ITB FP-2022-03 Addendum No. 2 Final.pdf

PDF 384 KB Posted

Attached to
FP-2022-03 West Steam Distribution main Replacement
Solicitation number
S-580100-00015853
Issued by
Umatilla County, Oregon

About this file

This is Addendum No. 2 to Invitation to Bid (ITB) FP-2022-03 issued by Eastern Oregon University for the West Steam Distribution Main Replacement project, prepared by Systems West Engineers, Inc. The addendum, dated February 16, 2026, modifies the original bidding documents dated January 23, 2026, and addresses specifications for underground HVAC piping systems. Key modifications include added expansion compensation design requirements, a change in approved Perma-Pipe product, addition of Rovanco as an approved manufacturer, and clarification of carrier pipe insulation type and thickness. The addendum clarifies that expansion loops may be direct-buried provided that expansion compensation is designed by the piping system manufacturer in accordance with Section 23 21 10 1.02.B. A mandatory pre-bid conference was held on February 10, 2025, at 10:00 AM, with 17 prospective bidders from regional mechanical, plumbing, and construction firms attending and becoming eligible to submit bids. The addendum requires all bidders to acknowledge receipt of the document on their bid forms to avoid disqualification.

The technical specifications outlined in the addendum establish performance requirements for high-pressure steam piping rated at 125 psig at 365°F and pumped condensate piping rated at 100 psig at 250°F. Pre-engineered conduit piping systems must comply with ASME standards, specifically ASME B31.9 for Building Services Piping, with approved manufacturers including Perma Pipe (ESCON A Ferro Shield Multi-Therm), Thermacor (Duo-Therm 505), and Rovanco (Insul-800). Shop drawings must be signed and sealed by a professional engineer and include detailed design layouts, pipe stress calculations using finite element analysis, and demonstration that pipe stresses remain within allowable requirements. Carrier pipe insulation specifications include aerogel materials with a maximum k-value of 0.16 Btu-in/hr-ft²-F at 75°F mean temperature and a maximum working temperature of 1200°F. All welding must comply with ASME Boiler and Pressure Vessel Code Section IX, with current AWS certification required for all welders performing work on the project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

725 A Street Springfield, OR 97477 | 550 NW Franklin Blvd., Suite 448 Bend, OR 97703

SystemsWestEngineers.com (541) 342-7210

Addendum No. 2, Y006.03, EOU Project Number FP-2022-03 1

ADDENDUM NO. 2

Y006.03

EOU Project Number FP-2022-03

From: Systems West Engineers, Inc.

725 A Street

Springfield, OR 97477

To: All Plan Holders of Record

Project: Eastern Oregon University West Steam Main Distribution Replacement

Date: February 16, 2026

This addendum forms a part of the Contract Documents and modifies the original Bidding Documents dated January 23, 2026 as noted below. Acknowledge receipt of this addendum in the space provided on the Bid Form. Failure to do so may subject the Bidder to disqualification.

General

Pre-Bid Conference Attendance List: Attached

Specifications

Section #23 21 10 – Underground HVAC Piping

Added expansion compensation design requirements.

Changed Perma-Pipe product.

Added Rovanco as a manufacturer.

Clarified carrier pipe insulation type and thickness.

Approvals

Manufacturers listed below are approved based on data submitted. Approvals do not alter responsibility for conformance with Contract Documents.

Section Approved Manufacturer

23 21 10 Rovanco https://www.systemswestengineers.com/

Addendum No. 2, Y006.03, EOU Project Number FP-2022-03 2

Questions:

Are the expansion loops intended to be located within a vault or installed as part of the direct-buried piping system? It has been asserted that expansion loops cannot be direct-buried.

a. Expansion loops may be direct-buried, but expansion compensation must be designed by the piping system manufacturer. Refer to section 23 21 10 1.02.B.

END OF ADDENDUM NO. 2

Nate Jenkins

NJJ\ejp

Enclosures: Pre-bid Conference Attendance List

Section 23 21 10

WEST STEAM DISTRIBUTION MAIN REPLACEMENT PROJECT

EASTERN OREGON UNIVERSITY

Mandatory Pre-Bid Conference • February 10, 2025, 10:00 AM

Only the Prospective Bidders on this List are eligible to submit Bids for this Project. Other Bidders are considered Non-Responsive

