This document is an addendum to Invitation to Bid (ITB) 24-42TM Coliseum Lake Weir, issued by the City of Hampton, Virginia. The addendum extends the question and answer period to March 29, 2024 and the bid due date to April 16, 2024 at 2:30 pm. It provides responses to various questions received, including clarifications on the sheet pile cofferdam, dewatering, geotechnical report, stop logs, railing and walkway design, solar panels, drainage area and flow data, permit information, and construction sequencing. The project involves the reconstruction of the existing weir located at the outfall of Coliseum Lake in Hampton, Virginia, with the replacement of the concrete bed, rip rap, and road curb and dog waste station.

The addendum includes revisions to the bid tab, with the sheet pile cofferdam and dewatering items now being lump sum. It also provides guidance on the sizing of the backup batteries for the sluice gates and clarifies that no alternative mobilization sites are available, but the city is open to suggestions. The project will be funded by the City of Hampton, and the contractor will be responsible for obtaining any necessary permits, while the city will provide the NPW permit.

View the file

Other files

File Type Posted
ITB 23-42TM Addendum 4.docx.pdf PDF
ITB 24- 42TM Addendum 6 Attachment 3 DE Marking Private Utilities Customer Information (002).pdf PDF
ITB 24-42TM Addendum 3 Attachment 6 NAO-2013-02345 NWP.pdf PDF
ITB 24-42TM Coliseum Lake Slide Gate 100pc Construction Plans_signed.pdf PDF
ITB 23-42TM Addendum 5 Responses.pdf PDF
ITB 24-42TM Addendum 1.pdf PDF
ITB 24-42TM Addendum 2.pdf PDF
ITB 24-42TM Addendum 3 Attachment 4 Coliseum Lake Weir HH Analysis.pdf PDF
ITB 24-42TM Addendum 5 Attachment 1 Coliseum Slide Gate Site Plan (1).pdf PDF
ITB 24-42TM Addendum 6 Attachment 4.pdf PDF
ITB 24-42TM Addendum 6.pdf PDF
ITB 24-42TM Approved Site Plan.pdf PDF
ITB 24-42TM Bid Tab —
ITB 24-42TM Lake Slide Gate - Construction Specs.pdf PDF
ITB 24-42TM Mandatory Pre-bid Sign In Sheet.pdf PDF
ITB 24-42TM Addendum 3 Attachment 1 f Coliseum Lake Slide Gate Bid Tab_Rev1.xlsx XLSX spreadsheet
ITB 24-42TM Addendum 3 Attachment 2 Overall Report Coliseum Weir Flow Data.xlsx XLSX spreadsheet
ITB 24-42TM Addendum 6 Attachment 1.jpg JPG image
ITB 24-42TM Addendum 3 Attachment 5 Coliseum Lake Weir Structural Design.pdf PDF
ITB 24-42TM Addendum 3 Attachment 7 WM19-126G Coliseum Lake Weir Repairs Part II.pdf PDF
ITB 24-42TM Addendum 3_Responses.pdf PDF
ITB 24-42TM Addendum 6 Attachment 2 DE Coliseum Lake Gate Project Dominion WO Sketch (002).pdf PDF
ITB 24-42TM Addendum 6 Attachment 5 DE Trenching Requirements.pdf PDF
ITB 24-42TM Coliseum Lake Slide Gate Bid Tab.pdf PDF
ITB 24-42TM Lake Weir Replacement.pdf PDF
ITB 24-42TM Addendum 3 Attachment 2 Overall Report Coliseum Weir Flow Data.xlsx XLSX spreadsheet
ITB 24-42TM Addendum 3 Attachment 7 WM19-126G Coliseum Lake Weir Repairs Part II.pdf PDF
ITB 24-42TM Coliseum Lake Slide Gate Bid Tab.pdf PDF
ITB 24-42TM Lake Weir Replacement.pdf PDF
ITB 23-42TM Addendum 4.docx.pdf PDF
ITB 24-42TM Addendum 2.pdf PDF
ITB 24-42TM Addendum 3 Attachment 4 Coliseum Lake Weir HH Analysis.pdf PDF
ITB 24-42TM Addendum 3 Attachment 5 Coliseum Lake Weir Structural Design.pdf PDF
ITB 24-42TM Mandatory Pre-bid Sign In Sheet.pdf PDF
ITB 24-42TM Addendum 1.pdf PDF
ITB 24-42TM Approved Site Plan.pdf PDF
ITB 24-42TM Lake Slide Gate - Construction Specs.pdf PDF
ITB 24-42TM Addendum 3 Attachment 1 f Coliseum Lake Slide Gate Bid Tab_Rev1.xlsx XLSX spreadsheet
ITB 24-42TM Addendum 3 Attachment 6 NAO-2013-02345 NWP.pdf PDF
ITB 24-42TM Coliseum Lake Slide Gate 100pc Construction Plans_signed.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB 24-42TM Coliseum Lake Weir

