This request for proposals solicits construction services for dioxin remediation at the Bien Hoa Airbase in Vietnam. The United States Agency for International Development Vietnam seeks to award a firm-fixed-price contract between $50-80 million for a period of approximately five years. The solicitation requires offerors to be registered under NAICS code 562910 for remediation services with a business size of $22 million and be eligible under geographic code 937. Questions regarding the RFP are due by July 12, 2021 and proposals are due August 19, 2021. The recorded site walk and pre-proposal conference will be held virtually during the week of July 19, 2021.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date: Size: Scale:
Revision: No: Sheet:
2nd Jun 2021 A3 As Shown
09 00 01
TCH Treatment Plant
Prepared by:
Drawing Title:
DIOXIN REMEDIATION
AT BIEN HOA AIRBASE
AREA PROJECT
Project Name:
G
G
G
G TCH Treatment Plant
Treated Material Storage Area
Site Office
Pre-Treatment Storage Area
W astewater - Vapor
Treatment Plant
G
Substation and W ater Supply
Haemers’s Site
G
G
Detention Ponds
G
Guard Shack
G
Guard Shack
Legend
Scale:
50 0 50 10025 M
1:3,000
Projection: VN-2000, central meridian 107 0 45 '
Treatment Function Area (m2)
30,600 3,100 12,000 26,700
5,000 Pre-Treatment Sto rage Area Wastew ater - Vapo r Treatment Plant TCH Treatment Plant Treated Mater ial Sto r age Area
Site Office
1,000Sub station and Water Supply
*No tes: A distance fr om TCH Treatment Plant b oundar y to Haemer's fencing is 6 m.
Steel Fencing
Pre-Treatment Sto rage Area
Wastewater - Vapo r Treatment Plant TCH Treatment Plant Treated Mater ial St o rage Area
Site Office
Sub station and Water Supply Haemer s’s fencing
Detention Pond
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F F
F F
F F
F
F
F
F
F F
F
F
FF Route In & Route Out
G G
C100-003
A
C100-003
A
C100-004
B
C100-004
C
C100-004
C
C100-004
B
A307/05/2021
PREPARED BY
NGƯỜI THỰC HIỆN:
CHECKED BY
NGƯỜI KIỂM TRA:
DIOXIN REMEDIATION AT BIEN HOA
AIRBASE AREA PROJECT - PHASE 1
DỰ ÁN XỬ LÝ Ô NHIỄM DIOXIN KHU VỰC
SÂN BAY BIÊN HÒA - GIAI ĐOẠN 1
AS NOTED
REV DESCRIPTION DATE BY
BẢN ĐIỀU CHỈNH NGÀY BỞI
PREPARED FOR
CHỦ ĐẦU TƯ:
LISBETH HABANS NAGRATH
DESIGNER OF RECORD
CHỦ NHIỆM THIẾT KẾ:
PROJECT NAME/ TÊN DỰ ÁN:
DRAWING TITLE/ TÊN BẢN VẼ:
DATE/ NGÀY: SIZE/ KHỔ: SCALE/ TỈ LỆ:
LE THI THANH THUY
PHAN THANH LUAN
SHEET
TỜ:
OF
CỦA:
Trigon Associates, llc1515 Poydras St., Ste 2200 New Orleans, LA 70112 www.trigonassociates.com
ENGINEERING • CONSULTING • MANAGEMENT
A&E BIEN HOA CONTRACTOR
NHÀ THẦU TV&TK BIÊN HÒA
DRAWING NO / BẢN VẼ SỐ:
CIVIL WORKS PHASE 1
11/05/2021
C100-002 02
PRE-TREATMENT STORAGE
AREA PLAN
PRE-TREATMENT STORAGE AREA PLAN
SC: 1-1000
AutoCAD SHX Text 2.75m
AutoCAD SHX Text 2.50m
AutoCAD SHX Text 3.00m
AutoCAD SHX Text 3.00m
AutoCAD SHX Text 2.75m
