(K) RFI Form.pdf

PDF 384 KB Posted

Attached to
Repair Water Main Valves/Lines, Southeast Zone
Solicitation number
6062471
Issued by

About this file

This document is a Request for Information (RFI) form related to a federal contract opportunity. The RFI is for Contract Number RFP 5997234, with the contract title and prime contractor/subcontractor information provided. The RFI requests information and a recommended solution regarding a drawing, detail, specification, and cost effect. The RFI requires a response by a specific date. The document also includes a recommendation section, a reply section, and instructions that this RFI does not constitute authorization to proceed with work.

The related federal contract opportunity is for Solicitation Number 6062471 to Repair Water Main Valves/Lines in the Southeast Zone at Naval Submarine Base New London in Groton, CT. The scope includes the removal and replacement of 38 water valves and associated piping. This requirement is limited to 7 contractors under MACC ML-C00068, and no other offers will be accepted. The contracting agency is the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files

File Type Posted
Amendment 00001.pdf PDF
(M) FAR 52.204-24.pdf PDF
(O) Sales Tax Exemption Form 2016-R-0149.pdf PDF
(J) Map to B135.pdf PDF
(H) General Requirements.pdf PDF
(B) Specifications.pdf PDF
(D) SUBMITTAL REGISTER.pdf PDF
(C) Drawings.pdf PDF
(F) PRICE PROPOSAL FORM.docx DOCX document
(E) NEPA.pdf PDF
(N) Guide to Taxes.pdf PDF
(A) MACC RFP.pdf PDF
(G) Wage Determination.pdf PDF
(P) CERT-141.pdf PDF
(I) Base Map.pdf PDF
(L) ECMS.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT NUMBER:

RFP 5997234

REQUEST FOR INFORMATION RFI NUMBER:

CONTRACT TITLE:

PRIME CONTRACTOR: SUBCONTRACTOR/SUPPLIER:

SUBJECT/TITLE OF RFI:

DRAWING(S): DETAIL(S): SPECIFICATION: CPM ACTIVITY NUMBER:

COST EFFECT: INCREASE: DECREASE: NONE:

INFORMATION REQUESTED & RECOMMENDED SOLUTION:

Date Response Required By: Date: Signature:

From:

To: Field Office Code

RECOMMENDATION:

Date: Signature:

From: Field Office To: Prime Contractor

REPLY:

Date: Signature:

This reply is given with the expressed understanding that it does not constitute basis for change in the amount or time of subject contract. If you do not concur, DO NOT PROCEED, and notify this office immediately.

Please assign PC # to this change. It is requested that a proposal be forwarded by . THIS DOES NOT

CONSTITUTE AUTHORIZATION TO PROCEED.

copy to: File 2L

Supv Civil Engineer Construction Representative

The RFI system is intended to provide an efficient mechanism for responding to contractor’s request for information ONLY. This system DOES NOT authorize the contractor to proceed with work - to do so, the contractor proceeds at his own risk. If the contractor considers the RFI response a changed condition, written notice to the Contracting Officer is required within 20 calendar days.

DISTRIBUTION: Original to File via REICC PL/DM ET A/E PC # via AROICC/CONTRACT OFFICER

File details come from the government source that posted it. Updated .