This document contains a solicitation for a firm-fixed-price contract to provide treatment services for dioxin remediation at Bien Hoa Airbase Area in Vietnam. USAID/Vietnam seeks to award a contract between $50-80 million for a period of up to 5 years. Prime contractors must be registered under NAICS code 562910 for remediation services with a business size of $22 million and be eligible under geographic code 937. The solicitation was issued on July 1, 2021 with questions due by July 12th. A virtual pre-proposal conference and site visit will be held the week of July 19th. Proposals are due by August 19, 2021. The scope of work includes design, construction, operation, and sampling services for treatment plants, vapor and wastewater systems, storage areas and related site work. Pricing is on a firm-fixed-price basis using CLIN line items.

View the file

Other files

File Type Posted
20210920 Revised No. 3 RFP_72044021R00002 USAID Treatment Phase 1 for Dioxin Remediation at Bien Hoa Airbase Area.pdf PDF
SF 30 Amendment No. 4 to RFP No. 72044021R00002 for USAID Treatment – Phase 1 for Dioxin Remediation at Bien Hoa Airbase Area.pdf PDF
20210920 ATTACHMENT J.13 PRICE PROPOSAL FORM (REVISION No.2).xlsx XLSX spreadsheet
Amendment No. 3 to RFP No. 72044021R00002 for USAID Treatment – Phase 1 for Dioxin Remediation at Bien Hoa Airbase Area.pdf PDF
20210827 Revised 2 RFP_72044021R00002 USAID Treatment - Phase 1 for Dioxin Remediation at Bien Hoa Airbase Area.pdf PDF
20210811 Treatment Phase 1 Virtual Conference RFP72044021R00002.pdf PDF
SF 30 Amendment No. 2 to RFP No. 72044021R00002 for USAID Treatment – Phase 1 for Dioxin Remediation at Bien Hoa Airbase Area.pdf PDF
20210723 Revised No.1_RFP_72044021R00002 USAID Treatment – Phase 1 for Dioxin Remediation at Bien Hoa Airbase Area.pdf PDF
Figure_6. Existing_Site_Surface_Condition.jpg JPG image
20210723 Amendment No.1_RFP No. 72044021R00002 for USAID Treatment – Phase 1 for Dioxin Remediation at Bien Hoa Airbase Area.pdf PDF
Section C_Figure_4_TCH_Treatment_Plant_Site_Layout.jpg JPG image
J.10-SITE-WIDE HEALTH AND SAFETY PLAN.pdf PDF
J.2-COMPENDIUM.pdf PDF
J.5 - BIEN HOA THERMAL STUDY FINAL REPORT (KEMRON).pdf PDF
J.11-SITE-WIDE HEALTH AND SAFETY PLAN SIGN OFF PAGE.docx DOCX document
J.1- ENVIRONEMENTAL ASSESSMENT (EA) BH 2016-05-03_EN.pdf PDF
J.4 - SITE LAYOUT AND PRE-TREATMENT STORAGE AREA (PTSA) PRELIMINARY_DESIGN.pdf PDF
20210701_RFP_72044021R00002_USAID_Treatment_Phase 1 for Dioxin Remediation at Bien Hoa Airbase Area.pdf PDF
J.6-TREATMENT AREA DRAINAGE PLAN v.3.pdf PDF
J.3 - ENVIRONMENTAL IMPACT ASSESSMENT (EIA).pdf PDF
J.12-BRANDING IMPLEMENTATION PLAN AND MARKING PLAN.pdf PDF
Section C_Figure 5_Drainage Plan.jpg JPG image
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Form 1

USAID/VIETNAM TREATMENT FOR DIOXIN REMEDIATION AT THE BIEN HOA AIRBASE AREA – PHASE I
ATTACHMENT J.2 BID FORM
CLINBid Item No.Bid Item DescriptionUnitsQuantityUnit PriceTotal Amount
11.00 GENERAL$ -
1.00.01Project PlansLS1$ -
1.00.02Project Management and SupportLS1$ -
Payment and Performance BondsLS1$ -
1.10 DESIGN (CLIN1)$ -
1.10.0110% DesignLS1$ -
1.10.0230% DesignLS1$ -
1.10.0360% DesignLS1$ -
1.10.0490% DesignLS1$ -
1.10.05Final DesignLS1$ -
CLIN 1 SUBTOTAL$ -
22.00 GENERAL$ -
2.00.01Mobilization and Demobilization - Construction Stage and Operation StageLS1$ -
2.00.02Environmental MitigationLS1$ -
2.00.03Health and Safety, Including PPE and Blood MonitoringLS1$ -
2.00.04Traffic ControlLS1$ -
2.00.05DecontaminationLS1$ -
2.00.06Project Management and SupportLS1$ -
Payment and Performance BondsLS1$ -
2.10 CONSTRUCTION$ -
2.10.01Field Logistics and Site PreparationLS1$ -
2.10.02Security FenceLS1$ -
2.10.03Site OfficeLS1$ -
2.10.04Treatment Plant(s)LS1$ -
2.10.05Vapor Treatment SystemLS1$ -
2.10.06Wastewater Treatment System, Including Water Service ConnectionsLS1$ -
2.10.07Electrical ServiceLS1$ -
2.10.08Treated Material Storage Area (TMSA)LS1$ -
2.20 OPERATION$ -
2.20.01Hauling Contaminated Material from Pre-Treatment Storage Area to Treatment Plant - 1st Treatment CycleLS1$ -
2.20.02Treatment of Contaminated Material - 1st Treatment CycleLS1$ -
2.20.03Hauling Clean Material from Treatment Plant(s) to TMSA - 1st Treatment CycleLS1$ -
2.20.04Sampling - 1st Treatment CycleLS1$ -
2.20.05Hauling Contaminated Material from Pre-Treatment Storage Area to Treatment Plant - 2nd Treatment CycleLS1$ -
2.20.06Treatment of Contaminated Material - 2nd Treatment CycleLS1$ -
2.20.07Hauling Clean Material from Treatment Plant(s) to TMSA - 2nd Treatment CycleLS1$ -
2.20.08Sampling - 2nd Treatment CycleLS1$ -
CLIN 2 SUBTOTAL$ -
2.30 TOTAL DAY WORKS
2.30.01Total Day Works - The CONTRACTOR is not entitled to any part of the Day Work item, either partially or fully, unless specifically authorized by USAID--$500,000$500,000
TOTAL BASE BID (CLIN 1 SUBTOTAL + CLIN 2 SUBTOTAL + TOTAL DAY WORKS)$ 500,000