ITB_27-01_DRAFT_AGREEMENT.pdf

PDF 2 MB Posted

Attached to
Polk Street Community Center Parking Lot Renovation Project
Solicitation number
27-01
Issued by
Bay County, Florida

About this file

This is a Draft Agreement document for construction services between Gadsden County Board of County Commissioners (Owner) and an unnamed Contractor for pedestrian improvements along CR 12 (5th Avenue). The project encompasses 649 square yards of 4-inch concrete sidewalk, 315 linear feet of concrete gravity wall (49 cubic yards of concrete), 315 linear feet of aluminum pipe handrail, and 73 square feet of detectable warnings. The work is designed by Alday-Howell Engineering, Inc., with the same firm serving as the Construction Engineering Inspector (CEI). Substantial Completion is required within 95 days of the Notice to Proceed, with final completion and readiness for payment within 110 days. The Contract includes both lump sum and unit price components, with unit price work covering roadway components (mobilization, maintenance of traffic, sediment barrier, clearing and grubbing, excavation, concrete gravity wall, pipe handrail, sidewalk concrete, detectable warnings, and performance turf) and signing and pavement marking components (single column ground sign relocation and thermoplastic markings). Progress payments are due on or about the 20th of each month at 90 percent of work completed, with retainage of 10 percent until Substantial Completion.

Liquidated damages are assessed at $1,000 per day for failure to achieve Substantial Completion and $500 per day for failure to complete remaining work after Substantial Completion. The Contract Price is indicated as redacted (shown as "xxxxxxx" in the document), with final amounts subject to adjustment based on actual unit price quantities determined by the Engineer. Upon Substantial Completion, the Owner shall pay 100 percent of work completed less retainage and 200 percent of the Engineer's estimate of remaining work value. The Contractor must provide Performance and Payment Bonds, with the Performance Bond requiring the Surety to arrange completion, undertake performance directly, obtain alternative bids, or make payment for damages if a Contractor Default is declared. Interest on unpaid amounts accrues at the maximum legal rate. The Agreement is based on the EJCDC C-520 (2013 Edition) standard form and includes comprehensive General Conditions governing site access, subsurface conditions, insurance requirements, contractor responsibilities, change orders, and dispute resolution procedures.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EJCDC® C-520, Agreement Between Owner and Contractor for Construction Contract (Stipulated Price).

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 1 of 8

AGREEMENT

BETWEEN OWNER AND CONTRACTOR

FOR CONSTRUCTION CONTRACT (STIPULATED PRICE)

THIS AGREEMENT is by and between Gadsden County BOCC (“Owner”) and

(“Contractor”).

Owner and Contractor hereby agree as follows:

ARTICLE 1 – WORK

1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows: pedestrian sidewalk improvements along CR 12 (5th Ave) and will include 649 square yards of 4” concrete sidewalk, 315 linear feet of concrete gravity wall (49 cubic yards of concrete), 315 linear feet of aluminum pipe handrail, and 73 square feet of detectable warnings.

ARTICLE 2 – THE PROJECT

2.01 The Project, of which the Work under the Contract Documents is a part, is generally described as follows: CR 12 (5TH Ave) – Pedestrian Improvements

ARTICLE 3 – ENGINEER

3.01 The Project has been designed by _Alday-Howell Engineering, Inc._(EOR – Seddon Gay)_.

3.02 The Owner has retained Alday-Howell Engineering, Inc. (CEI)_ (“Engineer”) to act as Owner’s representative, assume all duties and responsibilities, and have the rights and authority assigned to Engineer in the Contract Documents in connection with the completion of the Work in accordance with the Contract Documents.

ARTICLE 4 – CONTRACT TIMES

4.01 Time of the Essence

A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.

4.02 Contract Times: Days

A. The Work will be substantially completed within 95 days after the date when the Contract Times commence to run as provided in Paragraph 4.01 of the General Conditions, and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions within 110 days after the date when the Contract Times commence to run.

4.03 Liquidated Damages

A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones not achieved within the times specified in Paragraph 4.02 above, plus any extensions thereof allowed in accordance with the Contract. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or arbitration proceeding the

ITB 27-01 CR12 5th Ave Pedestrian Improvements Attachment B Draft Agreement

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 2 of 8 actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty):

1. Substantial Completion: Contractor shall pay Owner $_1,000_ for each day that expires after the time (as duly adjusted pursuant to the Contract) specified in Paragraph 4.02.A above for Substantial Completion until the Work is substantially complete.

2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Time (as duly adjusted pursuant to the Contract) for completion and readiness for final payment, Contractor shall pay Owner $_500__ for each day that expires after such time until the Work is completed and ready for final payment.

3. Liquidated damages for failing to timely attain Substantial Completion and final completion are not additive and will not be imposed concurrently.

ARTICLE 5 – CONTRACT PRICE

5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents the amounts that follow, subject to adjustment under the Contract:

A. For all Work other than Unit Price Work, a lump sum of: $_xxxxxxx_.

All specific cash allowances are included in the above price in accordance with Paragraph

13.02 of the General Conditions.