No. Name Representing/Title Location (City, State) Phone Email

1 John Garlitz EOU La Grande, OR 541-805-0807 jgarlitz@eou.edu

2 Brent Gyllenberg Gyllenberg Construction Baker City, OR 541-523-5000 gyllcons@eoni.com

3 Travis Dever MPP Piping Scio, OR 541-817-2312 travis.dever@mpppiping.com

4 Doug Parazoo MPP Piping Scio, OR 503-932-9671 doug.parazoo@mpppiping.com

5 Eli Childs R6 Contracting Union, OR 541-910-9211 eli@r6contracting.com

6 Lanee Lehne S2 Industrial Marcola, OR 541-632-02127 llehne@s2industrial.com

7 Nate Rudder Granite Construction Hermiston, OR 509-975-1551 nathan.rudder@gcinc.com

8 Maime Lipe Apex Mechanical Battle Ground, WA 360-666-8735 estimating@apexmechanical.org

9 Aaron Romer All Phase Electrical La Grande, OR 541-963-3000 allphase_electrical@frontier.com

10 Joe Anderson Walter Plumbing La Grande, OR 541-975-1234 walter.plumbing@live.com

11 Craig Walter Walter Plumbing La Grande, OR 541-975-1234 walter.plumbing@live.com

12 Tanner Jarvis Jarvis Mechanical La Grande, OR 541-480-5993 tanner@jarvismech.com

13 Jarod Teeter MBGC La Grande, OR 541-910-0887 jteeter@mikebeckergc.com

14 Matt Majino ES Constant Troutdale, OR 971-712-3306 matthew@esconstant.com

15 Ron Rieman Boyter Brothers Vancouver, WA 360-844-0591 ron@boyterbrothers.com

16 John Tapani JRT Mechanical Battle Ground, WA 360-666-0330 johnT@JRTmechanical.com

17 Darrell Johnson S2 Industrial Marcola, OR 541-915-7350 djohnson@s2industrial.com

West Steam Distribution Main Replacement EOU Project Number FP-2022-03 January 23February 163, 2026 – ADDENDUM 2

Section 23 21 10

UNDERGROUND HVAC PIPING

Eastern Oregon University Facilities & Planning Department Y006.03

SECTION 23 21 10

UNDERGROUND HVAC PIPING

PART 1 - GENERAL

1.01 SUMMARY

A. Section Includes:

1. Pre-engineered conduit piping.

1.02 ACTION SUBMITTALS

A. Product Data: For the following:

1. Pre-engineered conduit piping system components.

B. Shop Drawings: For underground steam and condensate piping. Signed and sealed by a professional engineer.

1. Submitted detailed design layout drawings including pipe sizes, locations, elevations showing all anchors and guides. Layout drawings shall also include all analysis node points.

2. Show details and sections of piping in trench, conduit, and cased pipe with clearances between piping, and show insulation thickness.

3. Calculate requirements for expansion compensation for underground piping. Calculate pipe stress and system expansion for each expansion compensation elbow using a finite element computer generated three-dimensional analysis. Calculations, including heat loss calculations, shall demonstrate that pipe stresses from temperature changes are within the allowable requirements in ASME B31.1 and the anchors and the guides will withstand the resultant forces. The computer analysis results shall include node stresses, forces, moments and displacements.

4. Show expansion compensators, offsets, and loops with appropriate materials to allow piping movement in the required locations. Show anchors and guides that restrain piping movement with calculated loads and show concrete thrust block dimensions.

5. Coordinate required anchor locations as determined in design with those shown on construction documents.

5.6. Expansion shall not be compensated for through cold-springing of the system during installation.

1.03 INFORMATIONAL SUBMITTALS

A. Qualifications Date: For qualified installer

B. Welding certificates.

C. Material Test Reports.

D. Field quality control reports.

E. Survey report of installed piping slope.

1.04 QUALITY ASSURANCE

January 23February 163, 2026 – ADDENDUM 2

Section 23 21 10

A. Welding Qualifications: Qualify procedures and personnel according to ASME Boiler and Pressure Vessel Code: Section IX.

1. Comply with provisions in ASME B31.9, "Building Services Piping."

2. Certify that each welder has passed AWS qualification tests for welding processes involved and that certification is current.

B. ASME Compliance: Comply with ASME B31.9, "Building Services Piping," for materials, products, and installation.

C. Manufacturer installer certifications where required for product warranty.

PART 2 - PRODUCTS

2.01 PERFORMANCE REQUIREMENTS

A. Provide components and installation capable of producing piping systems with the following minimum working-pressure ratings:

1. High Pressure Steam Piping: 125 psig at 365°F.

2. Pumped Condensate Piping: 100 psig at 250°F.

2.02 STEEL PIPES AND FITTINGS

A. Steel Pipe: Steel Pipe: ASTM A 53/A 53M, black with plain ends; type, grade, and wall thickness as indicated in "Piping Application" Article.

B. Cast-Iron, Threaded Fittings: ASME B16.4; Class 125.

C. Malleable-Iron, Threaded Fittings: ASME B16.3, Class 150

D. Malleable-Iron Unions: ASME B16.39; Class 150.

E. Wrought-Steel Fittings: ASTM A 234/A 234M, wall thickness to match adjoining pipe.

1. Material Group: 1:1.

2. End Connections: Butt welding.

3. Facings: Raised face.

F. Steel Welding Fittings: ASME B16.9, seamless or welded.

1. Welding Filler Metals: Comply with AWS D10.12M/D10.12 for welding materials appropriate for wall thickness and chemical analysis of steel pipe being welded.

