This is a Multi-Year Funding Document for the NMAH: Install Emergency Generator construction project (Project Number: 1803117), a Smithsonian Institution initiative with a total budget exceeding $10 million. The project spans three fiscal years with allocated funding increments: $5 million in FY 2026, $5 million in FY 2027 (obligated by 07/30/2027 or when available), and the remaining balance in FY 2028 (obligated by 07/30/2028 or when available). The project scope includes furnishing and installing two new 500kW natural gas-fueled generators on the museum's roof to replace an aging 300kW diesel-fueled generator, routing a new natural gas line through the building, converting existing collections storage space (Room 4606) into an Emergency Electrical Room, and performing all associated structural, mechanical, electrical, plumbing, security, hazardous material abatement, and architectural modifications. The facility is located at 1300 Constitution Avenue NW, Washington, D.C., 20560, and must remain fully operational and open to the public throughout the construction period.

The FY 2026 phase (4 months) covers general requirements, submittals and shop drawings, long-lead time orders, mobilization, and termination costs. The FY 2027 phase (12 months) encompasses general requirements, existing condition assessment, metals, finishes, plumbing, HVAC, electrical, communications work, and termination costs. The FY 2028 phase (6 months) addresses general requirements and completion of metals, finishes, plumbing, HVAC, electrical, and communications work. Offerors are required to clearly describe and justify any items deleted or added within each funding phase and must identify and provide descriptions of long-lead time items. The applicable NAICS codes are 236220 (Commercial and Institutional Building Construction) with a $45.0 million size standard and 238210 (Electrical Contractors and Other Wiring Installation Contractors) with a $19.0 million size standard.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Tite: NMAH: Install Emergency Generator Project Number: 1803117

The range for this construction project is over $10M.

FY 2026 FUNDING INCREMENT: ($5M available in FY 2026)

General Requirements (4 months)
$
Submittals and Shop Drawings
$
Long Lead Time Orders
$
Mobilization
$
SUBTOTAL:
$

Termination Cost (Cancellation Charge) $ _________________________________________

Other – Offerors shall clearly and completely describe items deleted/added to FY2026 Funding Phase $ ____________________________________________________________________ (Attach pages as necessary)

Identify and include description of long-lead time items.

TOTAL FY2026:

FY 2027 FUNDING INCREMENT: ($5.00M available in FY 2027 obligated by 07/30/2027 or when available)

General Requirements (12 months)
$
Existing Condition
$
Metals
$
Finishes
$
Plumbing
$
HVAC
$
Electrical
$
Communications
$
Others
$
SUBTOTAL:
$

Termination Cost (Cancellation Charge) $ ___________________

Other – Offerors shall clearly and completely describe items deleted/added to FY2027 Funding Phase $ ____________________________________________________________________ (Attach pages as necessary)

TOTAL FY2027:

FY 2028 FUNDING INCREMENT: (Balance of funding obligated by 7/30/28 or when available)

General Requirements (6 months)
$
Metals
$
Finishes
$
Plumbing
$
HVAC
$
Electrical
$
Communications
$
Others
$
SUBTOTAL:
$

Other – Offerors shall clearly and completely describe items deleted/added to FY2028 Funding Phase $ ____________________________________________________________________ (Attach pages as necessary)

TOTAL FY2027: