Choctaw_Beach_Fishing_Pier_FDEP_Exemption.pdf
PDF 7 MB Posted
- Solicitation number
- 27-01
- Issued by
- Bay County, Florida
About this file
This file is an FDEP (Florida Department of Environmental Protection) Exemption document related to the Tri Village Park Pier Construction project in Choctaw Beach, Walton County, Florida. The project involves the construction of a fishing pier at Tri Village Park on Choctawhatchee Bay, featuring an ADA-accessible ramp, access pier, terminal platform, kayak launch, stairs, and handrails constructed on driven timber piles with composite decking. The contract duration is one hundred twenty (120) days to substantial completion, with an additional thirty (30) days allocated for punch list completion. The project site is located at 13837 W Highway 20, Choctaw Beach, at the location of the former fire station on Choctawhatchee Bay.
The FDEP Exemption document addresses regulatory requirements and environmental compliance considerations necessary for the pier construction project. This exemption documentation is critical for project authorization and demonstrates that the proposed construction meets or is exempt from specific Florida Department of Environmental Protection regulations, allowing the project to proceed with construction activities on the state waterway and sensitive coastal environment.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FLORIDA DEPARTMENT OF
Environmental Protection
Northwest District
160 W. Government Street, Suite 308 Pensacola, Florida 32502-5794
Ron DeSantis Governor
Jay Collins
Lt. Governor
Alexis A. Lambert Secretary
April 14, 2026
Benjamin King 117 Montgomery Cir Defuniak Springs, FL 32435
File No. 0470011-001-EE-66, Walton County
Dear Mr. King:
On March 19, 2026, we received your request for verification of exemption to perform the following activities:
To construct a 959 square foot dock consisting of an ADA accessible ramp to an approximately 8’x87’ foot access pier and 10’x17.9’terminal platform, and 6’x14’ kayak launch area in Choctawhatchee Bay, Water Class II, 117 Montgomery Cir, Defuniak Springs, Section 28, Township 1 South, Range 21 West, Walton County.
Your request has been reviewed to determine whether it qualifies for (1) regulatory exemption,
(2) proprietary authorization (related to state-owned submerged lands), and (3) federal approval that may be necessary for work in wetlands or waters of the United States.
Your project qualifies for all three. However, this letter does not relieve you from the responsibility of obtaining other federal, state, or local authorizations that may be required for the activity.
State water quality certification is waived for activities that are exempt under rule 62-330.051, F.A.C.
If you change the project from what you submitted, the authorization(s) granted may no longer be valid at the time of commencement of the project. Please contact us prior to beginning your project if you wish to make any changes.
If you have any questions regarding this matter, please contact Michael Dylan Garrett at the letterhead address or at 850-595-0648 and Michael.D.Garrett@FloridaDEP.gov.
File Name: Choctaw Beach Fishing Pier FDEP File No.: 0470011-001-EE-66
1. Regulatory Review –Verified Based on the information submitted, the Department has verified that the activity as proposed is exempt, under Chapter 62-330.051,(5 (b)), Florida Administrative Code, or from the need to obtain a regulatory permit under Part IV of Chapter 373 of the Florida Statutes.
This exemption verification is based on the information you provided the Department and the statutes and rules in effect when the information was submitted. This verification may not be valid if site conditions materially change, the project design is modified, or the statutes or rules governing the exempt activity are amended. In the event you need to re-verify the exempt status for the activity, a new request and verification fee will be required. Any substantial modifications to the project design should be submitted to the Department for review, as changes may result in a permit being required.
2. Proprietary Review- Granted The Department acts as staff to the Board of Trustees of the Internal Improvement Trust Fund (Board of Trustees) and issues certain authorizations for the use of sovereign submerged lands.
The Department has the authority to review activities on sovereign submerged lands under Chapters 253 and 258 of the Florida Statutes, and Chapters 18-20 and 18-21 of the Florida Administrative Code.