B. For all Unit Price Work, an amount equal to the sum of the extended prices (established for each separately identified item of Unit Price Work by multiplying the unit price times the actual quantity of that item):

Unit Price Work – Roadway Component

Item No.

Description Unit Estimated Quantity

Unit Price

Extended Price

0101-1 MOBILIZATION LS 1

0102-1 MAINTENANCE OF TRAFFIC LS 1

0104-10-3 SEDIMENT BARRIER LF 1213

0110-1-1 CLEARING AND GRUBBING AC 0.31

0120-1 REGULAR EXCAVATION CY 85.1

0120-2-2 BORROW EXCAVATION, TRUCK

MEASURE CY 31.8

0400-0-11 CONCRETE CLASS NS, GRAVITY WALL,

INDEX 400-011 CY 49

0515-1-2 PIPE HANDRAIL – GUIDERAIL,

ALUMINUM LF 315

0522-1 SIDEWALK CONCRETE AND DRIVEWAYS,

4” THICK SY 649

0527-2 DETECTABLE WARNINGS SF 73

0570-1-2 PERFORMANCE TURF, SOD SY 821

ROADWAY COMPONENTS SUB-TOTAL OF ALL UNIT PRICE BID ITEMS

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 3 of 8

Unit Price Work – Signing & Pavement Marking Component

Item No.

Description Unit Estimated Quantity

Unit Price

Extended Price

0700-1-500 SINGLE COLUMN GROUND SIGN

ASSEMBLY, RELOCATE EA 3

0711-11-123

THERMOPLASTIC, STANDARD, WHITE,

SOLID, 12” FOR CROSSWALK AND

ROUNDABOUT

LF 96

SIGNING & PAVEMENT MARKING COMPONENTS SUB-TOTAL OF ALL UNIT

PRICE BID ITEMS

The extended prices for Unit Price Work set forth as of the Effective Date of the Contract are based on estimated quantities. As provided in Paragraph 13.03 of the General Conditions, estimated quantities are not guaranteed, and determinations of actual quantities and classifications are to be made by Engineer.

C. Total of Lump Sum Amount and Unit Price Work (subject to final Unit Price adjustment) $_xxxxx_.

D. For all Work, at the prices stated in Contractor’s Bid, attached hereto as an exhibit.

ARTICLE 6 – PAYMENT PROCEDURES

6.01 Submittal and Processing of Payments

A. Contractor shall submit Applications for Payment in accordance with Article 15 of the General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions.

6.02 Progress Payments; Retainage

A. Owner shall make progress payments on account of the Contract Price on the basis of Contractor’s Applications for Payment on or about the __20th___ day of each month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values established as provided in the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract.

1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not limited to liquidated damages, in accordance with the Contract

a. __90___ percent of Work completed (with the balance being retainage).

Total of all Extended Prices for Unit Price Work (subject to final adjustment on actual quantities)

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 4 of 8

b. __90___ percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage).

B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to _100_ percent of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less _200_ percent of Engineer’s estimate of the value of Work to be completed or corrected as shown on the punch list of items to be completed or corrected prior to final payment.

6.03 Final Payment

A. Upon final completion and acceptance of the Work in accordance with Paragraph 15.06 of the General Conditions, Owner shall pay the remainder of the Contract Price as recommended by Engineer as provided in said Paragraph 15.06.

ARTICLE 7 – INTEREST

7.01 All amounts not paid when due shall bear interest at the maximum legal rate.

ARTICLE 8 – CONTRACTOR’S REPRESENTATIONS

8.01 In order to induce Owner to enter into this Contract, Contractor makes the following representations:

A. Contractor has examined and carefully studied the Contract Documents, and any data and reference items identified in the Contract Documents.

B. Contractor has visited the Site, conducted a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

C. Contractor is familiar with and is satisfied as to all Laws and Regulations that may affect cost, progress, and performance of the Work.

D. Contractor has considered the information known to Contractor itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and the Site-related reports and drawings identified in the Contract Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor; and (3) Contractor’s safety precautions and programs.

E. Based on the information and observations referred to in the preceding paragraph, Contractor agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.

F. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents.

G. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

H. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 5 of 8

I. Contractor’s entry into this Contract constitutes an incontrovertible representation by Contractor that without exception all prices in the Agreement are premised upon performing and furnishing the Work required by the Contract Documents.

ARTICLE 9 – CONTRACT DOCUMENTS

9.01 Contents

A. The Contract Documents consist of the following:

1. This Agreement (pages 1 to __, inclusive).

2. Performance bond (pages _1_ to __, inclusive).

3. Payment bond (pages _1_ to __, inclusive).

4. Other bonds.

a. ___ (pages ___ to ___, inclusive).

