This document contains a request for proposals for the construction of Pod 6 at the Smithsonian Institution's Museum Support Center. The Smithsonian Institution seeks to award a multi-year funded firm-fixed price contract between $85-95 million to construct a three-story collections storage facility. Funding will be spread over three fiscal years from 2022 through 2024. Approximately 58% of the new building will be occupied by the Smithsonian and 42% by the National Gallery of Art. The project involves demolishing an old greenhouse and constructing bio retention ponds, roads, and parking. The precast concrete facility will provide climate-controlled storage for collections from several Smithsonian museums and the National Postal Museum. Offerors must submit technical and cost proposals by November 1, 2023 to be considered for the contract award.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The Smithsonian Institution intends to award one Multi Year Funded contract. Estimated cost range is between $85M and $95M.
FY2022 FUNDING INCREMENT: ($10M available this FY2022) General Conditions (5 months) $___________________ (assumes Jan. distribution of funds) Mobilization $___________________ Submittals and shop drawings $___________________ Utilities $___________________ Selective Demolition $_______________ Site work $__________________ Foundation $__________________
SUBTOTAL $___________________
Termination Cost (Cancellation Charge) $___________________ Other – Offerors shall clearly and completely describe items deleted/added to FY2022 Funding Phase $___________________ (Attach pages as necessary)
TOTAL-FY2022____________________________________________________$___________________ (Express in Words and Figures)
FY2023 FUNDING INCREMENT: (obligated by 11/1/2023 or sooner from FY2023 appropriation) General Conditions (12 months) $___________________ Submittals and shop drawings $___________________ Panel Mock-up Erect Superstructure $_______________ Precast Concrete Panel Installation $_______________ Utilities $_______________ Steel Stairs and Railings $_______________ Roofing $_______________ Internal Partitions $_______________ Install Mechanical, Electrical and Plumbing $_______________
SUBTOTAL $___________________
Other – Offerors shall clearly and completely describe items deleted/added to FY2023 Funding Phase $___________________ (Attach pages as necessary)
TOTAL-FY2023____________________________________________________$___________________ (Express in Words and Figure
FY2024 FUNDING INCREMENT: Balance of funding (obligated by 11/1/2023 or sooner from FY2024 appropriation) General Conditions $___________________ Submittals and shop drawings $___________________ Install Security Systems $_______________ Landscaping/Horticulture $_______________ Fire Protection system $___________________ Interior Finishing Commissioning and Testing $___________________ Demobilization $___________________ O&M $___________________ As-Built Documents Project Close-out $___________________
SUBTOTAL $___________________
Other – Offerors shall clearly and completely describe items deleted/added to FY2024 Funding Phase $___________________ (Attach pages as necessary)
TOTAL-FY2024____________________________________________________$___________________ (Express in Words and Figure