The activity appears to be located on sovereign submerged lands owned by the Board of Trustees. The activity is not exempt from the need to obtain the applicable proprietary authorization. As staff to the Board of Trustees, the Department has reviewed the activity described above, and has determined that the activity qualifies for an automatic consent by rule under Rule 18-21.005(1)(b) and Section 253.77 of the Florida Statutes to construct and use the activity on the specified sovereign submerged lands, as long as the work performed is located within the boundaries as described herein and is consistent with the terms and conditions herein.
No further application is required for this consent by rule.
General Conditions for Authorizations for Activities
All authorizations granted by rule or in writing under Rule 18-21.005, F.A.C., except those for geophysical testing, shall be subject to the general conditions as set forth in paragraphs (a) through
(j) below. The general conditions shall be part of all authorizations under this chapter, shall be binding upon the grantee, and shall be enforceable under Chapter 253 or 258, Part II, F.S.
(a) Authorizations are valid only for the specified activity or use. Any unauthorized deviation from the specified activity or use and the conditions for undertaking that activity or use shall constitute a violation. Violation of the authorization shall result in suspension or revocation of the grantee’s use of the sovereignty submerged land unless cured to the satisfaction of the Board.
(b) Authorizations convey no title to sovereignty submerged land or water column, nor do they constitute recognition or acknowledgment of any other person’s title to such land or water.
(c) Authorizations may be modified, suspended or revoked in accordance with their terms or the remedies provided in Sections 253.04 and 258.46, F.S., or Chapter 18-14, F.A.C.
(d) Structures or activities shall be constructed and used to avoid or minimize adverse impacts to sovereignty submerged lands and resources.
(e) Construction, use, or operation of the structure or activity shall not adversely affect any species which is endangered, threatened or of special concern, as listed in Rules 68A-27.003, 68A-27.004, and 68A-27.005, F.A.C.
(f) Structures or activities shall not unreasonably interfere with riparian rights. When a court of competent jurisdiction determines that riparian rights have been unlawfully affected, the structure or activity shall be modified in accordance with the court’s decision.
(g) Structures or activities shall not create a navigational hazard.
(h) Activities shall not interfere with the public easement for traditional uses of the sandy beaches provided in section 161.141, F.S.
(i) Structures shall be maintained in a functional condition and shall be repaired or removed if they become dilapidated to such an extent that they are no longer functional. This shall not be construed to prohibit the repair or replacement subject to the provisions of rule 18-21.005, F.A.C., within one year, of a structure damaged in a discrete event such as a storm, flood, accident, or fire.
(j) Structures or activities shall be constructed, operated, and maintained solely for water dependent purposes, or for non-water dependent activities authorized under paragraph 18- 21.004(1)(g), F.A.C., or any other applicable law.
3. Federal Review - SPGP Approved Your proposed activity as outlined in your application and attached drawings qualifies for Federal authorization pursuant to the State Programmatic General Permit VI-R1, and a SEPARATE permit or authorization will not be required from the U.S. Army Corps of Engineers. Please note that the Federal authorization expires on July 27, 2026. However, your authorization may remain in effect for up to 1 additional year, if provisions of Special Condition 15 of the SPGP VI-R1 permit instrument are met. You, as permittee, are required to adhere to all General Conditions and Special Conditions that may apply to your project. Special conditions required for your project are attached. A copy of the SPGP VI-R1 with all terms and conditions and the General Conditions may be found online in the Jacksonville District Regulatory Division Sourcebook (https://www.saj.usace.army.mil/Missions/Regulatory/Source-Book/).
Authority for review - an agreement with the USACOE entitled “Coordination Agreement Between the U. S. Army Corps of Engineers (Jacksonville District) and the Florida Department of Environmental Protection (or Duly Authorized Designee), State Programmatic General https://www.saj.usace.army.mil/Missions/Regulatory/Source-Book/
Permit”, Section 10 of the Rivers and Harbor Act of 1899, and Section 404 of the Clean Water Act.
3.2. Coastal Zone Management Presumed
The U.S. Army Corps of Engineers (Corps) or any designated federal, state or local agency administering general permits on behalf of the Corps under 33 C.F.R. Section 325.2(b)(2) may presume the verified exempt activities are consistent with the permitting Agency’s authorities within the FCMP, provided the activity receives any applicable authorization to use and occupy state-owned submerged lands under Chapter 253, F.S., and, as applicable, Chapter 258, F.S.
3.3. Water Quality Certification Waived
This permit also constitutes an express waiver of water quality certification under Section 401 of the Clean Water Act, 33 U.S.C. Section 1341. Pursuant to Rule 62-330.062, F.A.C. State Water Quality Certification is waived for activities that are exempt under rule 62-330.051 or 62- 330.0511, F.A.C.
Additional Information Please retain this letter. The activities may be inspected by authorized state personnel in the future to ensure compliance with appropriate statutes and administrative codes. If the activities are not in compliance, you may be subject to penalties under Chapter 373, F.S., and Chapter 18- 14, F.A.C.
NOTICE OF RIGHTS
This action is final and effective on the date filed with the Clerk of the Department unless a petition for an administrative hearing is timely filed under Sections 120.569 and 120.57, F.S., before the deadline for filing a petition. On the filing of a timely and sufficient petition, this action will not be final and effective until further order of the Department. Because the administrative hearing process is designed to formulate final agency action, the hearing process may result in a modification of the agency action or even denial of the application.
Petition for Administrative Hearing A person whose substantial interests are affected by the Department’s action may petition for an administrative proceeding (hearing) under Sections 120.569 and 120.57, F.S. Pursuant to Rules 28-106.201 and 28-106.301, F.A.C., a petition for an administrative hearing must contain the following information:
(a) The name and address of each agency affected and each agency’s file or identification number, if known;
(b) The name, address, any e-mail address, any facsimile number, and telephone number of the petitioner, if the petitioner is not represented by an attorney or a qualified representative; the name, address, and telephone number of the petitioner’s representative, if any, which shall be the address for service purposes during the course of the proceeding; and an explanation of how the petitioner’s substantial interests will be affected by the agency determination;
(c) A statement of when and how the petitioner received notice of the agency decision;
(d) A statement of all disputed issues of material fact. If there are none, the petition must so indicate;
(e) A concise statement of the ultimate facts alleged, including the specific facts that the petitioner contends warrant reversal or modification of the agency’s proposed action;
(f) A statement of the specific rules or statutes that the petitioner contends require reversal or modification of the agency’s proposed action, including an explanation of how the alleged facts relate to the specific rules or statutes; and
(g) A statement of the relief sought by the petitioner, stating precisely the action that the petitioner wishes the agency to take with respect to the agency’s proposed action.
The petition must be filed (received by the Clerk) in the Office of General Counsel of the Department at 3900 Commonwealth Boulevard, Mail Station 35, Tallahassee, Florida 32399- 3000, or via electronic correspondence at Agency_Clerk@dep.state.fl.us. Also, a copy of the petition shall be mailed to the applicant at the address indicated above at the time of filing.
Time Period for Filing a Petition In accordance with Rule 62-110.106(3), F.A.C., petitions for an administrative hearing by the applicant and persons entitled to written notice under Section 120.60(3), F.S., must be filed within 21 days of receipt of this written notice. Petitions filed by any persons other than the applicant, and other than those entitled to written notice under Section 120.60(3), F.S., must be filed within 21 days of publication of the notice or within 21 days of receipt of the written notice, whichever occurs first. You cannot justifiably rely on the finality of this decision unless notice of this decision and the right of substantially affected persons to challenge this decision has been duly published or otherwise provided to all persons substantially affected by the decision. While you are not required to publish notice of this action, you may elect to do so pursuant Rule 62- 110.106(10)(a).
The failure to file a petition within the appropriate time period shall constitute a waiver of that person's right to request an administrative determination (hearing) under Sections 120.569 and 120.57, F.S., or to intervene in this proceeding and participate as a party to it. Any subsequent intervention (in a proceeding initiated by another party) will be only at the discretion of the presiding officer upon the filing of a motion in compliance with Rule 28-106.205, F.A.C. If you do not publish notice of this action, this waiver will not apply to persons who have not received written notice of this action.