5. General Conditions (pages _1_ to __, inclusive).

6. Supplementary Conditions (pages _1_ to __, inclusive).

7. Specifications as listed in the table of contents of the Project Manual.

8. Drawings (not attached but incorporated by reference) consisting of __ sheets with each sheet bearing the following general title: ___ [or] the Drawings listed on the attached sheet index.

9. Addenda (numbers ___ to ___, inclusive).

10. Exhibits to this Agreement (enumerated as follows):

a. Contractor’s Bid (pages ___ to ___, inclusive).

NOTE(S) TO USER:

1. As noted in the introduction to this Agreement, in the typical case bidding-related documents such as the Instructions to Bidders and Bid are not included as Contract Documents. Include Contractor’s Bid as a Contract Document here only as a matter of necessity, for example if the Bid contains numerous line items and their prices, and rekeying such information would be burdensome and susceptible to error.

2. List other required attachments (if any), such as documentation submitted by Contractor prior to Notice of Award and documents required by funding or lending agencies.

11. The following which may be delivered or issued on or after the Effective Date of the Contract and are not attached hereto:

a. Notice to Proceed.

b. Work Change Directives.

c. Change Orders.

d. Field Orders.

B. The documents listed in Paragraph 9.01.A are attached to this Agreement (except as expressly noted otherwise above).

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 6 of 8

C. There are no Contract Documents other than those listed above in this Article 9.

D. The Contract Documents may only be amended, modified, or supplemented as provided in the General Conditions.

ARTICLE 10 – MISCELLANEOUS

10.01 Terms

A. Terms used in this Agreement will have the meanings stated in the General Conditions and the Supplementary Conditions.

10.02 Assignment of Contract

A. Unless expressly agreed to elsewhere in the Contract, no assignment by a party hereto of any rights under or interests in the Contract will be binding on another party hereto without the written consent of the party sought to be bound; and, specifically but without limitation, money that may become due and money that is due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment, no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents.

10.03 Successors and Assigns

A. Owner and Contractor each binds itself, its successors, assigns, and legal representatives to the other party hereto, its successors, assigns, and legal representatives in respect to all covenants, agreements, and obligations contained in the Contract Documents.

10.04 Severability

A. Any provision or part of the Contract Documents held to be void or unenforceable under any Law or Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon Owner and Contractor, who agree that the Contract Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision.

10.05 Contractor’s Certifications

A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph 10.05:

1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process or in the Contract execution;

2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of Owner, (b) to establish Bid or Contract prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;

3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non-competitive levels; and

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 7 of 8

4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

10.06 Other Provisions

A. Owner stipulates that if the General Conditions that are made a part of this Contract are based on EJCDC® C-700, Standard General Conditions for the Construction Contract, published by the Engineers Joint Contract Documents Committee®, and if Owner is the party that has furnished said General Conditions, then Owner has plainly shown all modifications to the standard wording of such published document to the Contractor, through a process such as highlighting or “track changes” (redline/strikeout), or in the Supplementary Conditions.

IN WITNESS WHEREOF, Owner and Contractor have signed this Agreement.

This Agreement will be effective on __________ (which is the Effective Date of the Contract).

OWNER: CONTRACTOR:

By: By:

Title: Title:

(If Contractor is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.)

Attest: Attest:

Title: Title:

Address for giving notices: Address for giving notices:

License No.:

(where applicable)

(If Owner is a corporation, attach evidence of authority to sign. If Owner is a public body, attach evidence of authority to sign and resolution or other documents authorizing execution of this Agreement.)

NOTE TO USER: Use in those states or other jurisdictions where applicable or required.

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 8 of 8

ITB 27-01 CR12 5th Ave Pedestrian Improvements

EJCDC® C-550, Notice to Proceed.

Prepared and published 2013 by the Engineers Joint Contract Documents Committee.

NOTICE TO PROCEED

Owner: Gadsden County Owner's Contract No.: N/A

Contractor: Contractor’s Project No.:

Engineer: Alday-Howell Engineering, Inc. FPID No.: N/A

Project: CR 12 (5th Ave) – Pedestrian

Improvements

Effective Date of Contract:

TO CONTRACTOR:

Owner hereby notifies Contractor that the Contract Times under the above Contract will commence to run on

[__________________, 20xx]. [see Paragraph 4.01 of the General Conditions]

On that date, Contractor shall start performing its obligations under the Contract Documents. No Work shall be done at the Site prior to such date. In accordance with the Agreement, [the date of Substantial Completion is

____________, and the date of readiness for final payment is_______] or [the number of days to achieve

Substantial Completion is ___________, and the number of days to achieve readiness for final payment is

Before starting any Work at the Site, Contractor must comply with the following:

[Note any access limitations, security procedures, or other restrictions]

**Previous Notice to Proceed (See Attached) has been deemed void due to unforeseen circumstances. This NTP has been drafted and executed to enable the contractor to mobilize and begin work in a timely manner.

