Amendment 0004 to the Solicitation N00019-14-R-0025.

View the file

Other files

File Type Posted
N00019-14-R-0025-0005.docx DOCX document
Unit_Load_Construction_Guidelines_Under_Replenishment_of_M548_Containers....pdf PDF
USN_Shipping_and_Storage_Container _M548 _DWG_7258943.pdf PDF
N00019-14-R-0025-0003.docx DOCX document
N00019-14-R-0025-0002.docx DOCX document
N00019-14-R-0025_A0002.doc DOC document
N00019-14-R-0025-0001.docx DOCX document
N00019-14-R-0025.docx DOCX document
Attachment_L-2_T-1_SB_Goals.xlsx XLSX spreadsheet
Attachment_L-4_PP-1_PP_Cont_Data.xlsx XLSX spreadsheet
Attachment_L-1_ES_Tables.xlsx XLSX spreadsheet
Attachment_1-_SOW_dtd_21_Aug_14.docx DOCX document
Attachment_L-3_Vol_3_PPQ.docx DOCX document
N00019-14-R-0025_Section_LM_17Sep2014.docx DOCX document
N00019-14-R-0025_Section_BK_17Sep2014.doc DOC document
Copy_of_Sample_Attendee_Form.xlsx XLSX spreadsheet
FMU-139DB_SOW_06182014.docx DOCX document
Exhibits_AB_CDRLs_for_FMU-139DB_-_8_May_14_51214.docx DOCX document
Sample_Feedback_Form.xlsx XLSX spreadsheet
N00019-14-R-0025-DRAFT_RFP.doc DOC document
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N00019-14-R-0025

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION I - CONTRACT CLAUSES

The following included by reference have been revised:

52.222-50
Combating Trafficking in Persons
FEB 2009
52.244-6
Subcontracts for Commercial Items
OCT 2014

SECTION K - REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS

The following included by full text have been revised:

52.225-18PLACE OF MANUFACTURE (MAR 2015)
(a) Definitions. As used in this clause--
“Manufactured end product” means any end product in product and service codes (PSCs) 1000-9999, except--
(1) PSC 5510, Lumber and Related Basic Wood Materials;
(2) Product or Service Group (PSG) 87, Agricultural Supplies;
(3) PSG 88, Live Animals;
(4) PSG 89, Subsistence;
(5) PSC 9410, Crude Grades of Plant Materials;
(6) PSC 9430, Miscellaneous Crude Animal Products, Inedible;
(7) PSC 9440, Miscellaneous Crude Agricultural and Forestry Products;
(8) PSC 9610, Ores;
(9) PSC 9620, Minerals, Natural and Synthetic; and
(10) PSC 9630, Additive Metal Materials.
“Place of manufacture” means the place where an end product is assembled out of components, or otherwise made or processed from raw materials into the finished product that is to be provided to the Government. If a product is disassembled and reassembled, the place of reassembly is not the place of manufacture.
(b) For statistical purposes only, the offeror shall indicate whether the place of manufacture of the end products it expects to provide in response to this solicitation is predominantly--
(1) [ ] In the United States (Check this box if the total anticipated price of offered end products manufactured in the United States exceeds the total anticipated price of offered end products manufactured outside the United States); or
(2) [ ] Outside the United States.

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

The following have been modified:

QUESTIONS AND ANSWERS

Question Reference Number
Document Title Name
Document Page Number
Question
Response
R-001
N00019-14-R-0025
N/A
The performance specification calls out a FZU-62 lanyard. Can the drawing for this item be provided?
Yes, the drawing is available upon request.
R-002
N00019-14-R-0025
N/A
Pursuant to the referenced RFP and the FMU-139D/B SDICD, request to be provided a copy of the following document as referenced in the ICD:

JICD-MDA-001 Interface Control Document Joint Direct Attack Munition to Host Aircraft.

Although the FMU-139D/B SDICD references the JDAM ICD, JICD-MDA-001, the referenced document is not required to prepare a compliant proposal. The FMU-139D/B SDICD provided in the RFP contains sufficient definition of the weapon-to-fuze interface to permit all potential Offerors to scope the required effort.