G. Nipples: ASTM A 733, made of same materials and wall thicknesses as pipe in which they are installed.

H. Pipe-Flange Gasket Materials: Suitable for chemical and thermal conditions of piping system contents.

1. ASME B16.21, nonmetallic, flat, asbestos free, 1/8-inch maximum thickness unless thickness or specific material is indicated.

a. Full-Face Type: For flat-face, Class 125, cast-iron and -bronze flanges.

b. Narrow-Face Type: For raised-face, Class 250, cast-iron and steel flanges.

I. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise indicated.

2.03 PRE-ENGINEERED CONDUIT PIPING SYSTEM

January 23February 163, 2026 – ADDENDUM 2

Section 23 21 10

A. Description: Factory-fabricated and -assembled, airtight and watertight, drainable, pressure-tested piping with conduit, inner pipe supports, and insulated carrier piping.

Fabricate so insulation can be dried in place by forcing dry air through conduit.

1. Manufacturers: Subject to compliance with requirements, provide one of the following products:

a. Perma Pipe, Inc. ESCON A Ferro Shield Multi-Therm

b. Thermacor Duo-Therm 505 b.c. Rovanco Insul-800

B. Carrier Pipe: Schedule 40 steel pipe and fittings, STM A-53, Grade B, ERW. Schedule 80 steel where indicated in "Piping Application" Article.

C. Carrier Pipe Insulation:

1. Aerogel

a. Max Working Temperature: 1200°F

b. Materials: Flexible blanket, maximum k-value of 0.16 Btu-in/hr-ft2-°F at 75°F mean temperature, hydrophobic (water absorption <6% by volume). Comply with

ASTM C1728.

c. Thickness:

1) 8”ø MPS: 1.18” (3 layers of 10mm)

2) 2-1/2”ø PR: 1.18” (3 layers of 10mm)

C.D. OuterCarrier Pipe Insulation:

1. Polyurethane Foam Pipe Insulation: Unfaced, preformed, rigid cellular polyurethane material intended for use as thermal insulation.

a. Minimum thickness of 1”

b. Insulation shall be rigid, 90% closed cell polyurethane with a minimum 2.4 lbs. per cubic foot density, and a compressive strength of 30 psi @ 75°F.

c. Comply with ASTM C591, Type I or Type IV, except thermal conductivity (k-value) shall not exceed 0.16 Btu x in./h x sq. ft. x deg F at 75 deg F after 180 days of aging.

d. Fabricate shapes in accordance with ASTM C450 and ASTM C585.

e. The insulation shall have a bare copper wire embedded into the system between the steel casing and the HDPE jacket. The wire shall be monitored by an alarm panel which measures resistance between the carrier pipe and the steel casing.

The panel shall be capable of alarming in the event of low resistance.

D.E. Conduit: 10-gauge, welded, smooth-wall black steel conforming to ASTM A-211, A-139, A- 134, and A-135 spiral wound steel.

1. Cover: With polyurethane foam insulation with an HDPE jacket.

2. Piping Supports within Conduit: Corrugated galvanized steel with a maximum spacing if 10 feet.

3. Fittings: Factory-fabricated and -insulated elbows and tees. Elbows may be bent pipe equal to carrier pipe. Tees shall be factory fabricated and insulated and shall be compatible with the carrier pipe.

4. Expansion Offsets and Loops: Size casing to contain piping expansion.

5. Accessories include the following:

a. Guides and Anchors: Steel plate welded to carrier pipes and to casing, complete with vent and drainage openings inside casing.

b. End Seals: Steel plate welded to carrier pipes and to casing, complete with drain and vent openings on vertical centerline.

c. Gland Seals: Packed stuffing box and gland follower mounted on steel plate, welded to end of casing, permitting axial movement of carrier piping, with drain and vent connections on vertical centerline.

d. Pressure Testable Joint Closure: On straight run joints.

January 23February 163, 2026 – ADDENDUM 2

Section 23 21 10

e. Conduit fittings: Factory pre-fabricated, pre-insulated, and jacketed with a molded, extrusion welded, or butt fusion welded PE jacket.

E.F. Jacket:

1. High density polyethylene (HDPE): Extruded, black, having a minimum wall thickness of 200 mils.

a. The inner surface of the HPDE jacket shall be oxidized by means of corona treatment of flame treatment to ensure a secure bond between the jacket and foam insulation preventing any ingression of water at the jacket/foam interface.