Owner: Gadsden County BOCC

Authorized Signature

By:

Title:

Date Issued:

Copy: Engineer

ITB 27-01 CR12 5th Ave Pedestrian Improvements

EJCDC® C-610, Performance Bond

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 1 of 4

PERFORMANCE BOND

CONTRACTOR (name and address): SURETY (name and address of principal place of business):

OWNER (name and address):

Gadsden County

9 E Jefferson Street, Quincy, FL 32353

CONSTRUCTION CONTRACT

Effective Date of the Agreement:

Amount:

Description (name and location): CR 12 (5th Ave) – Pedestrian Improvements

BOND

Bond Number:

Date (not earlier than the Effective Date of the Agreement of the Construction Contract):

Amount:

Modifications to this Bond Form: None See Paragraph 16

Surety and Contractor, intending to be legally bound hereby, subject to the terms set forth below, do each cause this Performance Bond to be duly executed by an authorized officer, agent, or representative.

CONTRACTOR AS PRINCIPAL SURETY

(seal) (seal)

Contractor’s Name and Corporate Seal Surety’s Name and Corporate Seal

By: By:

Signature Signature (attach power of attorney)

Print Name Print Name

Title Title

Attest: Attest:

Signature Signature

Title Title

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 2 of 4

Notes: (1) Provide supplemental execution by any additional parties, such as joint venturers. (2) Any singular reference to

Contractor, Surety, Owner, or other party shall be considered plural where applicable.

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 3 of 4

1. The Contractor and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to the Owner for the performance of the Construction

Contract, which is incorporated herein by reference.

2. If the Contractor performs the Construction Contract, the Surety and the Contractor shall have no obligation under this Bond, except when applicable to participate in a conference as provided in

Paragraph 3.

3. If there is no Owner Default under the Construction Contract, the Surety’s obligation under this Bond shall arise after:

3.1 The Owner first provides notice to the Contractor and

the Surety that the Owner is considering declaring a Contractor

Default. Such notice shall indicate whether the Owner is requesting a conference among the Owner, Contractor, and

Surety to discuss the Contractor’s performance. If the Owner does not request a conference, the Surety may, within five (5) business days after receipt of the Owner’s notice, request such a conference. If the Surety timely requests a conference, the

Owner shall attend. Unless the Owner agrees otherwise, any conference requested under this Paragraph 3.1 shall be held within ten (10) business days of the Surety’s receipt of the

Owner’s notice. If the Owner, the Contractor, and the Surety agree, the Contractor shall be allowed a reasonable time to perform the Construction Contract, but such an agreement shall not waive the Owner’s right, if any, subsequently to declare a

Contractor Default;

3.2 The Owner declares a Contractor Default, terminates

the Construction Contract and notifies the Surety; and

3.3 The Owner has agreed to pay the Balance of the

Contract Price in accordance with the terms of the Construction

Contract to the Surety or to a contractor selected to perform the

Construction Contract.

4. Failure on the part of the Owner to comply with the notice requirement in Paragraph 3.1 shall not constitute a failure to comply with a condition precedent to the Surety’s obligations, or release the

Surety from its obligations, except to the extent the Surety demonstrates actual prejudice.

5. When the Owner has satisfied the conditions of Paragraph 3, the

Surety shall promptly and at the Surety’s expense take one of the following actions:

5.1 Arrange for the Contractor, with the consent of the

Owner, to perform and complete the Construction Contract;

5.2 Undertake to perform and complete the Construction

Contract itself, through its agents or independent contractors;

5.3 Obtain bids or negotiated proposals from qualified

contractors acceptable to the Owner for a contract for performance and completion of the Construction Contract, arrange for a contract to be prepared for execution by the

Owner and a contractor selected with the Owners concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the bonds issued on the

Construction Contract, and pay to the Owner the amount of damages as described in Paragraph 7 in excess of the Balance of the Contract Price incurred by the Owner as a result of the

Contractor Default; or

5.4 Waive its right to perform and complete, arrange for

completion, or obtain a new contractor, and with reasonable promptness under the circumstances:

5.4.1 After investigation, determine the amount for

which it may be liable to the Owner and, as soon as practicable after the amount is determined, make payment to the Owner; or

5.4.2 Deny liability in whole or in part and notify the

Owner, citing the reasons for denial.

6. If the Surety does not proceed as provided in Paragraph 5 with reasonable promptness, the Surety shall be deemed to be in default on this Bond seven days after receipt of an additional written notice from the Owner to the Surety demanding that the Surety perform its obligations under this Bond, and the Owner shall be entitled to enforce any remedy available to the Owner. If the Surety proceeds as provided in Paragraph 5.4, and the Owner refuses the payment or the

Surety has denied liability, in whole or in part, without further notice the Owner shall be entitled to enforce any remedy available to the

Owner.

7. If the Surety elects to act under Paragraph 5.1, 5.2, or 5.3, then the responsibilities of the Surety to the Owner shall not be greater than those of the Contractor under the Construction Contract, and the responsibilities of the Owner to the Surety shall not be greater than those of the Owner under the Construction Contract. Subject to the commitment by the Owner to pay the Balance of the Contract

Price, the Surety is obligated, without duplication for:

7.1 the responsibilities of the Contractor for correction of defective work and completion of the Construction Contract;

7.2 additional legal, design professional, and delay costs resulting from the Contractor’s Default, and resulting from the actions or failure to act of the Surety under Paragraph 5; and

7.3 liquidated damages, or if no liquidated damages are specified in the Construction Contract, actual damages caused by delayed performance or non-performance of the Contractor.

8. If the Surety elects to act under Paragraph 5.1, 5.3, or 5.4, the

Surety’s liability is limited to the amount of this Bond.

9. The Surety shall not be liable to the Owner or others for obligations of the Contractor that are unrelated to the Construction

Contract, and the Balance of the Contract Price shall not be reduced or set off on account of any such unrelated obligations. No right of action shall accrue on this Bond to any person or entity other than the Owner or its heirs, executors, administrators, successors, and assigns.

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 4 of 4

10. The Surety hereby waives notice of any change, including changes of time, to the Construction Contract or to related subcontracts, purchase orders, and other obligations.

11. Any proceeding, legal or equitable, under this Bond may be instituted in any court of competent jurisdiction in the location in which the work or part of the work is located and shall be instituted within two years after a declaration of Contractor Default or within two years after the Contractor ceased working or within two years after the Surety refuses or fails to perform its obligations under this

Bond, whichever occurs first. If the provisions of this paragraph are void or prohibited by law, the minimum periods of limitations available to sureties as a defense in the jurisdiction of the suit shall be applicable.

12. Notice to the Surety, the Owner, or the Contractor shall be mailed or delivered to the address shown on the page on which their signature appears.

13. When this Bond has been furnished to comply with a statutory or other legal requirement in the location where the construction was to be performed, any provision in this Bond conflicting with said statutory or legal requirement shall be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement shall be deemed incorporated herein. When so furnished, the intent is that this Bond shall be construed as a statutory bond and not as a common law bond.

14. Definitions

14.1 Balance of the Contract Price: The total amount

payable by the Owner to the Contractor under the Construction

Contract after all proper adjustments have been made including allowance for the Contractor for any amounts received or to be received by the Owner in settlement of insurance or other claims for damages to which the Contractor is entitled, reduced by all valid and proper payments made to or on behalf of the

Contractor under the Construction Contract.

14.2 Construction Contract: The agreement between the

Owner and Contractor identified on the cover page, including all

Contract Documents and changes made to the agreement and the Contract Documents.

14.3 Contractor Default: Failure of the Contractor, which

has not been remedied or waived, to perform or otherwise to comply with a material term of the Construction Contract.

14.4 Owner Default: Failure of the Owner, which has not

been remedied or waived, to pay the Contractor as required under the Construction Contract or to perform and complete or comply with the other material terms of the Construction

Contract.

14.5 Contract Documents: All the documents that comprise

the agreement between the Owner and Contractor.

15. If this Bond is issued for an agreement between a contractor and subcontractor, the term Contractor in this Bond shall be deemed to be Subcontractor and the term Owner shall be deemed to be

Contractor.

16. Modifications to this Bond are as follows:

ITB 27-01 CR12 5th Ave Pedestrian Improvements

EJCDC® C-615, Payment Bond

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 1 of 4

PAYMENT BOND

CONTRACTOR (name and address): SURETY (name and address of principal place of business):

OWNER (name and address):

Gadsden County

9 E Jefferson Street, Quincy, FL 32353

CONSTRUCTION CONTRACT

Effective Date of the Agreement:

Amount:

Description (name and location): CR 12 (5th Ave) – Pedestrian Improvements

BOND

Bond Number:

Date (not earlier than the Effective Date of the Agreement of the Construction Contract):

Amount:

Modifications to this Bond Form: None See Paragraph 18

Surety and Contractor, intending to be legally bound hereby, subject to the terms set forth below, do each cause this Payment Bond to be duly executed by an authorized officer, agent, or representative.

CONTRACTOR AS PRINCIPAL SURETY

(seal) (seal)

Contractor’s Name and Corporate Seal Surety’s Name and Corporate Seal

By: By:

Signature Signature (attach power of attorney)

Print Name Print Name

Title Title

Attest: Attest:

Signature Signature

Title Title

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 2 of 4

Notes: (1) Provide supplemental execution by any additional parties, such as joint venturers. (2) Any singular reference to Contractor, Surety, Owner, or other party shall be considered plural where applicable.

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 3 of 4

1. The Contractor and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to the Owner to pay for labor, materials, and equipment furnished for use in the performance of the Construction Contract, which is incorporated herein by reference, subject to the following terms.

2. If the Contractor promptly makes payment of all sums due to Claimants, and defends, indemnifies, and holds harmless the Owner from claims, demands, liens, or suits by any person or entity seeking payment for labor, materials, or equipment furnished for use in the performance of the Construction Contract, then the Surety and the Contractor shall have no obligation under this

Bond.

3. If there is no Owner Default under the Construction

Contract, the Surety’s obligation to the Owner under this

Bond shall arise after the Owner has promptly notified the

Contractor and the Surety (at the address described in

Paragraph 13) of claims, demands, liens, or suits against the Owner or the Owner’s property by any person or entity seeking payment for labor, materials, or equipment furnished for use in the performance of the Construction

Contract, and tendered defense of such claims, demands, liens, or suits to the Contractor and the Surety.

4. When the Owner has satisfied the conditions in Paragraph

3, the Surety shall promptly and at the Surety’s expense defend, indemnify, and hold harmless the Owner against a duly tendered claim, demand, lien, or suit.

5. The Surety’s obligations to a Claimant under this Bond shall arise after the following:

5.1 Claimants who do not have a direct contract with

the Contractor,

5.1.1 have furnished a written notice of non-payment to the Contractor, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were, or equipment was, furnished or supplied or for whom the labor was done or performed, within ninety (90) days after having last performed labor or last furnished materials or equipment included in the

Claim; and

5.1.2 have sent a Claim to the Surety (at the address described in Paragraph 13).

5.2 Claimants who are employed by or have a direct

contract with the Contractor have sent a Claim to the Surety (at the address described in Paragraph

13).

6. If a notice of non-payment required by Paragraph 5.1.1 is given by the Owner to the Contractor, that is sufficient to satisfy a Claimant’s obligation to furnish a written notice of non-payment under Paragraph 5.1.1.

7. When a Claimant has satisfied the conditions of Paragraph

5.1 or 5.2, whichever is applicable, the Surety shall promptly and at the Surety’s expense take the following actions:

7.1 Send an answer to the Claimant, with a copy to the

Owner, within sixty (60) days after receipt of the

Claim, stating the amounts that are undisputed and the basis for challenging any amounts that are disputed; and

7.2 Pay or arrange for payment of any undisputed

amounts.

7.3 The Surety’s failure to discharge its obligations

under Paragraph 7.1 or 7.2 shall not be deemed to constitute a waiver of defenses the Surety or

Contractor may have or acquire as to a Claim, except as to undisputed amounts for which the

Surety and Claimant have reached agreement. If, however, the Surety fails to discharge its obligations under Paragraph 7.1 or 7.2, the Surety shall indemnify the Claimant for the reasonable attorney’s fees the Claimant incurs thereafter to recover any sums found to be due and owing to the Claimant.

8. The Surety’s total obligation shall not exceed the amount of this Bond, plus the amount of reasonable attorney’s fees provided under Paragraph 7.3, and the amount of this

Bond shall be credited for any payments made in good faith by the Surety.

9. Amounts owed by the Owner to the Contractor under the

Construction Contract shall be used for the performance of the Construction Contract and to satisfy claims, if any, under any construction performance bond. By the

Contractor furnishing and the Owner accepting this Bond, they agree that all funds earned by the Contractor in the performance of the Construction Contract are dedicated to satisfy obligations of the Contractor and Surety under this Bond, subject to the Owner’s priority to use the funds for the completion of the work.

10. The Surety shall not be liable to the Owner, Claimants, or others for obligations of the Contractor that are unrelated to the Construction Contract. The Owner shall not be liable for the payment of any costs or expenses of any

Claimant under this Bond, and shall have under this Bond no obligation to make payments to or give notice on behalf of Claimants, or otherwise have any obligations to

Claimants under this Bond.

11. The Surety hereby waives notice of any change, including changes of time, to the Construction Contract or to related subcontracts, purchase orders, and other obligations.

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 4 of 4

12. No suit or action shall be commenced by a Claimant under this Bond other than in a court of competent jurisdiction in the state in which the project that is the subject of the

Construction Contract is located or after the expiration of one year from the date (1) on which the Claimant sent a

Claim to the Surety pursuant to Paragraph 5.1.2 or 5.2, or

(2) on which the last labor or service was performed by anyone or the last materials or equipment were furnished by anyone under the Construction Contract, whichever of

(1) or (2) first occurs. If the provisions of this paragraph are void or prohibited by law, the minimum period of limitation available to sureties as a defense in the jurisdiction of the suit shall be applicable.

13. Notice and Claims to the Surety, the Owner, or the

Contractor shall be mailed or delivered to the address shown on the page on which their signature appears.

Actual receipt of notice or Claims, however accomplished, shall be sufficient compliance as of the date received.

14. When this Bond has been furnished to comply with a statutory or other legal requirement in the location where the construction was to be performed, any provision in this Bond conflicting with said statutory or legal requirement shall be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement shall be deemed incorporated herein. When so furnished, the intent is that this Bond shall be construed as a statutory bond and not as a common law bond.

15. Upon requests by any person or entity appearing to be a potential beneficiary of this Bond, the Contractor and

Owner shall promptly furnish a copy of this Bond or shall permit a copy to be made.

