HSIP Intersection Improvements Special Provisions Summary

This document comprises the Special Provisions for a Highway Safety Improvement Program (HSIP) construction project administered by the City of Tucson Department of Transportation and Mobility (DTM) in partnership with the Arizona Department of Transportation (ADOT), utilizing Federal Highway Administration (FHWA) funding. The project encompasses traffic signal upgrades and intersection improvements at three signalized locations: Broadway Boulevard and Jessica Avenue, Drexel Road and Tucson Boulevard, and Irvington Road and Mission Road. Work at the first two intersections is ground-disturbing and includes installing new traffic signal poles, curb access ramps, and median modifications, while work at the third intersection is non-ground-disturbing and limited to installing new signal heads on existing mast arms. The contract establishes a construction timeline of 180 calendar days and mandates contractor compliance with traffic control plans, stakeholder coordination, and maintenance of access to businesses, residences, and emergency services throughout the project duration. The contractor must submit a preliminary schedule at the preconstruction conference and a detailed critical path schedule within 15 days thereafter, with monthly progress updates required by the tenth working day of each month.

The Special Provisions establish comprehensive quality control requirements, with contractors responsible for material testing, sampling, and documentation through a designated Quality Control Manager. Payment shall be made in accordance with standard unit prices for identified contract items, with force account work requiring certified payrolls and equipment documentation prior to reimbursement. The project incorporates environmental mitigation measures including noxious and invasive plant species treatment plans, lead-based paint removal protocols where applicable, and stormwater pollution prevention best management practices. Utility coordination is required with multiple service providers including CenturyLink/Lumen, Cox Communications, Tucson Electric Power, Southwest Gas, Tucson Water, and Pima County Wastewater Reclamation, with contractors obligated to maintain specified separation distances and obtain blue stake locates prior to ground disturbance. The contractor must establish staging areas with written property owner approval, provide pre-construction public meetings within ten days of contract execution, and coordinate with emergency services, the postal service, and transit operators to maintain continuous access and service delivery throughout construction.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HSIP INTERSECTION IMPROVEMENTS

T0491 – THREE SIGNALIZED INTERSECTIONS

TUCSON POSITIVE OFFSET AND FLASHING YELLOW ARROW

TRAFFIC SIGNAL UPGRADES

SPECIAL PROVISIONS

ADOT TRACS. - T0491 01C

Federal Aid No. – TUC-0(282)D

COT Plan No. I-2025-013

PCRWRD No. UPC-2025-062

APRIL 2026

Page II

CONTRACT SPECIAL PROVISIONS FOR:

ADOT TRACS. T0491 01C / Fed Aid No. TUC-0(282)D / COT Plan No. I-2025-013

T0491 – THREE SIGNALIZED LOCATIONS

FLASHING YELLOW ARROW AND POSITIVE OFFSET UPGRADES AT:

1. Broadway Boulevard and Jessica Avenue

2. Drexel Road and Tucson Boulevard

3. Irvington Road and Mission Road

PROFESSIONAL SEALS

These specifications were prepared under the direction of the following individuals:

Their seals, affixed above, attest that those portions of these specifications which relate to the plan sheet numbers appearing next to the seal were prepared under their direction.

d

Date Signe

.C

ATE NO

CIFITRE

A

ANOZIR

, U A..S.

s

R seforPderetsige ional Engineer (Civi)l

34570

KIMBERLY

CARROLL

04 29 26

Page III

TABLE OF CONTENTS

GENERAL REQUIREMENTS

SECTION 101 - ABBREVIATIONS AND DEFINITIONS

SECTION 104 - SCOPE OF WORK

SECTION 105 - CONTROL OF WORK

SECTION 107 - LEGAL RELATIONS AND RESPONSIBILITY TO PUBLIC

SECTION 108 - PROSECUTION AND PROGRESS

SECTION 109 - MEASUREMENT AND PAYMENT

SECTION 202 - REMOVAL OF STRUCTURES AND JUNCTIONS

ITEM 2020007 - REMOVAL OF MISCELLANEOUS CONCRETE

ITEM 2020020 - REMOVAL OF CURB

ITEM 2020021 - REMOVAL OF CONCRETE CURB AND GUTTER

ITEM 2020022 - REMOVAL OF LANDSCAPING/PAVERS

ITEM 2020023 - REMOVAL OF CONCRETE HEADER CURB

ITEM 2020039 - REMOVE AND RELOCATE SIGN

ITEM 2020203 - REMOVE AND SALVAGE TRAFFIC SIGNAL EQUIPMENT

AND CONDUCTORS (BROADWAY & JESSICA)

ITEM 2020204 - REMOVE AND SALVAGE TRAFFIC SIGNAL EQUIPMENT

AND CONDUCTORS (IRVINGTON & MISSION)

ITEM 2020205 - REMOVE AND SALVAGE TRAFFIC SIGNAL EQUIPMENT

AND CONDUCTORS (DREXEL & TUCSON)

SECTION 206 - FURNISH WATER SUPPLY

SECTION 404 - BITUMINOUS TREATMENTS

SECTION 406 - ASPHALTIC CONCRETE

SECTION 515 - UTILITY IMPACTS

ITEM 5150005 - UTILITY POTHOLING, DEPTH LESS THAN TWELVE FEET

(12’)

Page IV

ITEM 5150007 - UTILITY POTHOLING, DEPTH GREATER OR EQUAL TO

TWELVE FEET (12')

SECTION 607 - SIGN SUPPORTS

ITEM 6070010 - SIGN POST (PERFORATED) (SINGLE)

ITEM 6070110 - FOUNDATION FOR SIGN POST (PERFORATED)

ITEM 6072000 - SIGN MOUNT ASSEMBLIES (MAST ARM MOUNTED)