Extension of Time Under Rule 62-110.106(4), F.A.C., a person whose substantial interests are affected by the Department’s action may also request an extension of time to file a petition for an administrative hearing. The Department may, for good cause shown, grant the request for an extension of time.
Requests for extension of time must be filed with the Office of General Counsel of the Department at 3900 Commonwealth Boulevard, Mail Station 35, Tallahassee, Florida 32399- 3000, or via electronic correspondence at Agency_Clerk@dep.state.fl.us, before the deadline for filing a petition for an administrative hearing. A timely request for extension of time shall toll the running of the time period for filing a petition until the request is acted upon.
mailto:Agency_Clerk@dep.state.fl.us
Mediation Mediation is not available in this proceeding.
FLAWAC Review The applicant, or any party within the meaning of Section 373.114(1)(a) or 373.4275, F.S., may also seek appellate review of this order before the Land and Water Adjudicatory Commission under Section 373.114(1) or 373.4275, F.S. Requests for review before the Land and Water Adjudicatory Commission must be filed with the Secretary of the Commission and served on the Department within 20 days from the date when this order is filed with the Clerk of the Department.
Judicial Review Once this decision becomes final, any party to this action has the right to seek judicial review pursuant to Section 120.68, F.S., by filing a Notice of Appeal pursuant to Florida Rules of Appellate Procedure 9.110 and 9.190 with the Clerk of the Department in the Office of General Counsel (Station #35, 3900 Commonwealth Boulevard, Tallahassee, Florida 32399-3000) and by filing a copy of the Notice of Appeal accompanied by the applicable filing fees with the appropriate district court of appeal. The notice must be filed within 30 days from the date this action is filed with the Clerk of the Department.
EXECUTION AND CLERKING
Executed in Pensacola, Florida.
STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
Michael Dylan Garrett Environmental Specialist
Enclosures:
62-330.05(5(b)), 1 page
Project drawings,7 pages
CERTIFICATE OF SERVICE
The undersigned duly designated deputy clerk hereby certifies that this document and all attachments were sent on the filing date below to the following listed persons:
DEP, Michael.D.Garrett@FloridaDEP.gov, Una.Cole@FloridaDEP.gov USACE, Terry.S.Hayes@usace.army.mil Applicant, ben.king@mywaltonfl.gov Walton County, scott.caraway@mywaltonfl.gov, Gregary@co.walton.fl.us
FILING AND ACKNOWLEDGMENT
FILED, on this date, pursuant to Section 120.52, F. S., with the designated Department Clerk, receipt of which is hereby acknowledged.
Michelle Goldsmith April 14, 2026 Clerk Date mailto:Michael.D.Garrett@FloridaDEP.gov mailto:Una.Cole@FloridaDEP.gov mailto:Terry.S.Hayes@usace.army.mil mailto:ben.king@mywaltonfl.gov mailto:scott.caraway@mywaltonfl.gov mailto:Gregary@co.walton.fl.us
62-330.051 F.A.C. Exempt Activities 62-330.051(5(b))
(5) Dock, Pier, Boat Ramp and Other Boating-related Work ‒
(b) Installation of private docks, piers, and recreational docking facilities, and installation of local governmental piers and recreational docking facilities, in accordance with section 403.813(1)(b), F.S. This includes associated structures such as boat shelters, boat lifts, and roofs, provided:
1. The cumulative square footage of the dock or pier and all associated structures located over wetlands and other surface waters does not exceed the limitations in section 403.813(1)(b), F.S.;
2. No structure is enclosed on more than three sides with walls and doors;
3. Structures are not used for residential habitation or commercial purposes, or storage of materials other than those associated with water dependent recreational use; and
4. Any dock and associated structure shall be the sole dock as measured along the shoreline for a minimum distance of 65 feet, unless the parcel of land or individual lot as platted is less than 65 feet in length along the shoreline, in which case there may be one exempt dock allowed per parcel or lot.
Rulemaking Authority 373.026(7), 373.043, 373.4131, 373.4145, 403.805(1) FS. Law Implemented 373.406, 373.4131, 373.4145, 373.415, 403.813(1) FS. History–New 10-1-13, Amended 6-1-18.