16. Definitions

16.1 Claim: A written statement by the Claimant

including at a minimum:

1. The name of the Claimant;

2. The name of the person for whom the labor was done, or materials or equipment furnished;

3. A copy of the agreement or purchase order pursuant to which labor, materials, or equipment was furnished for use in the performance of the Construction Contract;

4. A brief description of the labor, materials, or equipment furnished;

5. The date on which the Claimant last performed labor or last furnished materials or equipment for use in the performance of the

Construction Contract;

6. The total amount earned by the Claimant for labor, materials, or equipment furnished as of the date of the Claim;

7. The total amount of previous payments received by the Claimant; and

8. The total amount due and unpaid to the

Claimant for labor, materials, or equipment furnished as of the date of the Claim.

16.2 Claimant: An individual or entity having a direct

contract with the Contractor or with a subcontractor of the Contractor to furnish labor, materials, or equipment for use in the performance of the Construction Contract. The term Claimant also includes any individual or entity that has rightfully asserted a claim under an applicable mechanic’s lien or similar statute against the real property upon which the Project is located. The intent of this Bond shall be to include without limitation in the terms of “labor, materials, or equipment” that part of the water, gas, power, light, heat, oil, gasoline, telephone service, or rental equipment used in the Construction

Contract, architectural and engineering services required for performance of the work of the

Contractor and the Contractor’s subcontractors, and all other items for which a mechanic’s lien may be asserted in the jurisdiction where the labor, materials, or equipment were furnished.

16.3 Construction Contract: The agreement between

the Owner and Contractor identified on the cover page, including all Contract Documents and all changes made to the agreement and the Contract

Documents.

16.4 Owner Default: Failure of the Owner, which has

not been remedied or waived, to pay the

Contractor as required under the Construction

Contract or to perform and complete or comply with the other material terms of the Construction

Contract.

16.5 Contract Documents: All the documents that

comprise the agreement between the Owner and

Contractor.

17. If this Bond is issued for an agreement between a contractor and subcontractor, the term Contractor in this

Bond shall be deemed to be Subcontractor and the term

Owner shall be deemed to be Contractor.

18. Modifications to this Bond are as follows:

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Contractor's Application for Payment No.

Application Application Date:

Period:

To From (Contractor): Via (Engineer):

(Owner):

Project: Contract:

Owner's Contract No.: Contractor's Project No.: FPID No.:

1. ORIGINAL CONTRACT PRICE...........................................................................$

2. Net change by Change Orders......................................................................................$

3. Current Contract Price (Line 1 ± 2)................................................................................................$

4. TOTAL COMPLETED AND STORED TO DATE

(Column F total on Progress Estimates).............................................................................................................$

5. RETAINAGE:

a. X Work Completed..............................................$

b. X Stored Material..............................................$

c. Total Retainage (Line 5.a + Line 5.b).........................................................................................................................................$

6. AMOUNT ELIGIBLE TO DATE (Line 4 - Line 5.c)....................................................................................................................$

7. LESS PREVIOUS PAYMENTS (Line 6 from prior Application).........................................................................................................$

8. AMOUNT DUE THIS APPLICATION....................................................................................................................................$

9. BALANCE TO FINISH, PLUS RETAINAGE

(Column G total on Progress Estimates + Line 5.c above).....................................................................................................$

Contractor's Certification

Payment of: $ is recommended by:

Payment of: $ is approved by:

Contractor Signature

By: Date: Approved by:

N/A

Approved Change Orders

Application For Payment

Change Order Summary

CR 12 (5th Ave) - Pedestrian Improvements

Gadsden County Board of County Commissioners

AdditionsNumber Deductions

(Line 8 or other - attach explanation of the other amount)

TOTALS

(Line 8 or other - attach explanation of the other amount)

(Date)

Funding or Financing Entity (if applicable)

CHANGE ORDERS

(Date)

(Date)(Engineer)

(Owner)

NET CHANGE BY

The undersigned Contractor certifies, to the best of its knowledge, the following:

(1) All previous progress payments received from Owner on account of Work done under the Contract have been applied on account to discharge Contractor's legitimate obligations incurred in connection with the Work covered by prior Applications for Payment;

(2) Title to all Work, materials and equipment incorporated in said Work, or otherwise listed in or covered by this Application for Payment, will pass to Owner at time of payment free and clear of all Liens, security interests, and encumbrances (except such as are covered by a bond acceptable to Owner indemnifying Owner against any such Liens, security interest, or encumbrances); and

(3) All the Work covered by this Application for Payment is in accordance with the Contract Documents and is not defective.

EJCDC® C-620 Contractor's Application for Payment

© 2013 National Society of Professional Engineers for EJCDC. All rights reserved.

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Progress Estimate - Lump Sum Work

For (Contract): Application Number:

Application Period: Application Date:

B C D Materials Presently Total Completed Balance to Finish

Stored (not in C or D) and Stored to Date (B - F)

(C + D + E)

From Previous Application

(C+D)

Totals

(F / B)

GE

Specification Section

No.