AutoCAD SHX Text 2.50m
AutoCAD SHX Text
SEDIMENT DRYING BED
AutoCAD SHX Text
CONTAINMENT CURB
AutoCAD SHX Text
TURBIDITY CURTAIN WITH EXPANDED POLYSTYRENE (EPS) FOAM FOR FLOTATION
AutoCAD SHX Text NOTES: - ALL DIMENSIONS ARE IN CENTIMETER. ALL DIMENSIONS ARE IN CENTIMETER. - PTSA IS INCLUDED TWO CELLS. EACH CELL HAS 2 SUMPS AT THE CONNERS TO PTSA IS INCLUDED TWO CELLS. EACH CELL HAS 2 SUMPS AT THE CONNERS TO IS INCLUDED TWO CELLS. EACH CELL HAS 2 SUMPS AT THE CONNERS TO IS INCLUDED TWO CELLS. EACH CELL HAS 2 SUMPS AT THE CONNERS TO INCLUDED TWO CELLS. EACH CELL HAS 2 SUMPS AT THE CONNERS TO INCLUDED TWO CELLS. EACH CELL HAS 2 SUMPS AT THE CONNERS TO TWO CELLS. EACH CELL HAS 2 SUMPS AT THE CONNERS TO TWO CELLS. EACH CELL HAS 2 SUMPS AT THE CONNERS TO CELLS. EACH CELL HAS 2 SUMPS AT THE CONNERS TO CELLS. EACH CELL HAS 2 SUMPS AT THE CONNERS TO EACH CELL HAS 2 SUMPS AT THE CONNERS TO EACH CELL HAS 2 SUMPS AT THE CONNERS TO CELL HAS 2 SUMPS AT THE CONNERS TO CELL HAS 2 SUMPS AT THE CONNERS TO HAS 2 SUMPS AT THE CONNERS TO HAS 2 SUMPS AT THE CONNERS TO 2 SUMPS AT THE CONNERS TO 2 SUMPS AT THE CONNERS TO SUMPS AT THE CONNERS TO SUMPS AT THE CONNERS TO AT THE CONNERS TO AT THE CONNERS TO THE CONNERS TO THE CONNERS TO CONNERS TO CONNERS TO TO TO COLLECT RAINWATER AND LEACHATE FROM THE CENTER OF THE CELL, WHICH IS RAINWATER AND LEACHATE FROM THE CENTER OF THE CELL, WHICH IS RAINWATER AND LEACHATE FROM THE CENTER OF THE CELL, WHICH IS AND LEACHATE FROM THE CENTER OF THE CELL, WHICH IS AND LEACHATE FROM THE CENTER OF THE CELL, WHICH IS LEACHATE FROM THE CENTER OF THE CELL, WHICH IS LEACHATE FROM THE CENTER OF THE CELL, WHICH IS FROM THE CENTER OF THE CELL, WHICH IS FROM THE CENTER OF THE CELL, WHICH IS THE CENTER OF THE CELL, WHICH IS THE CENTER OF THE CELL, WHICH IS CENTER OF THE CELL, WHICH IS CENTER OF THE CELL, WHICH IS OF THE CELL, WHICH IS OF THE CELL, WHICH IS THE CELL, WHICH IS THE CELL, WHICH IS CELL, WHICH IS CELL, WHICH IS WHICH IS WHICH IS IS IS SLOPE TO THE CONNERS. - WATER FROM SUMPS FOR SEDIMENT SETTLEMENT WILL BE COLLECTED INTO TWO WATER FROM SUMPS FOR SEDIMENT SETTLEMENT WILL BE COLLECTED INTO TWO FROM SUMPS FOR SEDIMENT SETTLEMENT WILL BE COLLECTED INTO TWO FROM SUMPS FOR SEDIMENT SETTLEMENT WILL BE COLLECTED INTO TWO SUMPS FOR SEDIMENT SETTLEMENT WILL BE COLLECTED INTO TWO SUMPS FOR SEDIMENT SETTLEMENT WILL BE COLLECTED INTO TWO FOR SEDIMENT SETTLEMENT WILL BE COLLECTED INTO TWO FOR SEDIMENT SETTLEMENT WILL BE COLLECTED INTO TWO SEDIMENT SETTLEMENT WILL BE COLLECTED INTO TWO SEDIMENT SETTLEMENT WILL BE COLLECTED INTO TWO SETTLEMENT WILL BE COLLECTED INTO TWO SETTLEMENT WILL BE COLLECTED INTO TWO WILL BE COLLECTED INTO TWO WILL BE COLLECTED INTO TWO BE COLLECTED INTO TWO BE COLLECTED INTO TWO COLLECTED INTO TWO COLLECTED INTO TWO INTO TWO INTO TWO TWO TWO DETENTION PONDS