This solicitation seeks proposals for the Shitike Creek Water Main Crossing construction project located in Warm Springs, Oregon. The project scope includes installing approximately 1,000 linear feet of ductile iron water main and appurtenances across Shitike Creek to connect to the existing water distribution system. The construction duration is 150 calendar days from notice to proceed. Proposals are due by June 20, 2022.
The project is set aside exclusively for small businesses, with preference given to Indian Economic Enterprise firms. The construction contract will be a firm fixed price awarded under a lowest price technically acceptable evaluation. The solicitation includes plans, specifications and a site visit scheduled for interested offerors. The Department of Health and Human Services Indian Health Service is the contracting agency for this project located at the intersection of Wolford Canyon Road and Hollywood Boulevard in Warm Springs.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A00003
TOBY HAYDEN
75H70122R00045 Shitike Creek Water Main Crossing
The purpose of Amendment A00003 is to answer additional questions and update attachment J01. All other terms and conditions remain unchanged. See continuation page for details.
Indian Health Service - DES Seattle 701 5th Avenue, Suite 1600 Seattle, WA 98104
75H70122R00045
PO-20-M97
1 3
06/09/2022
05/20/2022
6/9/2022
SF 30 Continuation Page
75H70122R00045-A00003 Page 2 of 3
Amendment A00003 – SF 30, Block 14 (Cont’d)
The purpose of this amendment is as follows:
1. Additional questions (5 – 19) have been received and answered in response to this solicitation:
QUESTION ANSWER
I don't see any details for the bridge crossing. Are there drawings for this section that I am not seeing?
See attachment J02a Plans - Bridge Water Main
Crossing
The DI pipe will take about 150 day lead time from order. Do you have a provision for this regarding completion time?
The period of performance (POP) for this effort is 150 days from NTP; NTP is anticipated to be issued 10 days after award. For long lead time items, the contractor is expected to order approved materials as soon as possible in order to accommodate this POP.
Extensions to the POP will be considered for unusually long lead time items.
Requesting alternate equipment/material: Fusible
C900 pipe
Fusible PVC C900 is not an approved substitute for
Class 350 ductile iron water main.
Do you have any more detail on the bridge crossing? I do not see any information on it in the bid documents.
See answer to Q1
Is there a maximum length for the required 2 pipe sections after the welded-outlet for the blow-off assembly?
A full 20’ pipe section is allowable, as long as there are
2 connections with a minimum length of 2’ per connection.
We have had long delays in receiving ductile iron water main (~150-180 days), how will this affect the period of performance?
See answer to Q2
What is the nearest waste disposal location? There is a transfer station located in Madras, OR. The
Confederated Tribes of Warm Springs operates a landfill within Warm Springs, but its availability hasn’t been verified. Excess rock and spoil can be dumped at the nearby Warm Springs Wastewater Treatment Plant.
Are the tests (e.g. compactions tests) and special inspections the responsibility of the contractor?
Testing and special inspections as outlined in the specifications are the responsibility of the contractor.
The identity of the independent testing entities is required as a submittal.
Does the TERO office have traffic flaggers available for hire?
Yes, the TERO contact number is 541-615-0853, and website: wstero.com
What are the rush-hour times for traffic along
Hollywood Boulevard?
7:45-8:30am and 4:30-5:30pm.
What type of connections should be used for the tee that will connect to the existing system?
Welded flanges are preferred for the tee connecting to the existing system. The rest of the connections are as listed in the technical specifications.
Is there a preference on the order of installation for the water main?
In order to minimize downtime of the system, the
Utility prefers making the connections to the existing water main with the isolation valves, then to proceed with the rest of the water main installation.
What is the purpose of the shear pin in the bridge crossing supports?
The shear pin provides resistance to shear forces between the concrete curb and girder from the pipe weight.
SF 30 Continuation Page
75H70122R00045-A00003 Page 3 of 3
Is a flexible expansion joint required for the bridge crossing?
A flexible expansion joint is not included in the design.
The TR Flex restrained joints specified provide adequate movement to allow for expansion.
Is there a side view of the pipe support for the bridge crossing?
Side views are not available. Standard dimensions of the ASTM A36 steel members are available online however.
Are pipe saddles required for the pipe insulation on the bridge crossing?
Pipe saddle supports are required at the bridge supports. Pipe insulation will be jacketed around pipe with aluminum sheeting, which will be secured with stainless steel strapping, per the specifications
(Section 33 14 13, pg 10; sheets CP-02 and CP-03).
Is there an escalation clause for long lead times on material?
No
Is there a waiver on Buy American clauses? If so, does it apply to this project?
There are currently no waivers for the acquisition. The requirements of contract clause FAR 52.225-9 Buy
American – Construction Materials (NOV 2021) and
FAR 52.225-10 Notice of Buy American Requirement
– Construction Materials (MAY 2014) are applicable to this solicitation and resulting contract.
Offerors may request a determination of inapplicability of the Buy American statute by submitting a request to the Contracting Officer in accordance with FAR
52.225-10 paragraph (b)
Do you guys have a contact list for all job walk attendees on 6/7/22?
The companies in attendance were as follows:
Doyon
York Bros
McDonalds Excavating
Mckernan
NWCP
Bridge Masters Inc.
2. Section J Attachment J01 Technical Specifications is revised to update SECTION 33 14 13 Water Utility
Distribution Piping. The new version is attached as follows:
J01 Technical Specifications – Shitike Creek Crossing (REVISED as of A00003)
3. The proposal due date remains unchanged at Monday, June 20, 2022 at 2:00 PM PT.
4. All other terms and conditions remain unchanged.
Offerors are reminded to acknowledge all amendments on the SF1442 when submitting a proposal in accordance with the RFP requirements.