10+00
11+00
5.5'
8.25'
5.5'
10'
17'-9"
87'-012"
6'
13'
48'-134"
22'-1114"
8'
30'
32'-1034"
DECK EL. 12'
DECK EL. 8'
DECK EL. 10'
DECK EL. 6.00'
DECK EL.
14.00'
ADA RAMP 1:15
SLOPE (TYP.)
PROPOSED PIER
WITH HANDRAILS
SIDEWALK ELEV.
14.00'
INSTALL & MAINTAIN "NO BOAT
MOORING ALLOWED" SIGN
(TYP.)
KAYAK LAUNCH
MHW EL. 0.54'
14'
PIER CONCEPTUAL PLAN
PROJECT NAME
DESCRIPTIONDATE DESCRIPTION DATE
REVISIONS
SHEET
NO.
X:\Engineering\NAS\ENGINEERING\PROJECTS\ACTIVE\CHOCTAW BEACH FISHING PIER\2. Engineering Design & Permitting\CAD\Choctaw Beach Park Pier - Simplified Plan.dwg
4/13/2026 5:24:34 PM
TH
E O
F F
IC
IA
L
R E C
OR
D O
F T
H
IS
S H E E T
IS
T
H E E
LE
C
TR
ON
IC
F
IL
E D
IG
IT
AL
LY
S
IG
N E D A
N D S
E
AL
E D U
N D E R R
U
LE
1G
-2
3.
4‚ F
.A .C
CHANCE POWELL, P.E.
P.E. LICENSE NUMBER 60818
WALTON COUNTY ENGINEERING DEPT.
117 MONTGOMERY CIRCLE
DEFUNIAK SPRINGS, FL 32435
WALTON COUNTY
ENGINEERING DEPARTMENT
CHOCTAW BEACH FISHING PIER
N
1"
0'
PLAN VIEW
1" = 20'
AREA SUMMARY
PIER FOOTPRINT
OVER LAND [SF]
PIER FOOTPRINT
OVER WATER [SF]
TOTAL PIER
FOOTPRINT [SF]
1434 951 2385
AutoCAD SHX Text
16" OAK
AutoCAD SHX Text
30"OAK
AutoCAD SHX Text
18"HICKORY
AutoCAD SHX Text
SAND & CLAY DRIVE
AutoCAD SHX Text
WOOD SEAWALL
HWY 20
AL
LE
Y S T
CEDAR AVE
LIVE
OAK
ST
JUN
IPE
R D R
PER
SIM
MON
ST
PER
SIM
MON
ST
LIV
E O
AK
ST
BEE
CH
ST
C E D
AR
A V E
M
IM
OSA D
R
HW
Y 2
W
AT
E R O
AK
S
T
SATSUMA RD
CHOCTAW BEACH, FL
PROJECT LOCATION
2/19/2026 10:51:14 AM X:\Engineering\NAS\ENGINEERING\PROJECTS\ACTIVE\CHOCTAW BEACH FISHING PIER\2. Engineering Design & Permitting\CAD\Choctaw Beach Park Pier Design.dwg
INDEX
SHEET NO. SHEET DESCRIPTION
1 CONCEPTUAL PLAN
2-5 PIER DETAILS
6 FRAMING PLAN
NOTE:
DRAWINGS ARE SCHEMATIC AND FOR REFERENCE ONLY. NOT INTENDED FOR STRUCTURAL
DESIGN OR CONSTRUCTION.
WALTON COUNTY
ENGINEERING DEPARTMENT
CHOCTAW BEACH FISHING PIER
CONCEPTUAL PLANS
CHANCE POWELL, P.E.
P.E. LICENSE NUMBER 60818
WALTON COUNTY ENGINEERING DEPT.
117 MONTGOMERY CIRCLE
DEFUNIAK SPRINGS, FL 32435
N
1"
FISCAL
YEAR
8'-0"
2'-10" TO
HANDRAIL
3'-6" TO
TOP OF
GUARDRAIL
2"
4'-2"
O.C. (TYP)
6'-0" TO I.F. OF POSTS
8"
PILE
EMBEDMENT
DEPTH 10' MIN.