BEFORE DISCHARGE. - CIVIL WORKS 1 CONTRACTOR WILL LOAD MATERIAL FROM WEST TO EAST, FROM CIVIL WORKS 1 CONTRACTOR WILL LOAD MATERIAL FROM WEST TO EAST, FROM WORKS 1 CONTRACTOR WILL LOAD MATERIAL FROM WEST TO EAST, FROM WORKS 1 CONTRACTOR WILL LOAD MATERIAL FROM WEST TO EAST, FROM 1 CONTRACTOR WILL LOAD MATERIAL FROM WEST TO EAST, FROM 1 CONTRACTOR WILL LOAD MATERIAL FROM WEST TO EAST, FROM CONTRACTOR WILL LOAD MATERIAL FROM WEST TO EAST, FROM CONTRACTOR WILL LOAD MATERIAL FROM WEST TO EAST, FROM WILL LOAD MATERIAL FROM WEST TO EAST, FROM WILL LOAD MATERIAL FROM WEST TO EAST, FROM LOAD MATERIAL FROM WEST TO EAST, FROM LOAD MATERIAL FROM WEST TO EAST, FROM MATERIAL FROM WEST TO EAST, FROM MATERIAL FROM WEST TO EAST, FROM FROM WEST TO EAST, FROM FROM WEST TO EAST, FROM WEST TO EAST, FROM WEST TO EAST, FROM TO EAST, FROM TO EAST, FROM EAST, FROM EAST, FROM FROM FROM NORTHERN CELL TO SOUTHERN CELL USING EASTERN ACCESS ROADS. TREATMENT 1 CELL TO SOUTHERN CELL USING EASTERN ACCESS ROADS. TREATMENT 1 CELL TO SOUTHERN CELL USING EASTERN ACCESS ROADS. TREATMENT 1 TO SOUTHERN CELL USING EASTERN ACCESS ROADS. TREATMENT 1 TO SOUTHERN CELL USING EASTERN ACCESS ROADS. TREATMENT 1 SOUTHERN CELL USING EASTERN ACCESS ROADS. TREATMENT 1 SOUTHERN CELL USING EASTERN ACCESS ROADS. TREATMENT 1 CELL USING EASTERN ACCESS ROADS. TREATMENT 1 CELL USING EASTERN ACCESS ROADS. TREATMENT 1 USING EASTERN ACCESS ROADS. TREATMENT 1 USING EASTERN ACCESS ROADS. TREATMENT 1 EASTERN ACCESS ROADS. TREATMENT 1 EASTERN ACCESS ROADS. TREATMENT 1 ACCESS ROADS. TREATMENT 1 ACCESS ROADS. TREATMENT 1 ROADS. TREATMENT 1 ROADS. TREATMENT 1 TREATMENT 1 TREATMENT 1 1 1 CONTRACTOR WILL UNLOAD MATERIAL AT THE SAME DIRECTION ORDER WITH CIVIL WILL UNLOAD MATERIAL AT THE SAME DIRECTION ORDER WITH CIVIL WILL UNLOAD MATERIAL AT THE SAME DIRECTION ORDER WITH CIVIL UNLOAD MATERIAL AT THE SAME DIRECTION ORDER WITH CIVIL UNLOAD MATERIAL AT THE SAME DIRECTION ORDER WITH CIVIL MATERIAL AT THE SAME DIRECTION ORDER WITH CIVIL MATERIAL AT THE SAME DIRECTION ORDER WITH CIVIL AT THE SAME DIRECTION ORDER WITH CIVIL AT THE SAME DIRECTION ORDER WITH CIVIL THE SAME DIRECTION ORDER WITH CIVIL THE SAME DIRECTION ORDER WITH CIVIL SAME DIRECTION ORDER WITH CIVIL SAME DIRECTION ORDER WITH CIVIL DIRECTION ORDER WITH CIVIL DIRECTION ORDER WITH CIVIL ORDER WITH CIVIL ORDER WITH CIVIL WITH CIVIL WITH CIVIL CIVIL CIVIL WORKS 1 CONTRACTOR BUT USING WESTERN ACCESS ROADS. IF HALF OF CELL IS 1 CONTRACTOR BUT USING WESTERN ACCESS ROADS. IF HALF OF CELL IS 1 CONTRACTOR BUT USING WESTERN ACCESS ROADS. IF HALF OF CELL IS CONTRACTOR BUT USING WESTERN ACCESS ROADS. IF HALF OF CELL IS CONTRACTOR BUT USING WESTERN ACCESS ROADS. IF HALF OF CELL IS BUT USING WESTERN ACCESS ROADS. IF HALF OF CELL IS BUT USING WESTERN ACCESS ROADS. IF HALF OF CELL IS USING WESTERN ACCESS ROADS. IF