ITEM 6072001 - SIGN MOUNT ASSEMBLIES (FLAG MOUNTED)

SECTION 608 - SIGN PANELS

SECTION 701 - MAINTENANCE AND PROTECTION OF TRAFFIC

SECTION 704 - THERMOPLASTIC STRIPES AND MARKINGS

ITEM 7040005 - PAVEMENT MARKING (WHITE EXTRUDED

THERMOPLASTIC) (0.090”)

ITEM 7040006 - PAVEMENT MARKING (YELLOW EXTRUDED

THERMOPLASTIC) (0.090”)

ITEM 7040032 - PAVEMENT MARKING (WHITE EXTRUDED

THERMOPLASTIC) SGL. ARROW (0.090”)

ITEM 7040062 - PAVEMENT LEGEND (WHITE EXTRUDED THERMOPLASTIC)

(ONLY) (0.090”)

ITEM 7040130 - PAVEMENT MARKING (WHITE EXTRUDED

THERMOPLASTIC) (TRANSVERSE) (0.090”)

SECTION 706 - RAISED PAVEMENT MARKERS

ITEM 7060020 - PAVEMENT MARKING, REFLECTIVE (TYPE C, CLEAR, RED)

SECTION 708 - PAINTED PAVEMENT MARKINGS

ITEM 7080001 - PAINTED PAVEMENT MARKING

SECTION 731 - STRUCTURAL SUPPORTS & FOUNDATIONS FOR TRAFFIC

SIGNAL & STREET LIGHTING SYSTEMS

ITEM 7310354 - EXISTING CONTROL CABINET FOUNDATION

MODIFICATION

SECTION 732 - ELECTRICAL MATERIAL AND SERVICE

Page V

ITEM 7320020 - ELECTRICAL CONDUIT (2”) (PVC)

ITEM 7320030 - ELECTRICAL CONDUIT (3”) (PVC)

ITEM 7320040 - ELECTRICAL CONDUIT (4”) (PVC)

ITEM 7320049 - ELECTRICAL CONDUIT (2-4”) (PVC) (DIRECTION BORE)

ITEM 7320051 - ELECTRICAL CONDUIT (3-4”) (PVC) (TRENCH)

ITEM 7320420 - PULL BOX (NO. 7)

ITEM 7320421 - PULL BOX (NO. 7) (WITH EXTENSION)

ITEM 7320480 - RESET AND/OR RELOCATE EXISTING PULL BOXES

ITEM 7320631 - CONDUCTORS (TRAFFIC SIGNALS AND INTEGRAL STREET

LIGHTING) (BROADWAY & JESSICA)

ITEM 7320632 - CONDUCTORS (TRAFFIC SIGNALS AND INTEGRAL STREET

LIGHTING) (IRVINGTON & MISSION)

ITEM 7320633 - CONDUCTORS (TRAFFIC SIGNALS AND INTEGRAL STREET

LIGHTING) (DREXEL & TUCSON)

ITEM 7320612 - TRAFFIC SIGNAL GENERAL CONDUCTORS ALLOWANCE

ITEM 7320820 - BATTERY BACK UP POWER SYSTEM

ITEM 7330044 - TRAFFIC SIGNAL FACE (TYPE F) (ALUMINUM HOUSING)

ITEM 7330045 - TRAFFIC SIGNAL FACE (TYPE F)

ITEM 7330070 - TRAFFIC SIGNAL FACE (TYPE G)

ITEM 7330086 - TRAFFIC SIGNAL FACE (TYPE G) (ALUMINUM HOUSING)

ITEM 7330202 - TRAFFIC SIGNAL FACE (PEDESTRIAN) (COUNT DOWN)

ITEM 7330305 - TRAFFIC SIGNAL MOUNTING ASSEMBLY (TYPE II)

ITEM 7330315 - TRAFFIC SIGNAL MOUNTING ASSEMBLY (TYPE IV)

ITEM 7330320 - TRAFFIC SIGNAL MOUNTING ASSEMBLY (TYPE V)

ITEM 7330325 - TRAFFIC SIGNAL MOUNTING ASSEMBLY (TYPE VI)

ITEM 7330330 - TRAFFIC SIGNAL MOUNTING ASSEMBLY (TYPE VII)

Page VI

ITEM 7330350 - TRAFFIC SIGNAL MOUNTING ASSEMBLY (TYPE XI)

SECTION 734 - TRAFFIC SIGNAL CONTROLLER ASSEMBLY

SECTION 735 - DETECTORS

SECTION 803 - LANDSCAPE BORROW AND PLATING MATERIAL

SECTION 806 - TREES, SHRUBS AND PLANTS

ITEM 8061700 - LANDSCAPE PRUNING

SECTION 908 - CONCRETE CURBS, GUTTERS, SIDEWALKS AND

DRIVEWAYS

ITEM 9080005 - CONCRETE CURB (STD DTL 209) (TYPE 2)

ITEM 9080051 - CONCRETE CURB AND GUTTER (STD DTL. 209) (TYPE 1G)

ITEM 9080088 - CONCRETE RAMP CURB (STD. DTL. 207)

ITEM 9080090 - CONCRETE CURB TERMINAL SECTION (STD DTL. 212)

ITEM 9080150 - CONCRETE MEDIAN PAVEMENT

ITEM 9080201 - CONCRETE SIDEWALK

ITEM 9080290 - CURB ACCESS RAMP

ITEM 9080402 - CONCRETE HEADER

SECTION 924 - CONTRACTOR QUALITY CONTROL

SECTION 930 - INCIDENTAL ITEMS

SECTION 932 - PAVERS

SECTION 1005 - BITUMINOUS MATERIALS FOR SURFACING

SECTION 1007 - RETROREFLECTIVE SHEETING

ATTACHMENT A – TYPE B TRENCH DETAIL

ATTACHMENT B – HOLIDAY RESTRICTIONS

ATTACHMENT C – UTILITY COORDINATION STATUS SUMMARY

ATTACHMENT D – UTILITY COORIDNATION LETTERS

SPECIFICATIONS AND DETAILS

The work embraced herein shall be performed in accordance with the requirements of the following separate documents:

Specifications

Pima Association of Governments (PAG), Standard Specifications for Public Improvements, 2015

Edition, Volume 1 (typically referenced as “Standard Specifications” unless otherwise specified).

http://apps.pagnet.org/standardspecifications/

Details

PAG, Standard Details for Public Improvements, 2015 Edition, Volume 2, except as modified on the plans.

http://apps.pagnet.org/standardspecifications/

City of Tucson Department of Transportation and Mobility (DTM), Curb Access Ramp Detail, 2025. See Appendix B of these Special Provisions (Sheets 1 through 15).

https://www.tucsonaz.gov/files/sharedassets/public/v/1/transportation-and-mobility/engineering/documents/curb_access_ramp_sep2025.pdf

City of Tucson DTM, Longitudinal Joint Detail, 2024. See Appendix E of these Special Provisions

(Sheet 1 of 1).

https://www.tucsonaz.gov/files/sharedassets/public/v/1/transportation-and-mobility/dtm/documents/divisions/engineering/longitudinal-joint-detail.pdf

ADOT, Engineering And Construction, Construction Standard Drawings, (C-Drawings), May

2012 and current revisions.

https://azdot.gov/business/engineering-and-construction/roadway-engineering/roadway-design/construction-standard

ADOT, Engineering And Construction, Signals and Lighting Standard Drawings, current revisions.

https://azdot.gov/business/engineering-and-construction/traffic/signals-and-lighting-standard-sls-drawings

Manuals

Arizona Supplement to the Manual on Uniform Traffic Control Devices (MUTCD), 2023 edition

(January 2026) https://azdot.gov/sites/default/files/2026-01/MUTCD-wAZ-Supplement.pdf

2015 Edition of the Additions by the City of Tucson to the Manual on Uniform Traffic Control

Devices, for Temporary Traffic Control http://apps.pagnet.org/standardspecifications/ http://apps.pagnet.org/standardspecifications/ https://www.tucsonaz.gov/files/sharedassets/public/v/1/transportation-and-mobility/engineering/documents/curb_access_ramp_sep2025.pdf https://www.tucsonaz.gov/files/sharedassets/public/v/1/transportation-and-mobility/engineering/documents/curb_access_ramp_sep2025.pdf https://www.tucsonaz.gov/files/sharedassets/public/v/1/transportation-and-mobility/dtm/documents/divisions/engineering/longitudinal-joint-detail.pdf https://www.tucsonaz.gov/files/sharedassets/public/v/1/transportation-and-mobility/dtm/documents/divisions/engineering/longitudinal-joint-detail.pdf https://azdot.gov/business/engineering-and-construction/roadway-engineering/roadway-design/construction-standard https://azdot.gov/business/engineering-and-construction/roadway-engineering/roadway-design/construction-standard https://azdot.gov/business/engineering-and-construction/traffic/signals-and-lighting-standard-sls-drawings https://azdot.gov/business/engineering-and-construction/traffic/signals-and-lighting-standard-sls-drawings https://azdot.gov/sites/default/files/2026-01/MUTCD-wAZ-Supplement.pdf https://www.tucsonaz.gov/files/sharedassets/public/v/1/government/departments/department-of-transportation-and-mobility/documents/2015_cot_additions_final.pdf

City of Tucson Department of Transportation, Traffic Signal Design Manual, May 2003 and current revisions https://www.tucsonaz.gov/files/sharedassets/public/v/1/dtm/documents/divisions/traffic-eng/design_manual.pdf

Pima County/City of Tucson, Signing and Pavement Marking Manual, December 2020.

https://content.civicplus.com/api/assets/c8d13f95-b46c-446e-97fe-8e5127201983

Other Specifications and Details

The Arizona Department of Transportation (ADOT) Standard Specifications for Road and Bridge

Construction, 2021 Edition.

https://azdot.gov/business/contracts-and-specifications/specifications-pay-items-list

Pima County Regional Wastewater Reclamation Department, Standard Specifications and Details for Construction, 2022 Edition.

https://webcms.pima.gov/UserFiles/Servers/Server_6/File/Government/Wastewater%20Reclama tion/Engineering/SSDC_2022_Updated.pdf

Tucson Water, Standard Specifications and Details Manual, 2017 Edition:

https://www.tucsonaz.gov/files/water/docs/StandardSpecsDetails/Tucson_Water_Standard_Speci fications_and_Details_Manual_Complete_Dec_2017_V1.pdf

These Special Provisions, Bid Schedule, and the Project Plans.

https://www.tucsonaz.gov/files/sharedassets/public/v/1/government/departments/department-of-transportation-and-mobility/documents/2015_cot_additions_final.pdf https://www.tucsonaz.gov/files/sharedassets/public/v/1/government/departments/department-of-transportation-and-mobility/documents/2015_cot_additions_final.pdf https://www.tucsonaz.gov/files/sharedassets/public/v/1/dtm/documents/divisions/traffic-eng/design_manual.pdf https://www.tucsonaz.gov/files/sharedassets/public/v/1/dtm/documents/divisions/traffic-eng/design_manual.pdf https://content.civicplus.com/api/assets/c8d13f95-b46c-446e-97fe-8e5127201983 https://azdot.gov/business/contracts-and-specifications/specifications-pay-items-list https://webcms.pima.gov/UserFiles/Servers/Server_6/File/Government/Wastewater%20Reclamation/Engineering/SSDC_2022_Updated.pdf https://webcms.pima.gov/UserFiles/Servers/Server_6/File/Government/Wastewater%20Reclamation/Engineering/SSDC_2022_Updated.pdf https://www.tucsonaz.gov/files/water/docs/StandardSpecsDetails/Tucson_Water_Standard_Specifications_and_Details_Manual_Complete_Dec_2017_V1.pdf https://www.tucsonaz.gov/files/water/docs/StandardSpecsDetails/Tucson_Water_Standard_Specifications_and_Details_Manual_Complete_Dec_2017_V1.pdf

GENERAL REQUIREMENTS

For the purpose of these Special Provisions, the terms City, City of Tucson and Engineer are synonymous.