Description

Contractor's Application

Scheduled Value ($)

A

This Period

FWork Completed

EJCDC® C-620 Contractor's Application for Payment

© 2013 National Society of Professional Engineers for EJCDC. All rights reserved.

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Progress Estimate - Unit Price Work Contractor's Application

Application Period: Application Date:

A B C D E F

(F / B) Bid Item No. Description

Balance to Finish

(B - F)

Contract Information

Item

Quantity Units Unit Price

Total Value of Item ($)

Item Estimated

Quantity

Installed

Value of Work

Installed to

Date

Materials Presently

Stored (not in C)

Total Completed and Stored to Date

(D + E)

Totals

EJCDC® C-620 Contractor's Application for Payment

© 2013 National Society of Professional Engineers for EJCDC. All rights reserved.

ITB 27-01 CR12 5th Ave Pedestrian Improvements

Stored Material Summary Contractor's Application

Application Period: Application Date:

B E G

Supplier

Invoice No.

Submittal No.

(with

Specification

Section No.)

A C

Bid

Item

No.

Storage

Location Description of Materials or Equipment Stored

D F

Stored Previously Incorporated in Work

Date Placed into Storage

(Month/Year)

Amount

Date (Month/

Year)

Amount

Materials Remaining in Storage ($)

(D + E - F)

Amount Stored this Month ($)

Subtotal Amount

Completed and

Stored to Date

(D + E)

Totals

EJCDC® C-620 Contractor's Application for Payment

© 2013 National Society of Professional Engineers for EJCDC. All rights reserved.

ITB 27-01 CR12 5th Ave Pedestrian Improvements

EJCDC® C-625, Certificate of Substantial Completion.

Prepared and published 2013 by the Engineers Joint Contract Documents Committee.

CERTIFICATE OF SUBSTANTIAL COMPLETION

Owner: Gadsden County Owner's Contract No.:

Contractor: Contractor’s Project No.:

Engineer: Alday-Howell Engineering, Inc. (CEI) FPID No.: N/A

Project: CR 12 (5th Ave) – Pedestrian Improvements Contract Name:

This [preliminary] [final] Certificate of Substantial Completion applies to:

All Work The following specified portions of the Work:

Date of Substantial Completion

The Work to which this Certificate applies has been inspected by authorized representatives of Owner, Contractor, and

Engineer, and found to be substantially complete. The Date of Substantial Completion of the Work or portion thereof designated above is hereby established, subject to the provisions of the Contract pertaining to Substantial Completion.

The date of Substantial Completion in the final Certificate of Substantial Completion marks the commencement of the contractual correction period and applicable warranties required by the Contract.

A punch list of items to be completed or corrected is attached to this Certificate. This list may not be all-inclusive, and the failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract.

The responsibilities between Owner and Contractor for security, operation, safety, maintenance, heat, utilities, insurance, and warranties upon Owner's use or occupancy of the Work shall be as provided in the Contract, except as amended as follows: [Note: Amendments of contractual responsibilities recorded in this Certificate should be the product of mutual agreement of Owner and Contractor; see Paragraph 15.03.D of the General Conditions.]

Amendments to Owner's responsibilities: None

As follows

Amendments to

Contractor's responsibilities: None

As follows:

The following documents are attached to and made a part of this Certificate: [punch list; others]

This Certificate does not constitute an acceptance of Work not in accordance with the Contract Documents, nor is it a release of Contractor's obligation to complete the Work in accordance with the Contract.

EXECUTED BY ENGINEER: RECEIVED: RECEIVED:

By: By: By:

(Authorized signature) Owner (Authorized Signature) Contractor (Authorized Signature)

Title: Title: Title:

Date: Date: Date:

ITB 27-01 CR12 5th Ave Pedestrian Improvements

C-641, Certificate of Final Completion.

CERTIFICATE OF FINAL COMPLETION

Owner: Gadsden County Owner's Contract No.: N/A

Contractor: Contractor’s Project No.: N/A

Engineer: Alday-Howell Engineering, Inc. (CEI) FPID No.: N/A

Project: CR 12 (5th Ave) – Pedestrian Improvements

This [preliminary] [final] Certificate of Final Completion applies to:

All Work under the Contract Documents or to the following specified parts thereof:

The Work to which this Certificate applies has been inspected by authorized representatives of Owner, Contractor, and Engineer, and found to be complete in accordance with the Contract Documents on

Date of Final Completion

Notice to Proceed: ____________________________________________________________________________(DATE)

Notice Contract Time: _______________________________________________________________(CALENDAR DAYS) Additional Contract Time Approved by Change Order: __________________________________________________________(CALENDAR DAYS)

Total Approved Contract Time: ________________________________________________________(CALENDAR DAYS)

Actual Contract Time: _______________________________________________________________(CALENDAR DAYS)

Unapproved Construction Time: _______________________________________________________(CALENDAR DAYS)

A warranty inspection will be held on:…