HALF OF CELL IS USING WESTERN ACCESS ROADS. IF HALF OF CELL IS WESTERN ACCESS ROADS. IF HALF OF CELL IS WESTERN ACCESS ROADS. IF HALF OF CELL IS ACCESS ROADS. IF HALF OF CELL IS ACCESS ROADS. IF HALF OF CELL IS ROADS. IF HALF OF CELL IS ROADS. IF HALF OF CELL IS IF HALF OF CELL IS IF HALF OF CELL IS HALF OF CELL IS HALF OF CELL IS OF CELL IS OF CELL IS CELL IS CELL IS IS IS EMPTY AND MATERIAL IS AVAILABLE FOR CIVIL WORKS 1 CONTRACTOR TO HAUL AND AND MATERIAL IS AVAILABLE FOR CIVIL WORKS 1 CONTRACTOR TO HAUL AND AND MATERIAL IS AVAILABLE FOR CIVIL WORKS 1 CONTRACTOR TO HAUL AND MATERIAL IS AVAILABLE FOR CIVIL WORKS 1 CONTRACTOR TO HAUL AND MATERIAL IS AVAILABLE FOR CIVIL WORKS 1 CONTRACTOR TO HAUL AND IS AVAILABLE FOR CIVIL WORKS 1 CONTRACTOR TO HAUL AND IS AVAILABLE FOR CIVIL WORKS 1 CONTRACTOR TO HAUL AND AVAILABLE FOR CIVIL WORKS 1 CONTRACTOR TO HAUL AND AVAILABLE FOR CIVIL WORKS 1 CONTRACTOR TO HAUL AND FOR CIVIL WORKS 1 CONTRACTOR TO HAUL AND FOR CIVIL WORKS 1 CONTRACTOR TO HAUL AND CIVIL WORKS 1 CONTRACTOR TO HAUL AND CIVIL WORKS 1 CONTRACTOR TO HAUL AND WORKS 1 CONTRACTOR TO HAUL AND WORKS 1 CONTRACTOR TO HAUL AND 1 CONTRACTOR TO HAUL AND 1 CONTRACTOR TO HAUL AND CONTRACTOR TO HAUL AND CONTRACTOR TO HAUL AND TO HAUL AND TO HAUL AND HAUL AND HAUL AND AND AND LOAD, TWO CONTRACTORS CAN SWITCH ACCESS ROADS EACH OTHER.
1.5
1.5
1.5
1.5
1.5
1.5
A307/05/2021
PREPARED BY
NGƯỜI THỰC HIỆN:
CHECKED BY
NGƯỜI KIỂM TRA:
DIOXIN REMEDIATION AT BIEN HOA
AIRBASE AREA PROJECT - PHASE 1
DỰ ÁN XỬ LÝ Ô NHIỄM DIOXIN KHU VỰC
SÂN BAY BIÊN HÒA - GIAI ĐOẠN 1
AS NOTED
REV DESCRIPTION DATE BY
BẢN ĐIỀU CHỈNH NGÀY BỞI
PREPARED FOR
CHỦ ĐẦU TƯ:
LISBETH HABANS NAGRATH
DESIGNER OF RECORD
CHỦ NHIỆM THIẾT KẾ:
PROJECT NAME/ TÊN DỰ ÁN:
DRAWING TITLE/ TÊN BẢN VẼ:
DATE/ NGÀY: SIZE/ KHỔ: SCALE/ TỈ LỆ:
LE THI THANH THUY
PHAN THANH LUAN
SHEET
TỜ:
OF
CỦA:
Trigon Associates, llc1515 Poydras St., Ste 2200 New Orleans, LA 70112 www.trigonassociates.com
ENGINEERING • CONSULTING • MANAGEMENT
A&E BIEN HOA CONTRACTOR
NHÀ THẦU TV&TK BIÊN HÒA
DRAWING NO / BẢN VẼ SỐ:
CIVIL WORKS PHASE 1
CROSS SECTIONS
C100-003 03
11/05/2021
A C100-002
SECTION A
SCALE: 1-200
A C100-002
SECTION A CONTINUED
SCALE: 1-200
NOTE:
A C100-002
SECTION A CONTINUED
SCALE: 1-200
AutoCAD SHX Text
BERM
AutoCAD SHX Text i%%%
AutoCAD SHX Text
SOIL ANCHOR
AutoCAD SHX Text
BERM
AutoCAD SHX Text i%%%
AutoCAD SHX Text
BERM
AutoCAD SHX Text
SOIL ANCHOR
AutoCAD SHX Text NON-WOVEN GEOTEXTILE %%U>%%U 25kN/m
AutoCAD SHX Text
DOUBLE-SIDE TEXTURED HDPE LINER (1.5MM)
AutoCAD SHX Text
COMMON FILL 20CM THICK
AutoCAD SHX Text
GROUND LEVELLING
AutoCAD SHX Text NON-WOVEN GEOTEXTILE %%U>%%U 25kN/m
AutoCAD SHX Text
DOUBLE-SIDE TEXTURED HDPE LINER (1.5MM)
AutoCAD SHX Text
COMMON FILL 20CM THICK
AutoCAD SHX Text
GROUND LEVELLING
AutoCAD SHX Text
- ALL DIMENSIONS ARE IN CENTIMETER.