ADDENDUM NO 3

DATE: March 30, 2024

ITB: ITB 24-42TM Coliseum Lake Weir

DATE ISSUED: February 27, 2024

BID DUE: April 16, 2024 at 2:30 p.m (Extended)

SUBJECT: To extend the question and answer period and the closing date and to respond to questions received.

Ladies/Gentlemen:

Addendum No. 3 is being issued to extend the question and answer date, extend the closing date and to provide a response to questions already received.

In order to allow for questions for the new information provided in this addendum, ITB 24-42TM Coliseum Lake Weir’s question and answer period has been extended to:

March 29, 2024 at 3:00 p.m. est

Questions should be emailed to tmartin@hampton.gov. Questions sent to the architect or the project manager will not be included in the addendum and will not be responded to.

ITB 24-42TM Coliseum Lake Weir closing date has been extended to:

April 16, 2024 at 2:30

Questions:

1. Question: We noticed the bid date was extended 3 weeks. Can the question period be extended to 3/29 allow vendors time to review the specifications in more detail?

Answer: The question period is now being extended to 03/29 and the bid date is now extended to Tuesday, April 16th at 2:30 pm.

2. Question: How was the quantity of 2300 SF for bid item 33, Sheet pile

Cofferdam, determined? Please provide a measurement and payment description and assumed dimensions this was based on. Typically we see these as lump sum pay items.

Answer: Please see updated bid tab. Cofferdam is now a lump sum item.

mailto:tmartin@hampton.gov

3. Question: Please confirm bid item 32 will be paid for each day dewatering and pumps are on-site for construction.

Answer: Dewatering pay item is now changed to lump sum. To size the pumps, please refer to the hydrology and hydraulics report (specifically

Appendix F – raw data provided as a spreadsheet) attached to

Addendum 3.

4. Question: Please provide Geotech report that is referenced on sheet G-2

Sequence of Construction Step 10.

Answer: Geotech report is attached with Addendum 3.

5. Question: Please provide more details on the stop logs. What is the quantity to be provided? Is there a separate stop log slot in the concrete structure? Details are not clear on what is desired.

Answer: Should for some reason, the gates were malfunction and get stuck in open position, the purpose of the stop logs is for the maintenance crews to be able to block the water from either the lake or the creek side.

A slot must be provided in the concrete for the aluminum stop logs to be placed. Eight (8) 6” (150mm) height stop logs per each four-foot-tall gate totaling sixteen (16) stop logs will be required.

6. Question: Sheet M-3 has two details for the railing and grated walkway. The railing posts are called out to be embedded every 5’ but we don’t see how this is possible with the span over the weir. Also, are the bars enough to support this span or are beams required to support it? M-3 calls out 6’ wide and S-1 has 8’ wide. Also, we can’t find any details for the concrete ramps on either side. Please provide a more complete and detailed design for the walkway.

Answer: The 8” circular railing posts to be embedded every 4 feet over the

28 feet length of the maintenance bridge/walkway. The width of the bridge/walkway to be 8 feet as shown on sheet S-1.

7. Question: Bid item 28 calls for Solar Panel but we can’t find any information on the drawings for specifications for this. Please let us know where it is or provide via addendum.

Answer: Solar panels will no longer be required as part of this project to charge the batteries. The batteries will be charged directly from the

Dominion Energy connection. The sizing of the batteries should be done in such a way that they can provide a 72 hour (3-days) backup to actuate

(open and close twice a day) the sluice gates.

8. Question: Please provide the drainage area that flows into this lake and any past storm data/lake height information.

Answer: Please refer to response to Question 3 of Addendum 3.

9. Question: Are there alternative sites suitable for mobilization?

Answer: No. However, the city is open to suggestions.