DRIVEN LAST 3'
6'-7" TO O.F. OF POSTS
1'-4"
(2)-34" DIA. SS THRU-BOLTS W/ SS WASHERS
AND NUTS (TYP)
INSTALL 6x8 PT BLOCKING B/W CROSS BRACE
MEMBERS WHERE CROSS BRACING IS REQUIRED (TYP.)
INSTALL 2x8 PT CROSS BRACING WHERE EXISTING FINISH
GRADE TO TOP OF PILE CAP EXCEEDS 3 FT. (TYP.)
8x8 SOLID PT TIMBER BEAM TO PILE W/
CONNECTIONS AS SHOWN
FLOW THROUGH 2x6 MOISTURE SHIELD COMPOSITE
DECKING (CAPE COD GRAY) OR APPROVED EQUAL (TYP.)
℄ PILE (TYP.)
ADA HANDRAIL
2x10 PT JOIST @ 16" O.C. W/ SIMPSON H2.ASS @
EA. CROSSING W/ 8D SS NAILS (TYP.)
4x6 P.T. POST SPACED @ 4'
MAX SPACING
SS PL 5x14x 3
16 E.F. CONNECTED W/ (4)- 34" SS
THRU BOLT & SS WASHER AND NUT.
℄ BOARDWALK
(2)- 5
8" DIA SS CB W/ SS WASHERS AND NUT
COUNTERSUNK AS REQ. (TYP)
(2)- 5
8" DIA SS CB W/ SS WASHERS AND NUT
COUNTERSUNK AS REQ. (TYP)
PT TIMBER PILE (TYP.)
SECURE W/ #12x3" DECK
SCREWS (TYP.)
-8
-4
-8
-4
DECK
EL. = 6'
DECK
EL. = 10'
DECK
EL. = 14'
STAIRS
STAIRS
CONFIRM NECESSARY
PILE DEPTHS
MHW = 0.54'
EXISTING GROUND
SIDEWALK
EL. = 14'
5.46'
TO
WATER
PIER DETAILS (1)
PROJECT NAME
DESCRIPTIONDATE DESCRIPTION DATE
REVISIONS
SHEET
NO.
X:\Engineering\NAS\ENGINEERING\PROJECTS\ACTIVE\CHOCTAW BEACH FISHING PIER\2. Engineering Design & Permitting\CAD\Choctaw Beach Park Pier Design.dwg
2/19/2026 10:51:16 AM
O
F F
IC
IA
L
R E C
OR
D O
F T
H
IS
S H E E T
IS
T
H E E
LE
C
TR
ON
IC
F
IL
E D
IG
IT
AL
LY
S
IG
N E D A
N D S
E
AL
E D U
N D E R R
U
LE
1G
-2
3.
4‚ F
.A .C
CHANCE POWELL, P.E.
P.E. LICENSE NUMBER 60818
WALTON COUNTY ENGINEERING DEPT.
117 MONTGOMERY CIRCLE
DEFUNIAK SPRINGS, FL 32435
WALTON COUNTY
ENGINEERING DEPARTMENT
CHOCTAW BEACH FISHING PIER
PROFILE TYPICAL CROSS SECTION
1" = 2'
5'-6"
8'-3"
5'-1112" 7'-912"
6"
7"
11"
7"
11"
6"
2"x6" COMPOSITE
DECKING BOARDS
2"x10" CROSS
BEAMS
2"x6" PT RAIL BEAMS
2"x10" PT
STRINGERS
DECK EL. 14'
DECK EL. 10'
2x8 STRINGER
3'-512"
8'
1'-1"
COMPOSITE DECKING
2x12 MOISTURE SHIELD
COMPOSITE TOP CAP
6x6 GUARDRAIL POST
@ 5'-0" O.C. MAX
2x6 BEAM
2x8x2 FT. LONG SPLICE BLOCK
2x6 BLOCKING
4" DIA. GALV. THRU-BOLTS (TYP.)
℄ PILE (TYP.)
NOTCH TOP OF PILE FOR FULL BEAM
BEARING (TYP.)