1. Project Objectives

The objective of this contract is to complete construction as quickly as possible while minimizing the impact to the Stakeholders. Stakeholders include, but are not limited to, adjacent businesses, commuters, buses, emergency services, maintenance, pedestrians, bicyclists, adjacent schools, and adjoining neighborhoods.

The contractor shall maintain access to all side streets, access roads, driveways, alleys, parking lots, and adjacent businesses during their hours of operations.

The contractor shall ensure pedestrian access and safety across the work zone at all times.

Access to neighborhoods, businesses, and schools shall be maintained at all times.

2. Prebid Meeting

A pre-bid meeting is a part of the bid process and will be held at the location determined in the

Invitation for Bids solicitation.

The contractor shall field verify all existing conditions shown on plans prior to beginning construction. Any significant deviations to the conditions that may affect the timely construction of improvements shall be brought to the attention of the Engineer.

The contractor shall not store equipment, supplies, materials, or debris on the sidewalks or bike paths.

Before undertaking work at any location covered by this project, the contractor shall obtain all applicable permits as needed from the City of Tucson.

3. Contract Time

The contract time for the construction phase of the project shall be 180 calendar days.

4. Maintenance and Protection of Traffic

The contractor shall prepare and submit traffic control plans to the Engineer for review and approval two weeks prior to the start of the project construction activities (or at the Preconstruction

Meeting).

The traffic control plans shall conform to requirements of Part 6 of the Manual on Uniform Traffic

Control Devices (MUTCD), edition adopted by the Arizona Department of Transportation

(ADOT), Section 701 of the Standard Specifications, and these Special Provisions.

Construction work activities that impact traffic shall not begin until the traffic plan, days, and duration have been approved by the Engineer. No separate measurement or payment will be made for preparation and submittal of traffic control plans for review and approval; it will be considered included the price of the contract bid items.

Changes or revisions to the traffic control plan (TCP) and specifications shall be submitted and approved by the Engineer in advance of implementation.

The contractor shall not store equipment, supplies, materials, or debris on the sidewalks or bike paths.

The contractor shall be required to check on all traffic control barricading, signing and message boards twice daily and maintenance, as needed.

Residential and commercial driveway access shall be continuously maintained.

The contractor is advised of the Civil Sanctions for Temporary Traffic Control Violations included in Section 20 of the Additions by the City of Tucson to the Manual on Uniform Traffic Control

Devices, for Temporary Traffic Control.

The contractor shall provide a clear and safe pedestrian access travel way at all times during construction. Safe pedestrian access through the construction site shall be provided during and after regular work hours.

The contractor shall contact local law enforcement, local fire department and local ambulance services a minimum of 72 hours in advance of any roadway restrictions. The contractor shall ensure that emergency vehicles have access to the project area and adjacent residences at all times.

The existing traffic signal operations at the various intersections identified in the plans shall be operational and continuous twenty-four (24) hours per day, seven (7) days a week. Any periods of time for which the signals are temporarily out of service shall be controlled by uniformed law enforcement agency personnel.

The contractor shall not schedule any traffic restrictions during weekends or recognized holidays, unless otherwise approved by the Engineer. Holidays are from 12:00 PM of the last working day prior to the holiday until 6:00 AM of the first working day following the holiday. When the holiday falls on a Tuesday, the Monday before the holiday is considered part of the holiday.

The contractor shall provide all safety equipment, barricades, proper lighting and all other items to perform nighttime work when deemed necessary by the Engineer.

5. Project Limits and Restrictions

The contractor shall perform all work within the public right-of-way. The contractor shall assume all responsibility and liability for any encroachment upon private property. The use of private property for construction yards will be allowed only if zoning requirements allows its use for this purpose. Under no circumstances shall any equipment, vehicles or other construction items, not specifically required or needed for the immediate construction at hand, be stored or left on private property without the express permission of the property owner.

The contractor shall not block or impede access to any business services including but not limited to fuel islands and drive throughs.

No ground disturbing activities shall take place at the Irvington Road and Mission Road intersection.

6. Material Sources

Material sources shall be as specified in the project plans, Section 1004, 1005, 1006, 1007 and

1008 of the Standard Specifications.

7. Salvaged Items

All materials identified as on the plans to be salvaged as part of this project shall be delivered to a location as directed by the Engineer.

Signs shall be removed and salvaged in accordance with the plans and these Special Provisions.

Salvaged signs shall be delivered to the City of Tucson Sign Shop at 4004 S. Park Avenue, Building 6 (West End). The contractor shall contact April Ormsby (april.ormsby@tucsonaz.gov)

(520-373-3641) at least 5 working days in advance to coordinate the time and location for delivery of salvaged signs.

Traffic signal equipment shall be removed and salvaged in accordance with the plans and these

Special Provisions. Salvaged traffic signal equipment shall be delivered to the City of Tucson

Streets and Traffic Maintenance Division yard. The contractor shall contact Armando Bracamonte

(520-429-6647, armando.bracamonte@tucsonaz.gov) one week prior to delivery to coordinate the time and location for delivery of the salvaged traffic signal equipment.

