E1. Q&A M0026426Q0094 Professional Art Framing Services for the NMMC response.pdf
PDF 151 KB Posted
- Attached to
- Professional Art Framing Services for the National Museum of the Marine Corps - updated 6/17/26 with Q&A
- Solicitation number
- M0026426Q0094
- Issued by
-
United States Marine Corps
About this file
This is a Questions and Answers (Q&A) document for the Professional Art Framing Services solicitation (M0026426Q0094) for the National Museum of the Marine Corps (NMMC). The effort is a recompete of a 5-year Indefinite Delivery Indefinite Quantity (IDIQ) contract previously awarded to Montclair Picture Framing Outlet, Inc. under contract M0026420P0185 on 25 September 2020, with a total award value of $239,777.00.
The government clarifies critical service and technical requirements through this Q&A. Contractors must complete a Task Pricing Table for each billable task with firm-fixed rates that include all framing and matting materials. Framing work occurs at the contractor's facility, with the contractor responsible for picking up works of art and prints from the NMMC Museum Support Facility (MSF) and delivering completed frames to either the MSF or main NMMC building. The contractor must complete framing within 15 working days of artwork pickup, with the overall task order completion required within 6 months of award. The contractor must also be available within 48 hours for touch-ups on vendor-supplied frames at the MSF or gallery. The government addresses material substitutions for discontinued fillets, specifying that substitutes must closely match gold colors for affected items. For Item 9, the government confirms fillet placement inside the frame (not within mat opening) and requests standard (non-museum grade) non-glare plexiglass rather than UV-filtering plexiglass. Line 15 of the PWS requires pricing for a 2-inch embellished wood frame. Quoters must submit completed pricing tables and proposed pricing for Draft Task Order 1 as email attachments to be considered for award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
M0026426Q0094 Professional Art Framing Services for the NMMC, Q&A
1. Is there any incumbent/recompete or this is a brand-new project? If yes, could you please provide us with their award number or even if the customer bought similar services in the past.
Government Response: The incumbent for this effort is Montclair Picture Framing Outlet, Inc. This effort is a recompete for a 5-year Indefinite Delivery Indefinite Quantity contract (IDIQ). The previous contract is M0026420P0185, awarded 25 Sep 2020. Total Award Value, $239,777.00.
2. Marine Mass
a. The specified Larson Juhl fillet #131912 has been discontinued by the manufacturer.
b. This item uses CMI fillet #3551 as a substitute.
c. Based on the provided information, it appears that a gold fillet is intended to be used inside the ornate gold frame. Could you please confirm that this interpretation is correct?
Government Response: Yes, we would be looking for a similar fillet to closely match the gold color of the selected now discontinued fillet.
3. Untitled (Korea)
a. The specified fillet has also been substituted due to availability.
b. Our understanding is that a gold fillet is to be used inside a dark wood-tone frame. Please confirm if this is correct.
4. Marine Corps Women's Reserve by Crockwell
a. The specified fillet has been substituted with an equivalent available product.
b. Please confirm that this substitution is acceptable.
5. Item 9
a. The specified fillet has been substituted with Larson Juhl silver fillet #114153.
b. However, it is unclear whether the fillet is intended to be installed inside the frame itself or within the mat opening. Please clarify the intended placement.
c. For pricing purposes, we used Crescent Rag Mat #1170 Cool White.
d. The specification requests non-glare plexiglass. Please clarify whether this should be:
i. Standard non-glare plexiglass, or
ii. Ultraviolet (UV) filtering non-glare plexiglass.
Government Response:
5-b: The fillet is intended to be placed inside the frame and not within the mat opening.
5-d: We are requesting Standard (non-museum grade) non-glare plexiglass.
Thank you for the clarification. We are revising the Pricing Table as follows:
Lines 27 – 29: Ultraviolet (UV) filtering non-glare plexiglass
Lines 30 – 32: Standard (non-museum grade) non-glare plexiglass
6. Task Pricing Table
a. We must admit that we do not fully understand the requirements of the
"Task Pricing Table" referenced in the solicitation.
b. Could you please provide additional guidance, instructions, or an example of how the Task Pricing Table should be completed and submitted?
Government Response:
As per the PWS: “The Government intends to award an Indefinite Delivery Indefinite Quantity contract (IDIQ) for this requirement with a 5-year ordering period during which individual task orders may be issued/awarded under the master IDIQ contract. The ordering period for the base year shall begin upon the date of contract award.” The Task Pricing Table must be completed for each Billable Task, and “Contractor must include the cost of any materials in their firm-fixed rates to include those involving framing and matting, for example.”
7. Confirming that NMMC will provide all items to be framed to the vendor.
Government Response: As per the PWS: “All framing work shall be conducted at the Contractor’s facility. The Contractor shall pick up the works of art and fine art prints on canvas and/or paper from the NMMC art collection located at the MSF and deliver to either the MSF or main NMMC building.”
8. (Be available within 48 hours to perform touch-ups on frames as needed at the NMMC Museum Support Facility (MSF) or in the NMMC art gallery). Does this request pertain to vendor's supplied frames not the existing frame in the NMMC archives?
Government Response: In this instance it refers to the frames supplied by the vendor.
9. Period of Performance: Please clarify. 1. (Framing of the 8 works of art and 2 prints must be completed within 6 months of task order award. The contractor shall have 15 working days to complete framing upon the pickup of the works of art and prints.)
Government Response: Some of the works to be framed may be available to be picked up at the same time, others at a different time based on need. While the task order will be completed within the 6 months timeframe, the 15 working days to complete framing upon the pickup of works refers to the period of time when the works are actually picked up and are within the vendor’s responsibility.
10. Submission of pricing? See below. I am unclear how to fill out the Task Pricing Table versus the Task Order. After reviewing the Task Order attachment, Line 15 indicates 3 different manufacturers. Line items not called out for framing, do we suggest a frame for pricing purposes?
“Quoters must submit their quotes as an attachment(s) to their email submission.
This includes any/all quote pricing and technical information. OFFERORS, PLEASE TAKE NOTE: Completion of 1. Pricing table provided within the PWS, and 2. Proposed Pricing for Draft Task Order 1 is required to be considered for award (see attachments).”
Government Response: On line 15 of the PWS calls for the pricing of a 2” embellished wood frame, response should coincide with this quideline.