10. Question: Are there available As-Built drawings?

Answer: If the question is referring to as-built drawings of the weir, they are not available

11. Question: Has a load rating or load analysis been conducted for the earth dam?

Answer: Geotechnical report and structural design are attached to

Addendum 3

12. Question: What will happen to the well monitoring points.

Answer: The well monitoring points shall be protected during constructions, and after construction, to be protected by a locking cover.

13. Question: Can you provide daily flow rates or volume required for the bypass system.

Answer: Please refer to response to Question 3 of Addendum 3.

14. Question: Is the Rip Rap on the South side of the structure being replaced beyond the Right of way

Answer: No.

15. Question: Can you provide the permit?

Answer: Yes, please find attached NPW Permit to Addendum 3

16. Question: Note 12 (Sequence of Construction "Construct Storm Sewer

Drain on CD 102" Please confirm where the storm drain is being constructed, there is no CD102 in the RFP documents.

Answer: Not sure of the Note 12 being referred in the question. Please follow the suggested construction sequence listed on Sheet G-2 (3 of 11) of the construction plans.

17. Question: Confirm that the pay item 41 - Construction Entrance is in Tons and not Each

Answer: Pay item 41 – construction Entrance is now a lump sum item

18. Question: Consider postponing the bid date by 3 weeks to allow for the

Good Faith Effort to be completed.

Answered: The bid date has been postponed to Tuesday, April 16th at 2:30 pm.

19. Question: Note 18 "Pave Site" please confirm paving quantity and location.

Answer: Any pavement on H2O Community or the asphalt along the sidewalk near the project site, that gets disturbed due to the construction activity of this project is considered as an incidental, and the contractor is responsible to bring the disturbed pavement to the original state.

20. Question: What is the estimated flow rates that can be anticipated during this project?

Answer: Please refer to the hydrology and hydraulics report attached to

Addendum 3 for additional guidance.

21. Question: What is the basis of having to contact residents, what are we making them aware of? The contracted work will not affect any services to them. What means should the contractor notify them?

Answers: The contractor is required to install a 4’ x 6’ project sign to inform the residents of the work that is being performed as part of the project.

22. Question: Please provide a list of permits that the contractor will be responsible for obtaining.

Answer: Yes, please find attached NPW Permit to Addendum 3

23. Question: Please clarify what easement(s) the contractor will be responsible for obtaining.

Answer: All work for this project performed on City property or within the

ROW. If additional clarification is required, please submit your questions on/before Friday, March 29th.

24. Question: Please provide clarification on the Stop Log & Slide Gate designs.

Answer: Please refer to response to Question 5 of Addendum 3.

25. Question: Please provide a geotechnical report and borings (Appendix A)

Answer: Please refer to the geotechnical report attached to Addendum 3

26. Question: Who will be responsible for the cost associated with obstructions while driving piles or excavating?

Answer: The contractor should perform all the work for this project either on the City property or within the right-of-way/easements. If for any unforeseen reasons, there will obstructions, that would an incidental and not a covered cost by the city.

Additional Items of Clarification Provided as part of Addendum 3:

• Utilize new bid tab “Coliseum Lake Slide Gate Bid Tab_Rev1.xlsx”

• Refer to Figure 1 below:

o EXISTING LIGHT POLE TO BE REMOVED AND STORED DURING

CONSTRUCTION. PROVIDE TRAFFIC RATED IN- GROUND JUNCTION BOX TO

SPLICE THE EXISTING LIGHTING CIRCUIT WIRING SO IT REMAINS

ENERGIZED. AFTER CONSTRUCTION, RE-INSTALL LIGHT POLE TO PRE-

CONSTRUCTION CONDITIONS.

o CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING WITH

LIGHTING OWNER TO DE-ENERGIZE THE LIGHTING CIRCUIT FOR THE

LIGHT POLE REMOVAL AND RE-INSTALLATION.

Figure 1: Existing Light Pole and Bench currently located at the proposed construction entrance for the project

Bidders must take due notice and be governed accordingly. This addendum must be acknowledged as indicated in the Invitation to Bid or your Bid may not be considered.

All other terms and conditions must remain the same.

For the City of Hampton

Tammy Martin

Tammy Martin, CPPB, Senior Buyer

1 Franklin Street

Hampton, VA 23669

Phone: 757-727-2205

Email: tmartin@hampton.gov mailto:tmartin@hampton.gov