The contractor shall be responsible for all loading, unloading, and hauling of all salvaged materials at the location specified. No measurement of direct payment will be made for this work, the cost being considered as included in the price of contract items.

8. Staging Area

Identification of equipment, materials storage/stockpiling and Contractor/Sub-contractor parking shall be the responsibility of the Contractor. The Contractor shall provide the Engineer with a copy of the written approval of the property owner indicating that the property owner is fully aware and agreeable to said equipment, material storage/stockpiling, and Contractor/Sub-contractor parking.

This written approval is to be provided to the Engineer prior to commencement of the work.

No work shall be allowed to commence unless the conditions and requirements of this specification section is adhered to. Failure of the contractor to abide by this specification section shall be sufficient grounds for the City to suspend work.

9. Environmental Requirements and Mitigation Measures

The project mitigation measures are not subject to change without written approval from ADOT

Environmental Planning. The Contractor shall follow all the requirements of the permits specified herein and comply with the project special provisions as well as the PAG Standard Specifications for Public Improvements, as well as all applicable local environmental requirements.

If vegetation clearing will occur during the migratory bird breeding season (March 1–August 31), the contractor shall avoid any active bird nests. If the active nests cannot be avoided, the contractor shall notify the Engineer to evaluate the situation. During the non-breeding season (September 1–

February 28) vegetation removal is not subject to this restriction.

The contractor shall develop a Noxious and Invasive Plant Species Treatment and Control Plan in accordance with the requirements in the contract documents:

• Plants to be controlled shall include those listed in the state and federal noxious weed and the state invasive species lists in accordance with state and federal laws and executive orders.

• The plan and associated treatments shall include all areas within the project right-of-way and easements as shown on the project plans.

• The treatment and control plan shall be submitted to the Engineer for the Department of

Transportation and Mobility Professional Landscape Architect for review and approval prior to implementation by the contractor.

• Control of noxious and invasive species in the project area shall be performed prior to the start of ground-disturbing activities, throughout the duration of construction, and any landscape establishment period.

For median modifications:

• Prior to beginning any work, an approved contractor shall develop and implement a Lead-

Based Paint Removal and Abatement Plan for the removal of the lead-based paint, Toxicity

Characteristic Leaching Procedure testing of the generated waste stream, and proper disposal of the waste stream derived from the median modifications within the project limits. The contractor shall select a lead abatement contractor that meets the qualification requirements specified within the special provisions and as approval by the Engineer. The contractor shall follow all applicable federal, state, and local codes and regulations, including Arizona Department of Transportation Standard Specifications for Road and

Bridge Construction (2021 Edition), related to the treatment and handling of lead-based paint. The contractor shall submit the Lead-Based Paint Removal and Abatement Plan to the Engineer and the ADOT Environmental Planning Hazardous Materials Coordinator

(602.920.3702 or 602.712.7767) for review and approval at least 10 (ten) working days prior to beginning the work.

Visible fugitive dust emissions from paint removal shall be controlled through wet or dry (e.g., vacuum) means during the removal process. If the liquid waste stream generated by a water-blasting obliteration method passes the Toxicity Characteristic Leaching Process analysis, it may be used as a dust palliative or for compaction on the project. If the water is not used on the project, it shall be properly disposed of in accordance with all applicable federal, state, and local regulations.

10. Soil Conditions

Contractor shall be made aware that during design, potholing encountered caliche at shallow depths at the intersection of Drexel Road and Tucson Bouleveard. There shall be no separate measurement for providing any mitigation for hard dig areas at any intersection on the project, the cost being considered as included in the price of the other items.

SECTION 101 - ABBREVIATIONS AND DEFINITIONS

101-3 TERMS: of the Standard Specifications are revised as follows:

Supplemental Agreement – Add the following: “All supplemental agreements will be issued in compliance with City of Tucson Procurement Code.”

SECTION 104 - SCOPE OF WORK

104-1 INTENT OF CONTRACT: of the Standard Specifications is modified to add:

(A) Covenant of Good Faith and Fair Dealing

This contract imposes an obligation of good faith and fair dealing in its performance and enforcement.

The contractor and the Department, with a positive commitment to honesty and integrity, agree to the following mutual duties:

1. Each will function within the laws and statutes applicable to their duties and responsibilities.

2. Each will assist in the other's performance.

3. Each will avoid hindering the other's performance.

4. Each will proceed to fulfill its obligations diligently.

5. Each will cooperate in the common endeavor of the contract.

(B) Communication Chain and Escalation Ladder:

The City of Tucson Department of Transportation and Mobility intends to encourage the foundation of a cohesive partnership with the contractor and its principal subcontractors and suppliers. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objectives are effective and efficient contract performance and completion within budget, on schedule, and in accordance with plans and specifications.

Should issues arise that will affect performance, budget, or schedule, the contractor’s superintendent shall discuss and attempt to work out a solution that is agreeable to the assigned inspector. If no resolution is possible in one day, the issue shall be escalated to the contractor’s

Project Manager and the City of Tucson’s Project Manager.

The two project managers shall attempt to work out a solution. If no solution can be agreed upon within three days, the issue shall be escalated to the contractor owner and the City’s Field

Engineering Manager.

104-5 Maintenance of Traffic: of the Standard Specifications is modified to add:

The contractor shall maintain access to all side streets, access roads, businesses, residences, driveways, alleys and parking lots.

Throughout the duration of construction, access by Emergency Services, Sun Tran and mail delivery shall be maintained.

The contractor shall not store equipment, supplies, materials, or debris on the sidewalks or bike paths. Pedestrian access shall be maintained on at least one side of the street throughout the duration of the project.