PT TIMBER PILE (TYP.)
PIER DETAILS (2)
PROJECT NAME
DESCRIPTIONDATE DESCRIPTION DATE
REVISIONS
SHEET
NO.
X:\Engineering\NAS\ENGINEERING\PROJECTS\ACTIVE\CHOCTAW BEACH FISHING PIER\2. Engineering Design & Permitting\CAD\Choctaw Beach Park Pier Design.dwg
2/19/2026 10:52:01 AM
O
F F
IC
IA
L
R E C
OR
D O
F T
H
IS
S H E E T
IS
T
H E E
LE
C
TR
ON
IC
F
IL
E D
IG
IT
AL
LY
S
IG
N E D A
N D S
E
AL
E D U
N D E R R
U
LE
1G
-2
3.
4‚ F
.A .C
CHANCE POWELL, P.E.
P.E. LICENSE NUMBER 60818
WALTON COUNTY ENGINEERING DEPT.
117 MONTGOMERY CIRCLE
DEFUNIAK SPRINGS, FL 32435
WALTON COUNTY
ENGINEERING DEPARTMENT
CHOCTAW BEACH FISHING PIER
TYPICAL PROFILE
1" = 2'
TYPICAL STAIR DETAIL
1" = 3'
2"
3"
8'
2'
6"
(3) C5x3.97 ALUMINUM
STRINGERS, EQ. SPACED
2x10 PT STRINGERS
STRUCTURAL THERMOPLASTIC RAILING BY AVCON (OR
APPROVED EQUAL) AT STAIR, PER CONTRACTOR
McNICHOLS ALUMINUM PLANKS HD 1 12" THK., 2'-0"x6'-0" LONG
L13 4x1
4x
4 ALUMINUM SUPPORT FRAMING SHOP
WELDED TO TOP FLG. OF STRINGER
(2) 2x RIM BAND TO RECEIVE
STRINGERS, TYP.
TIMBER PILE
NOTCH TOP OF PILE FOR
FULL BEAM BEARING, TYP.
2x12 BEAM, EA. SIDE OF PILE
W/ (2) 34" ∅ STAINLESS STEEL
THRU-BOLTS. TYP. PL 14"x2 2"x0'-7
4" SHOP WELDED
SOLID TO STRINGER, EA. END,
TYP. W/ (2) 12" ∅ STAINLESS
STEEL THRU BOLTS @ 3" O.C.
DECK EL. 2'
DECK EL. 6'
(2) 2x RIM BAND TO RECEIVE
STRINGERS, TYP.
6'-912"5'-212"4'-8"5'-014"
PIER DETAILS (3)
PROJECT NAME
DESCRIPTIONDATE DESCRIPTION DATE
REVISIONS
SHEET
NO.
X:\Engineering\NAS\ENGINEERING\PROJECTS\ACTIVE\CHOCTAW BEACH FISHING PIER\2. Engineering Design & Permitting\CAD\Choctaw Beach Park Pier Design.dwg
2/19/2026 10:52:00 AM
O
F F
IC
IA
L
R E C
OR
D O
F T
H
IS
S H E E T
IS
T
H E E
LE
C
TR
ON
IC
F
IL
E D
IG
IT
AL
LY
S
IG
N E D A
N D S
E
AL
E D U
N D E R R
U
LE
1G
-2
3.
4‚ F
.A .C
CHANCE POWELL, P.E.
P.E. LICENSE NUMBER 60818
WALTON COUNTY ENGINEERING DEPT.
117 MONTGOMERY CIRCLE
DEFUNIAK SPRINGS, FL 32435
WALTON COUNTY
ENGINEERING DEPARTMENT
CHOCTAW BEACH FISHING PIER
KAYAK LAUNCH PROFILE
1" = 2'
512"
712"
8'
6'
1'-4" 1'
812" 712"
1'-212"
4x6 GUARDRAIL
POST
2x4
2x8
PT TIMBER
PILE (TYP.)SECURE W/
#12x3" DECK
SCREWS (TYP.)