AutoCAD SHX Text NON-WOVEN GEOTEXTILE %%U>%%U 25kN/m
AutoCAD SHX Text
DOUBLE-SIDE TEXTURED HDPE LINER (1.5MM)
AutoCAD SHX Text
COMMON FILL 20CM THICK
GROUND LEVELLING
1.5 1
1.5
1.5
BERM
1.5
1.5
A307/05/2021
PREPARED BY
NGƯỜI THỰC HIỆN:
CHECKED BY
NGƯỜI KIỂM TRA:
DIOXIN REMEDIATION AT BIEN HOA
AIRBASE AREA PROJECT - PHASE 1
DỰ ÁN XỬ LÝ Ô NHIỄM DIOXIN KHU VỰC
SÂN BAY BIÊN HÒA - GIAI ĐOẠN 1
AS NOTED
REV DESCRIPTION DATE BY
BẢN ĐIỀU CHỈNH NGÀY BỞI
PREPARED FOR
CHỦ ĐẦU TƯ:
LISBETH HABANS NAGRATH
DESIGNER OF RECORD
CHỦ NHIỆM THIẾT KẾ:
PROJECT NAME/ TÊN DỰ ÁN:
DRAWING TITLE/ TÊN BẢN VẼ:
DATE/ NGÀY: SIZE/ KHỔ: SCALE/ TỈ LỆ:
LE THI THANH THUY
PHAN THANH LUAN
SHEET
TỜ:
OF
CỦA:
Trigon Associates, llc1515 Poydras St., Ste 2200 New Orleans, LA 70112 www.trigonassociates.com
ENGINEERING • CONSULTING • MANAGEMENT
A&E BIEN HOA CONTRACTOR
NHÀ THẦU TV&TK BIÊN HÒA
DRAWING NO / BẢN VẼ SỐ:
CIVIL WORKS PHASE 1
CROSS SECTIONS
C100-004 04
11/05/2021
B C100-002
SECTION B-B
SCALE: 1-30
C C100-002
SECTION C-C
SCALE: 1-200
NOTE:
AutoCAD SHX Text
SILT CURTAIN
AutoCAD SHX Text
SOIL ANCHOR
AutoCAD SHX Text
CONTAINMENT CURB
AutoCAD SHX Text
TURBIDITY CURTAIN WITH EXPANDED POLYSTYRENE (EPS) FOAM FOR FLOTATION
AutoCAD SHX Text
SKIMMER
AutoCAD SHX Text
SOIL ANCHOR
AutoCAD SHX Text
TO EAST PERIMETER DRAINAGE CHANNEL
AutoCAD SHX Text i %1%
AutoCAD SHX Text i %2%
AutoCAD SHX Text
DOUBLE-SIDE TEXTURED HDPE LINER (1.5MM)
AutoCAD SHX Text
COMMON FILL 20CM THICK
AutoCAD SHX Text
GROUND LEVELLING
AutoCAD SHX Text NON-WOVEN GEOTEXTILE %%U>%%U 25kN/m
AutoCAD SHX Text
HDPE 1.5MM THICK
AutoCAD SHX Text
COMPACTION OF EXCAVATED GROUND
AutoCAD SHX Text NON-WOVEN GEOTEXTILE %%U>%%U 25kN/m
AutoCAD SHX Text
DOUBLE-SIDE TEXTURED HDPE LINER (1.5MM)
AutoCAD SHX Text
COMMON FILL 20CM THICK
AutoCAD SHX Text
GROUND LEVELLING
- ALL DIMENSIONS ARE IN CENTIMETER.