The existing traffic signal operations at the various intersections identified in the plans shall be operational and continuous twenty-four (24) hours per day seven (7) days a week. Any periods of time for which the signals are temporarily out of service shall be controlled by Uniformed Law

Enforcement personnel and marked car.

The contractor shall not schedule any traffic restrictions during weekends or recognized holidays, unless otherwise approved by the Engineer. Holidays are from 12:00 PM of the last working day prior to the holiday until 6:00 AM of the first working day following the holiday. When the holiday falls on a Tuesday, the Monday before the holiday is considered part of the holiday.

The contractor shall provide all safety equipment, barricades, proper lighting and all other items to perform nighttime work when deemed necessary by the Engineer.

104-6 Maintenance of the Project Site: of the Standard Specifications is modified to add:

Any existing or salvaged materials damaged by the contractor during construction shall be repaired and/or replaced. The cost of such repair and replacement shall be at the Contractors expense. It is the responsibility of the contractor to become thoroughly familiar with all visible features of the site before preparing his proposal.

104-8 Final Clean Up: of the Standard Specifications is added:

No accumulation of materials, debris, rubbish, etc., shall be left at any site overnight. All areas

(sites) shall be left reasonably clean (as determined by the project inspector) at the end of each day.

SECTION 105 - CONTROL OF WORK

105-6 Cooperation with Utility Companies: the sixth paragraph of the Standard

Specification is modified to add:

The contractor will acknowledge and agree that no monetary compensation will be given to the contractor by the Agency as a result of the impacts or delays to his operations that are caused by the utility companies.

105-17.02 Substantial Completion: the Standard Specification is modified to add:

Once substantial completion is granted, the contractor shall actively work to achieve Final

Acceptance of the construction phase of the Contract within 21-calendar days from the

Substantial Completion date of that phase. Failure to prosecute the remaining work within this time period will result in the resumption of time charges and the application of liquidated damages from the date scheduled for final acceptance.

The contractor is responsible for maintenance and repairs of any project work until final acceptance, at which time the City will accept the improvements for operation and maintenance.

105-17.04 Final Acceptance: the thrid paragraph of the Standard Specification is modified to add:

In addition, final acceptance will not be made until all completed record drawings and working drawings, as required in Subsection 105-2, have been submitted and deemed acceptable by the

Engineer.

105-18 Claims: of the Standard Specification is modified to add:

The administrative process for resolution of disputes and claims is sequential in nature and is composed of the following steps:

Step I Review by City of Tucson DTM

Step II Review by Procurement

Step III Review by the City Attorney’s Office

If the contractor rejects the decision of DTM, the dispute or claim will be forwarded to the

Procurement for resolution in accordance with the Procurement Code.

105-18.01 Notice of Claims: of the Standard Specifications is modified to add:

Reference to the authorized representative shall mean the Procurement Contract Officer.

References to submissions to the Engineer or authorized representative shall be modified to include submissions to both the Engineer and authorized representative.

105-18.02 Submission of Claims: of the Standard Specifications is modified to add:

Reference to the authorized representative shall mean the Procurement Contract Officer.

References to submissions to the Engineer or authorized representative shall be modified to include submissions to both the Engineer and authorized representative.

Content of the Claim: The claim shall be in writing and shall include the following information:

(a) The name, address, telephone number and email address of the claimant;

(b) The signature of the claimant or its representative

(c) Identification of the solicitation or contract number

(d) A detailed statement of the legal and factual grounds of the claim including copies of relative documents as described in Section A and Section B of the

Standard Specifications; and

(e) The form of relief requested.

105-18.03 Decision on Claims: of the Standard Specifications is revised to read:

The decision of claims shall be made by the Procurement Department’s Contract Officer in accordance to Tucson Code Section 28-92.

105-20 MEDIATION OF CLAIMS AND DISPUTES: of the Standard Specifications is modified to add:

Notwithstanding Section 105-18.03 of the Standard Specifications, if the contractor is not satisfied with the decision of the Engineer, and prior to filing for arbitration or litigation, the contractor may request a non-binding mediation by filing a request for mediation in writing with the Engineer.

The Engineer will then arrange for a mutually agreeable mediator. Such request for mediation shall be made within 30 calendar days from actually receiving the Engineer’s decision as provided for in this section.

In connection with the mediation, each party shall bear its own costs, and any fees and expenses assessed by the mediator shall be borne equally by both parties.

SECTION 106 - CONTROL OF MATERIAL

106-4 Tests and Acceptance of Materials: of the Standard Specifications is modified to add:

(A) Contractor Quality Control. The contractor is responsible for quality control measures necessary to provide acceptable quality in production, handling, and placement of all materials.

The contractor shall provide all the personnel, equipment, materials, supplies, and facilities necessary to obtain samples and perform tests listed in the applicable section. The contractor shall designate a qualified employee as Quality Control Manager to be responsible for implementing, monitoring, and as necessary, adjusting the processes to ensure acceptable quality. All testing shall be performed by a laboratory listed for the tests to be performed in the ADOT Directory of Approved Materials Testing Laboratories, meeting the requirements of “System for the Evaluation of Testing Laboratories.” Sampling and testing shall be performed by and under the direction of ATI and ACI certified technicians and supervisors. The directory and certification requirements may be obtained from the City’s Materials Laboratory at (520-791-3127). Payment for contractor quality control shall be made in accordance with Section 924, Contractor Quality Control, of these Special Provisions.

The City will perform the quality assurance testing for the purpose of accepting the contractor’s test results.

