J03 Submittal and Testing Log.xlsx
XLSX spreadsheet 18 KB Posted
- Solicitation number
- 75H70122R00045
About this file
This solicitation package describes a federal construction contract opportunity for the Shitike Creek Water Main Crossing project in Warm Springs, Oregon. The Indian Health Service seeks a small business contractor to install approximately 1,000 linear feet of new water transmission main piping and associated infrastructure. The scope of work includes excavation, trenching, pipe installation, backfilling, erosion control measures, site restoration, and disinfection of the new water distribution system. The solicitation package provides plans, specifications and a construction wage determination. The project is set aside exclusively for small businesses with a preference for Indian Economic Enterprises. The performance period is 150 calendar days from notice to proceed. Questions are due by June 10th and proposals are due by June 20th, with award planned for a firm fixed price construction contract. The location is at the intersection of Wolford Canyon Road and Hollywood Boulevard in Warm Springs. The contractor must comply with Tribal Employment Rights Ordinance requirements of the Confederated Tribes of Warm Springs.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal log
| MATERIAL SUBMITTAL REVIEW FORM - CONSTRUCTION |
| CONFEDERATED TRIBES OF WARM SPRINGS |
| SHITIKE CREEK WATER MAIN CROSSING |
| [CONTRACT #] |
CONTRACTOR:
| SUBMITTALS REQUIRED | |||||
| Item No. | Item Reference | Description | Model No., Type, Manufacturer, etc. | Received Date | Approval Status |
| Includes submittals for schedules A & B | |||||
| Section 01 30 00 Administrative Requirements | |||||
| 1 | Construction Schedule | ||||
| Section 01 40 00 Quality Requirement | |||||
| 2 | Testing Entities | See testing log | |||
| Section 01 55 26 Construction Traffic Control | |||||
| 3 | Traffic Control Plan | ||||
| Section 01 70 00 Execution and Closeout Requirements | |||||
| 4 | Record Drawings | ||||
| 5 | O&M Manual | Include valve cut sheets, etc. | |||
| 6 | Product Warranties | ||||
| Section 03 30 00 Cast-In-Place Concrete | |||||
| 7 | Concrete Mix Design | Separate for each concrete strength | |||
| 8 | Concrete Products | Manufacturer, Certificate, Curings compounds, etc. | |||
| Section 05 50 00 Metal Fabrications | |||||
| 9 | Shop Drawings | ||||
| Section 31 23 16 Excavation | |||||
| 10 | Excavation Protection Plan | ||||
| Section 31 23 17 Trenching | |||||
| 11 | Bedding Material | ||||
| Section 33 23 18 Rock Removal | |||||
| 12 | Rock Removal Method | If Needed | |||
| 13 | Nearby Building Report | If Needed | |||
| Section 31 23 19 Dewatering | |||||
| 14 | Dewatering Plan | Layout, depths, pump sizes, etc. | |||
| 15 | Product Data | Pump and equipment cut sheets | |||
| 16 | Material Data | Filter sand and grout | |||
| 17 | Closeout | Abandoned well location and depths | |||
| Section 31 25 13 Erosion Controls | |||||
| 18 | Product Data | Sil fencing, erosion fiber logs, etc. | |||
| Section 32 11 23 Aggregate Base Courses | |||||
| 19 | Materials Source and Manufacturer Cert. | ||||
| Section 32 12 16 Asphalt Paving | |||||
| 20 | Product Data | materials and mix design | |||
| Section 32 13 13 Concrete Paving | |||||
| 21 | Design Data | Mix ingredients proportions, and admxitures | |||
| Section 32 92 19 Seeding | |||||
| 22 | Product Data | Seed mix, fertilizer, mulch | |||
| Section 33 13 00 Disinfecting of Water Distribution | |||||
| 23 | Product Data | Disinfection method, chemical | |||
| Section 33 14 13 Water Utility Distribution Piping | |||||
| 24 | Product Data: | ||||
| 24.a | Transmission Main Pipe | Include above ground, below ground, transition pipe, and welded outlets | |||
| 24.b | Restrained Fittings | ||||
| 24.c | Gate Valve | ||||
| 24.d | Butterfly Valves | ||||
| 24.e | Combination Air Valves | ||||
| 24.f | Air Release Valves | ||||
| 24.g | Corporation Stop | ||||
| 24.h | Service Saddle | ||||
| 24.i | Pipe Insulation | ||||
| 24.j | Flush Hydrants | ||||
| 24.k | Blowoff Assembly Materials | Include pipe and fittings | |||
| 24.l | Pipe Encasement |
Testing log
| MATERIAL SUBMITTAL REVIEW FORM - CONSTRUCTION |
| CONFEDERATED TRIBES OF WARM SPRINGS |
| SHITIKE CREEK WATER MAIN CROSSING |
| [CONTRACT #] |
CONTRACTOR:
| Testing Log | ||||||
| Test No. | Description and Reference | Type/Frequency | Lab/Tester | Results | Result Date | Acceptable? |
| Includes tests schedules A & B | ||||||
| Section 03 30 00 Cast-In-Place Concrete | ||||||
| 1 | Strength Tests: | 1 set per 150 CY or less per day | ||||
| 1 | 7 days | |||||
| 1 | 28 days | |||||
| 1 | 56 days | |||||
| 2 | Field Tests: | Every Strength Sample | ||||
| 2.a | Slump test | |||||
| 2.b | Air Content Test | |||||
| 2.c | Temperature Test | |||||
| Section 31 23 19 Dewatering | ||||||
| 3 | Pumping Test | |||||
| 4 | Dewatering Monitoring: | |||||
| 4.a | Discharge | Daily until static, then semiweekly | ||||
| 4.b | Groundwater elevation | Daily | ||||
| 4.c | Total voulme pumped | Daily | ||||
| Section 32 11 23 Aggregate Base Courses | ||||||
| 5 | Compaction | Every 1,000 square yard applied | ||||
| Section 32 12 16 Asphalt Paving | ||||||
| 6 | Thickness | Every 1,000 square yard applied | ||||
| 7 | Density | Every 1,000 square yard applied | ||||
| Section 31 23 10 Excavation Trenching and Backfill (Schedule B only) | ||||||
| 8 | Compaction | 1 every 100 LF pipe if not under a roadway. If under roadway, 6-inch loose lifts tested | ||||
| Section 31 23 17 Trenching | ||||||
| 9 | Compaction | 1 every 500 LF pipe, multiple lifts | ||||
| Section 32 13 13 Concrete Paving | ||||||
| 10 | Strength Tests: | 1 set per 150 CY or less per day | ||||
| 10.a | 7 days | |||||
| 10.b | 28 days | |||||
| 10.c | 56 days | |||||
| 11 | Field Tests: | Every strength sampling | ||||
| 11.a | Slump test | |||||
| 11.b | Air Content Test | |||||
| 11.c | Temperature Test | |||||
| Section 33 13 00 Disinfecting of Water Distribution | ||||||
| 12 | Chlorine Residual | Prior to connecting to existing system, repeated as needed | ||||
| 13 | Coliform Testing | Every 1,200 feet of main plus 1 for each branch, repeated as needed | ||||
| Section 33 14 13 Water Utility Distribution Piping | ||||||
| 14 | Hydrostatic Test | At completion, repeat as needed | ||||
| 15 | Leakage Test | At completion, repeat as needed | ||||
| 16 | Bedding Compaction Test | Every 1,000 LF pipe installed |
File details come from the government source that posted it. Updated .