This document is an amendment to a solicitation for a federal contract opportunity. The purpose of this amendment is to revise the scope of work and extend the proposal due date for the project to repair water main valves and lines in the southeast zone at Naval Submarine Base New London in Groton, CT.
The revised scope of work includes an estimate that 50% of the waterlines to be removed are assumed to be asbestos, which must be handled, removed, and disposed of per state, local codes, and SUBASE manifest requirements. The proposal due date has been extended to August 14, 2024, 12:00 PM EST. This requirement is limited to the 7 contractors under MACC ML-C00068, and no other offers will be accepted. The contracting agency is the Department of the Navy Naval Facilities Engineering Command.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| (M) FAR 52.204-24.pdf | ||
| (K) RFI Form.pdf | ||
| (O) Sales Tax Exemption Form 2016-R-0149.pdf | ||
| (J) Map to B135.pdf | ||
| (H) General Requirements.pdf | ||
| (B) Specifications.pdf | ||
| (D) SUBMITTAL REGISTER.pdf | ||
| (C) Drawings.pdf | ||
| (F) PRICE PROPOSAL FORM.docx | DOCX document | |
| (E) NEPA.pdf | ||
| (N) Guide to Taxes.pdf | ||
| (A) MACC RFP.pdf | ||
| (G) Wage Determination.pdf | ||
| (P) CERT-141.pdf | ||
| (I) Base Map.pdf | ||
| (L) ECMS.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
1.2
C:\PERFORM\FORMS\S30.FRP
Forms Management
C:PERFORMFORMSS30.FRP
Acrobat PDFWriter 2.01 for Windows D:19971010095222 D:19990614133004
C:PERFORMFORMSS30.FRP
Standard Form 30 - Amendment of Solicitation/Modification of Contract Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER
3. EFFECTIVE DATE
4. REQUISITION/PURCHASE REQUISITION NUMBER
5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6)
CODE
STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.
is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY
CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer) Previous edition unusable
| 9A. AMENDMENT OF SOLICITATION NUMBER: 00001 |
| 9A. AMENDMENT OF SOLICITATION NUMBER: ACQR 6062471 |
| 7. CODE: |
| 12. ACCOUNTING AND APPROPRIATION DATA (If required): |
| 13A. THIS CHANGE ORDER IS ISSUED PURSUANT TO. Specify authority. THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.: |
| 13C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF: |
| 13D. OTHER. Specify type of modification and authority.: |
| 15A. NAME AND TITLE OF SIGNER. Type or print.: |
| 16A. NAME AND TITLE OF CONTRACTING OFFICER. Type or print.: Kirsten M. Cohoon |
| 14. DESCRIPTION OF AMENDMENT OR MODIFICATION (Organized by UCF section headings, including solicitation or contract subject matter where feasible.): The purpose of this amendment is to add revision to scope and extend proposal due date. |
Contractor shall estimate that 50% of the waterlines to be removed are assume to be asbestos and must be handled, removed and disposed of per state, local codes and SUBASE manifest requirements.
Proposal due date extended to 14 August 2024, 12:00 PM EST
| FACILITY CODE: |
| 6. ISSUED BY: NAVFACSYSCOM MID-ATLANTIC |
PWD NEW LONDON
BOX 400 BLDG 135
NAVAL SUBMARINE BASE NEW LONDON
GROTON, CT 06349-5026
| 8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code): |
| 7. ADMINISTERED BY (If other than Item 6): |
See Item 6
| 1. CONTRACT ID CODE: |
| 4. REQUISITION/PURCHASE REQUISITION NUMBER: ACQR 6062471 |
| 10A. MODIFICATION OF CONTRACT/ORDER NUMBER: |
| 5. PROJECT NUMBER. If applicable.: |
| PAGE: 1 |
| PAGES: 1 |
| 3. EFFECTIVE DATE. Enter 2 digit month, 2 digit day and 4 digit year.: 2024-08-06 |
| 9B. DATED. SEE ITEM 11. Enter 2 digit month, 2 digit day and 4 digit year.: 2024-07-09 |
| 10B. DATED. SEE ITEM 13. Enter 2 digit month, 2 digit day and 4 digit year.: |
| 9A. AMENDMENT OF SOLICITATION NUMBER: 0 |
| 10A. MODIFICATION OF CONTRACT/ORDER NUMBER: 0 |
| 11. The above numbered solicitation is amended as set forth in Item 14. : 1 |
| 13A. THIS CHANGE ORDER IS ISSUED PURSUANT TO. Specify authority. THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.: 0 |
| 13B. THE ABOVE NUMBERED CONTRACT OR ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES. Such as changes in paying office, appropriation date, etc. SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103b.: 0 |
| 13C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF: 0 |
| 13D. OTHER Specify type of modification and authority.: 0 |
| 13E. IMPORTANT: Contractor is not required to sign this document and return copies to the issuing office.: 1 |
| 13E. IMPORTANT: Contractor is required to sign this document and return copies to the issuing office.: 0 |
| 11. The hour and date specified for receipt of Offers is extended : 1 |
| 11. The hour and date specified for receipt of Offers is not extended : 0 |
| 15B. CONTRACTOR OR OFFEROR. Signature of person authorized to sign. Digital Signature.: |
| 16C. DATE SIGNED. Enter 2 digit month, 2 digit day and 4 digit year.: 2024-08-06 |