Minimum Testing Frequency information is shown in the following tables (Table 106-1) for any appropriate testing required as needed for the items in the project. Additional testing requirements are as specified in the most recent update of Section 900 of the Arizona Department of Transportation, Materials Testing Manual. The contractor may provide certificates of analysis or certificates of compliance for items identified in the City of Tucson/Pima County Standard Specifications for Public Improvement in lieu of the testing requirements of those materials identified in the ADOT Materials Testing Manual.

(B) Specific Contractor Quality Control Measures.

Quality Control Plan: At the preconstruction conference, the contractor shall designate a qualified employee as Quality Control Manager to be responsible for implementing, monitoring and, as necessary, adjusting the processes to ensure acceptable quality. Also at the preconstruction conference, the contractor shall be prepared to discuss his understanding of the quality control responsibilities for the specified materials.

Records: The contractor shall maintain complete testing records and make them available to the Engineer for review and copies as requested.

Weekly Quality Control Reports: The contractor shall submit Weekly Quality Control Reports to the Engineer. The weekly reports shall state the types of work, such as earthwork, Portland cement concrete, or asphaltic concrete, which have been performed during the report period, and shall also include the process control measures taken to ensure quality. The weekly report shall provide sample identification information for materials tested during the report period, including sample number, date sampled, sample location, person obtaining sample, and original source of material. The report shall also provide the results for all required tests and any retests, corrective actions, and any other information relevant to quality control. Although hand-written documentation can be included, the quality control report narrative, sample identification information, results for tests and any retests, and corrective actions shall be typed to ensure the Department can make clear reproductions of the documents.

The report period shall end at midnight of each Friday, and the report shall be submitted to the Engineer no later than 5:00 p.m. of the following Wednesday or at a time agreed upon by the Engineer.

Table 106-1

CONTRACTOR QUALITY CONTROL TESTING REQUIREMENTS

TYPE OF

TEST

TEST

METHOD

SAMPLING

POINT

MINIMUM TESTING

FREQUENCY

Structural Backfill (203-5, 501, 502, 503, 505, 508, 509, 510, 610, 731, 732, 906 & 920)

Gradation ARIZ 201 Stockpile

1 per 500 CY per Source

1 per source PI AASHTO T 89, T 90

Proctor Density ARIZ 225, ARIZ 226, ARIZ 245

1 per Source

Compaction ARIZ 227, ARIZ 230, ARIZ 231, ARIZ 232, ARIZ 235, ARIZ 246

In-place 1 per 200 CY, minimum

1 per lift

Roadway Subgrade

Gradation ARIZ 201 Roadway 1 per Soil Type

PI AASHTO T 89, T 90

Proctor Density ARIZ 225, ARIZ 226, ARIZ 245

Compaction ARIZ 227, ARIZ 230, ARIZ 231, ARIZ 232, ARIZ 235, ARIZ 246

Roadway 1 per 1,000 feet

Sidewalk Subgrade

Proctor Density ARIZ 225, ARIZ 226, ARIZ 245

Roadway Prism 1 per Soil Type

Compaction ARIZ 227, ARIZ 230, ARIZ 231, ARIZ 232, ARIZ 235, ARIZ 246

Roadway Prism 1 per 2000 square feet of sidewalk and/or 1 per 500 square feet of curb access ramp

Proctor Density ARIZ 225, ARIZ 226, ARIZ 245

In-place 1 per Soil Type

Compaction ARIZ 227, ARIZ 230, ARIZ 231, ARIZ 232, ARIZ 235, ARIZ 246

In-place 1 per 1,000 feet per lift

Embankment

Proctor Density ARIZ 225, ARIZ 226, ARIZ 245

In-place 1 per Soil Type

Compaction ARIZ 227, ARIZ 230, ARIZ 231, ARIZ 232, ARIZ

235, ARIZ 246

In-place 1 per 1,000 feet per lift

Borrow Within Three Feet of Finished Subgrade Elevation

Gradation ARIZ 201 Stockpile 1 per Source

1 per Source PI AASHTO T 89, T 90

Aggregate Base

Fractured Coarse Aggregate Particles

ARIZ 212 Crusher belt or Stockpile 1 per Source

CONTRACTOR QUALITY CONTROL TESTING REQUIREMENTS

TYPE OF

TEST

TEST

METHOD

SAMPLING

POINT

MINIMUM TESTING

FREQUENCY

Gradation ARIZ 201 1 per 600 CY

PI AASHTO T89, T90

Proctor Density ARIZ 225, ARIZ 226, ARIZ 245

1 per Source

Compaction ARIZ 227, ARIZ 230

ARIZ 331, ARIZ 232

ARIZ 235, ARIZ 246

Roadway 1 per 600 CY

Asphaltic Concrete Aggregate (all types) MA for AC

Sand Equivalent AASHTO T 176 Cold Feed 1 per 2000 tons of total aggregate.

Fractured Course Aggregate Particles

ARIZ 212 Cold Feed 1 per 2000 tons of total aggregate.

Uncompacted Void Content ARIZ 247 Cold Feed 1 per 2000 tons of total aggregate.

