This document is an Addendum to a Solicitation for the Long Baseline Neutrino Facility (LBNF) Near Site Conventional Facilities (NSCF) Beamline Complex RFP, Solicitation No. LBNF-BC-350919-BWQ.
The Addendum extends the due date for questions from October 2, 2024 to November 27, 2024, and the Proposal Due Date from October 23, 2024 to December 18, 2024. It also requires bidders to acknowledge the Addendum prior to the new proposal due date. The project scope includes construction services for the Beamline Complex facilities at Fermilab, including buildings, enclosures, and site infrastructure to support the LBNF Beamline. The procurement is a Firm Fixed Price (FFP) Subcontract, and Fermi Research Alliance, LLC (FRA) reserves the right to reject any and all proposals. A mandatory Pre-Proposal Conference will be held on July 11, 2024, and all prospective bidders must attend to be eligible for award.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM TO SOLICITATION
ADDENDUM NO.
DATE OF ADDENDUM:
9/27/2024
SOLICITATION NO.
LBNF-BC-350919-BWQ
DATE ISSUED:
6/05/2024
PROJECT NO.
N/A
OPENING DATE:
12/18/2024
TITLE OF PROJECT:
LONG BASELINE NEUTRINO FACILITY (LBNF) NEAR SITE CONVENTIONAL FACILITIES (NSCF)
BEAMLINE COMPLEX RFP
Bidders must acknowledge this Addendum prior to the hour and date set forth in the solicitation by one of the following methods:
1. By completing the Representations, Certifications and Acknowledgments (PUR-466), or
2. By separate email.
If by virtue of this Addendum you desire to change a bid already submitted, such change may be made by email, provided such email makes reference to the Solicitation and this Addendum and is received prior to the time set for opening.
This Addendum is providing additional information on the items below:
I. DUE DATE FOR QUESTIONS AND PROPOSALS
1. The due date for questions is changed from October 2, 2024 to November 27, 2024.
2. The Proposal Due Date is changed from 3PM Central Time October 23, 2024 to 3PM Central Time December 18, 2024.
ALL OTHER TERMS AND CONDITIONS AS REFERENCED UNDER THE SUBJECT RFP REMAIN UNCHANGED.
Fermi Research Alliance, LLC Brian Quinn P.O. Box 500 Project Procurement Specialist Batavia, IL 60510 (630) 840-5777 M.S 210