R-003
N00019-14-R-0025
N/A
Block 4 on the SF33 is checked as "Negotiated (RFP)" and not "Sealed Bid (IFB)
This Solicitation is being procured under FAR Part 15-Contracting by Negotiation. Potential Offerors are directed to FAR part 15 for the processes.
R-004
N00019-14-R-0025
N/A
Please provide clarity or the intent of clause 5252.245-9506 Government Production and Research Property (page 71/100); FAR 45.301 (Use and Charges) does not provide the definitions as noted in the clause.
This clause was deleted.
R-005
N00019-14-R-0025
N/A
Clause 5252.222-9501 Identification of First-Tier Subcontractors for Pre-Award Clearance Purposes (page 70/100) states a $10,000,000 threshold. How is this threshold to be calculated? What years should it cover? What quantities should be used, the quantities identified in Section M for evaluation purposes, or something else?
How is this threshold to be calculated? Reference the contract maximum, F-3 Order Limitations

What years should it cover? Reference the contract maximum, F-3 Order Limitations What quantities should be used, the quantities identified in Section M for evaluation purposes, or something else? Quantities are dependent on Offeror's proposed price up to the contract maximum, F-3 Order Limitations.

R-006
N00019-14-R-0025
N/A
For the Small Business Subcontracting Plan, what award quantity should be used to calculate contract value and subcontract value?
See Section L, Part B - Specific Instructions, Volume 2 - Technical Proposal, subsection 2.7 Small Business Management.
R-007
N00019-14-R-0025
N/A
Is the FFCS used to initiate a thermal battery or is the initial pulsed energy required to be stored within the Electronic Safe and Arm Fuze (ESAF)?
Fuze Function Control Set (FFCS) serves as the standard communications protocol between the fuze host weapons and launch platforms, enabling vital in-flight fuze (arm and delay time) selectability capability that Fleet operators have relied on for decades. The FFCS provides the energy through the MK-122 switch in the weapon to operate the fuze for the mission.
R-008
N00019-14-R-0025
N/A
Requesting information and drawings with respect to the arm power cable assembly, mating connector and arm connector within the ESAF.

· 30003-7542966 Cable Assembly Fuze Control M72.

· 30003-7542967 Cable Assembly Fuze Control M73.

· 30003-7542968 Cable Assembly Fuze Control M74.

· 98747-9042203 Cable, Power

Yes, the drawing is available upon request.

R-009
N00019-14-R-0025
N/A
Requesting the FMU-139 C/B performance specification and the primary technical motivation for the FMU-139 D/B variant.
The FMU-139C/B Performance Specification (PS) is a stand-alone, independent document from the FMU-139D/B PS. As the two documents are not related, the FMU-139C/B PS will not be provided. The FMU-139D/B will enable cockpit programmability not currently available with the current FMU-139C/B fuze. Additional product improvements include a Serial Data Interface (SDI) between the aircraft and fuze, and increased hard target penetration capability. The FMU-139D/B provides the flexibility for use in both Mk-80 series weapons and the BLU-109 penetrator, thus eliminating the need for additional FMU-143 procurements and reducing the USN portfolio. In addition, newer aircraft, including the F-15, F-16, F-22 and F-35 do not support the Fuze Function Control Set (FFCS), and rely solely on the SDI for cockpit selectability. Therefore, the FMU-139D/B will provide future compatibility for these tactical aircraft.
R-010
N00019-14-R-0025
N/A
Requesting FZU-48/FZU-63 performance specification and current government drawings.

· Technical Data Package for FZU-48

· Technical Data Package for FZU-63

Yes, the drawing is available upon request.

R-011
N00019-14-R-0025
N/A
Would it be best for the Small Business Subcontracting Plan to only cover the amount of CLIN 0001 and that with the release of delivery orders, the Plan could be updated to reflect the latest planned awards?

See Section L, Part B - Specific Instructions, Volume 2 - Technical Proposal, subsection 2.7 Small Business Management. SB Sub-contracting Plans would only require revisions in the event that the ceiling amount (F-3 Order Limitations) is increased in a future modification.

R012
N00019-14-R-0025
N/A
Requesting packaging drawings with respect to the FMU-139D/B specification
Yes, the drawing is available upon request.

(End of Summary of Changes) image1.wmf