F.G. Leak Detection Panel:

1. Alarm panel monitoring copper wire which measures resistance between the carrier pipe and the steel casing. The panel shall be capable of alarming in the event of low resistance and reporting out to Building Automation System.

G.H. Source Quality Control: Factory test conduit and carrier pipe as indicated in Part 3.

PART 3 - EXECUTION

3.01 EARTHWORK

A. See Division 31 for excavation, trenching, and backfilling.

B. Underground systems shall be buried in a trench not less than two feet deeper than the top of the pipe and not less than eighteen inches wider than the combined O.D. of all piping systems. A minimum thickness of 24 inches of compacted backfill placed over the top of the pipe will meet H-20 highway loading.

C. Trench bottom shall have a minimum of 6 inches of sand, pea gravel, or specified backfill as a cushion for the piping. All field cutting of the pipe shall be performed in accordance with the manufacturer’s installation instructions.

3.02 PIPING APPLICATION

A. High Pressure Steam Piping:

1. 2-1/2-inch and larger shall be one of the following:

a. Schedule 40 steel carrier pipe in a pre-engineered conduit piping system.

B. Pumped Condensate Piping:

1. 2-1/2-inch and larger shall be one of the following:

a. Schedule 80 steel carrier pipe in a pre-engineered conduit piping system.

3.03 PIPING INSTALLATION

A. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping systems. Indicate piping locations and arrangements if such were used to size pipe and calculate friction loss, expansion, pump sizing, and other design considerations. Install piping as indicated unless deviations to layout are approved on Coordination Drawings.

B. Remove standing water in the bottom of trench.

C. Do not backfill piping trench until field quality control testing, pipe slope survey, and Manufacturer’s Field Service have been completed and results approved.

January 23February 163, 2026 – ADDENDUM 2

Section 23 21 10

D. Install piping with slope as indicated in Civil plans.

E. In conduits, install drain valves at low points and manual air vents at high points.

F. Install components with pressure rating equal to, or greater than, system operating pressure.

G. Install piping free of sags and bends.

H. Install fittings for changes in direction and branch connections.

I. See Section 23 05 17 – Sleeves and Sleeve Seals for HVAC Piping, for sleeves and mechanical sleeve seals through exterior building walls.

J. Secure anchors and fittings where piping changes direction, and where elsewhere required by manufacturer’s written installation instructions, with concrete thrust blocks. Apply bitumastic coating to carbon-steel anchors and guides. Pour concrete thrust blocks and anchors.

3.04 JOINT CONSTRUCTION

A. Ream ends of pipes and tubes, and remove burrs. Bevel plain ends of steel pipe.

B. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before assembly.

C. Welded Joints: Construct joints according to AWS D10.12M/D10.12, using qualified processes and welding operators according to “Quality Assurance” Article.

D. Flanged Joints: Select appropriate gasket material, size, type, and thickness for service application. Install gasket concentrically positioned. Use suitable lubricants in bolt threads.

E. Conduit and Cased Piping Joints: Assemble sections and finish joints with pourable or split insulation and exterior jacket sleeve and apply shrink-wrap seals.

3.05 IDENTIFICATION

A. Install continuous plastic underground warning tapes during back filling of trenches for underground steam and condensate piping. Locate tapes 6 to 8 inches below finished grade, directly over piping. See Division 31 for warning tape materials and devices and their installation.

3.06 FIELD QUALITY CONTROL

A. Testing Agency: Engage a qualified testing agency to perform tests and inspections.

B. Manufacturer’s Field Service: Engage a factory-authorized service representative to inspect, test, and adjust components, assemblies, and equipment installations, including connections. Arrange for Manufacturer representatives to perform site visits at the following milestones:

1. At time of material delivery.

2. Prior to joint closure installation for installed piping inspection.

3. After system is fully installed and in service to review alarm panel and monitoring system.

January 23February 163, 2026 – ADDENDUM 2

Section 23 21 10

C. Tests and Inspections:

1. Prepare steam and condensate piping for testing according to ASME B31.9 and as follows

a. Leave joints, including welds, uninsulated and exposed for examination during test.

b. Fill system with water. Where there is a risk of freezing, air or a safe, compatible liquid may be used.

c. Use vents installed at high points to release trapped air while filling system.

2. Test steam and condensate piping as follows:

a. Subject steam and condensate piping to hydrostatic test pressure that is not less than 1.5 times the design pressure.

b. After hydrostatic test pressure has been applied for 10 minutes, examine joints for leakage. Remake leaking joints using new materials and repeat hydrostatic test until no leaks exist.

3. Test conduit as follows:

a. Seal vents and drains and subject conduit to 15 psig for 4 hours with no loss of pressure. Repair leaks and retest as required.

4. Engage surveyor to measure installed site steam piping slope prior to backfill/cover.

D. Prepare test and inspection reports, including survey of installed piping slope.

END OF SECTION