8x8 SOLID PT
TIMBER BEAM
2x8 SPLICE
BLOCK
2x6 BLOCKING
PILE NOTCHED
FOR FULL LOAD
BEARING
2x8 STRINGER
RAMP @ 1:15 SLOPE
RAMP @ 1:15 SLOPE
4'-2"
COMPOSITE DECKING
2x12 MOISTURE SHIELD
COMPOSITE TOP CAP
6x6 GUARDRAIL POST
@ 5'-0" O.C. MAX
2x6 BEAM
DECK EL. 14'
6'
(2)-34" DIA. SS THRU-BOLTS W/
SS WASHERS AND NUTS (TYP)
1'-214"1'-214"
PIER DETAILS (4)
PROJECT NAME
DESCRIPTIONDATE DESCRIPTION DATE
REVISIONS
SHEET
NO.
X:\Engineering\NAS\ENGINEERING\PROJECTS\ACTIVE\CHOCTAW BEACH FISHING PIER\2. Engineering Design & Permitting\CAD\Choctaw Beach Park Pier Design.dwg
2/19/2026 10:51:38 AM
O
F F
IC
IA
L
R E C
OR
D O
F T
H
IS
S H E E T
IS
T
H E E
LE
C
TR
ON
IC
F
IL
E D
IG
IT
AL
LY
S
IG
N E D A
N D S
E
AL
E D U
N D E R R
U
LE
1G
-2
3.
4‚ F
.A .C
CHANCE POWELL, P.E.
P.E. LICENSE NUMBER 60818
WALTON COUNTY ENGINEERING DEPT.
117 MONTGOMERY CIRCLE
DEFUNIAK SPRINGS, FL 32435
WALTON COUNTY
ENGINEERING DEPARTMENT
CHOCTAW BEACH FISHING PIER
JOINT DETAIL
1" = 1'
RAMP JUNCTION DETAIL
1" = 3'
8' 8'8'8'8'8'
87'-012"
4'-814"4'-814"
10'
8' 8'8'8'7'-414"
5'-6"
(STEPS)8'-3"
5'-6"
(STEPS)
6'-11"5'-814"
129'-9"
4'-2"
17'-9"
512"
32'-1034"
512"
5'-1"
8'
8'
8'-812"
5'-714"
9'-11"
2'-10" 2'-10" 2'-10"
5'-814"
4'-2"
4'-2"
4'-2"
8'
5'-212"
14'
(ALUMINUM STEPS)4'-8"
6'
FRAMING PLAN
PROJECT NAME
DESCRIPTIONDATE DESCRIPTION DATE
REVISIONS
SHEET
NO.
X:\Engineering\NAS\ENGINEERING\PROJECTS\ACTIVE\CHOCTAW BEACH FISHING PIER\2. Engineering Design & Permitting\CAD\Choctaw Beach Park Pier Design.dwg
2/19/2026 10:52:00 AM
O
F F
IC
IA
L
R E C
OR
D O
F T
H
IS
S H E E T
IS
T
H E E
LE
C
TR
ON
IC
F
IL
E D
IG
IT
AL
LY
S
IG
N E D A
N D S
E
AL
E D U
N D E R R
U
LE
1G
-2
3.
4‚ F
.A .C
CHANCE POWELL, P.E.
P.E. LICENSE NUMBER 60818
WALTON COUNTY ENGINEERING DEPT.
117 MONTGOMERY CIRCLE
DEFUNIAK SPRINGS, FL 32435
WALTON COUNTY
ENGINEERING DEPARTMENT
CHOCTAW BEACH FISHING PIER
FRAMING PLAN
1" = 10'
| Permit Choctaw Beach Fishing Pier 0470011-001-EE-66 |
| File No. 0470011-001-EE-66, Walton County |
| Final Drawings |
| Pier Conceptual Plan (Simplified)_4-13-26 |
| Sheets and Views |
| PIER PLAN SIMPLIFIED |
| choc drawigns |
| Sheets and Views |
| 0 Cover Sheet |
| 2 DETAILS 1 |
| 3 DETAILS 2 |
| 4 DETAILS 3 |
| 5 DETAILS 4 |
| 6 FRAMING PLAN |