | For Option CLIN 0100 for Peculiar Support Equipment (PSE), is it the Government's intent to be able to exercise a quantity other than the total option quantity (i.e. five (5) sets of PSE)? | The formal RFP released 24 October 2013 addresses this question. All PSE line items are set up with stepladder pricing. If the Option is exercised, the Government reserves the right to purchase between one (1) and five (5) sets of PSE. Please reference Section B and all applicable notes. These quantities are also reflected in Table 1 of Section L, Section 5.1.2. |
| 6 | Draft SOW | Paragraph 2.1 | Is it the Government's intention to impose MIL-STD-461F rather than MIL-STD-416E on all equipment being proposed? | Theformal RFP released 24 October 2013 addresses this question. The formal SOW invokes MIL-STD-461F. Please refer to SOW Section 2.1. |
| 7 | Draft SOW | Paragraph 3.6 | Will the Government require a Far Field Test to be performed on each production unit? | The formal RFP released 24 October 2013 addresses this question. The Government requires a Far Field Test to be performed on each production unit. Please refer to SOW Section 3.6. |
| 8 | Draft SOW | Paragraph 3.7.1 | Will the previously qualified components of ALMDS require any additional qualification testing as s result of a contract award? | The formal RFP released 24 October 2013 addresses this question. The previously qualified components of ALMDS will not require any additional component testing. Please refer to SOW Section 3.7.1. |
| 9 | Draft SOW | Paragraph 3.8.2 | Does the Contractor need to update the GFI baseline TDP against the supplied DIDs as defined in draft SOW 3.8.2? | The formal RFP released 24 October 2013 addresses this question. The GFI baseline TDP shall be updated against the supplied DIDs. Please refer to SOW Section 3.8.2. |