Gradation ARIZ 201 Cold Feed 1 per 500 tons

Asphaltic Concrete

Voids ARIZ 415, ARIZ 417, ARIZ 424

Roadway or Plant 1 per 500 tons of asphaltic concrete production

Asphalt Content ARIZ 421, ARIZ 427 or other approved methods

Roadway or Plant 1 per 500 tons of each mix

Gradation ARIZ 201 or ARIZ 427 Cold Feed or Plant 1 per 500 tons

Compaction ARIZ 412 OR ARIZ 104, Sec. 3, ARIZ 415, ARIZ 410a

Roadway 1 per 300 tons of asphaltic concrete production, minimum of one per shift

Asphaltic Concrete (Asphalt Rubber) (in addition to the requirements above) Asphaltic Concrete (Asphalt Rubber)

(in addition to the requirements above)

Asphalt Rubber Content ARIZ 421 Roadway 4 times per full shift Nuclear Gauge

Backfill and Bedding Material (501, 502, 508, 510, 511, 732 & 932)

Gradation ARIZ 201 Stockpile 1 per 500 CY 1 per Source

PI AASHTO T 89, T 90

Proctor Density ARIZ 225, 226, 245 1 per Source

Compaction ARIZ 227, 230, 231, 232, 235, 246

In-place 1 per 200 CY, minimum 1 per lift

Thermoplastic Striping (704)

Thickness Standard Specification 704- 3.03

In-place 1 per color per production day of long line and of short line

Fine Aggregate for Portland Cement Concrete

Gradation ARIZ 201 Crusher Belt or Stockpile 1 every other day Sand Equivalent AASHTO T176

CONTRACTOR QUALITY CONTROL TESTING REQUIREMENTS

TYPE OF

TEST

TEST

METHOD

SAMPLING

POINT

MINIMUM TESTING

FREQUENCY

Coarse Aggregate for Portland Cement Concrete

Gradation ARIZ 201 Crusher Belt or Stockpile 1 every other day

Class B and Class S Portland Cement Concrete

Entrained Air (above 3,000

ft. elev. only)

AASHTO T 152 At Point of Discharge 1 per 100 Cubic Yards of Ea.

Class of Concrete

Slump AASHTO T 119 At Point of Discharge 1 per 100 CY or fraction thereof of continuously placed concrete, on a daily basis, for each class or source

Temperature ASTM C 1064 At Point of Discharge (SS –1006-5.02 and 5.03)

1 per 100 CY or fraction thereof of continuously placed concrete, on a daily basis, for each class or source

Fabrication of Test Cylinders

AASHTO T 141 At Point of Discharge

(SS-1006-7.02)

1 set per 100 CY or fraction thereof of continuously placed concrete, on a daily basis, for each class or source

Compressive Strength Test

Cylinders 28 day *

AASHTO T 23 At Point of Discharge

(SS-1006-7.06)

1 set per 100 CY or fraction thereof of continuously placed concrete, on a daily basis, for each class or source

* Additional cylinders may be taken by the contractor for their convenience for early breaks at the contractor’s cost.

For asphalt concrete testing the contractor shall perform the quality control measures described in the table above and the measures detailed below. At the weekly meeting, the contractor shall be prepared to explain and discuss how the following processes will be employed.

(a) Aggregate production, including crusher methods, pit extraction, and washing.

(b) Stockpile management, including stacking methods, separation technique, plant feed technique, stockpile pad thickness, and segregation prevention.

(c) Proportioning and plant control, including plant scale calibration, mix temperature control, storing method, and addition of admixture.

(d) Transporting and placing, including hauling distance and temperature control, segregation and non-uniform placement control, and joint placement and technique.

(e) Compaction, including types and weight of rollers, establishing and monitoring of roller patterns, and temperature controls.

SECTION 107 - LEGAL RELATIONS AND RESPONSIBILITY TO

PUBLIC

107-6.01 Archaeological Features. The Standard Specifications is modified to add:

In the event that archaeological or historical features are encountered, cease work that could damage the features and contact the City of Tucson Historic Preservation Office at 837-6968 or

791-4171 and the Engineer.

107-8 PUBLIC CONVENIENCE AND SAFETY

The Standard Specifications is modified to add:

The contractor shall provide pedestrian and bicycle access at all times, adjacent to the work area.

Any disturbance of landscaping by grading needed to provide access shall be replaced when the work is complete. Materials necessary to meet the intent of this requirement shall be removed upon completion. The costs of said work or materials shall be considered incidental to the contract and included in the overall bid price.

In general, business access will be maintained at all times. Where additional driveway access is necessary to provide access and to ensure the safe traffic circulation of large delivery vehicles, secondary driveways or affecting improvements, driveways shall be built one half at a time to provide at least one lane ingress/egress during the respective construction.

107-15 PREVENTION OF LANDSCAPE DEFACEMENT; PROTECTION OF

STREAMS, LAKES, AND RESERVOIRS is hereby added to the Standard

Specifications:

107-15.01 National Pollution Discharge Elimination System

107-15.01(A) General.

This project is less than 1 acre. The Contractor shall implement the Arizona Department of

Environmental Quality (ADEQ) requirements for protecting the quality of stormwater runoff during construction, as specified under the Arizona Pollutant Discharge Elimination System

(AZPDES) General Permit for Construction Activities.

The construction activities are considered “Exempt Discharges” under AZPDES General Permit for Construction Activities, Part 1.D.6.b. However, efforts to prevent pollutants from discharging from the project must be utilized by providing, installing, maintaining, removing and disposing of erosion control measures including, but not limited to, such items as gravel filter berms, dikes, catch basin inlet protection, end-of-pipe filtering devices, silt fences, dams, sediment basins, netting, straw bale barriers, slope drains, and other erosion control devices or methods.

107-15.01(B) Materials.

The Contractor shall not be required to prepare a Stormwater Pollution Prevention Plan (SWPPP) but shall follow Best Management Practices in accordance with the AZPDES General Permit for

Construction Activities, in conjunction with the City of Tucson Construction Project Manager and the City of Tucson Stormwater Management Section.

A Notice of Intent (NOI) and Notice of Termination (NOT) shall not be required.

107-15.01(C) Construction.

As part of the contractor’s Best Management Practices, the following items shall be considered to protect stormwater quality during the course of construction:

• Spill Containment Plan

• Stabilized construction entrances

• Equipment maintenance procedures

• Designated washout areas

• Protected chemical and materials storage area

• Solid Waste Management

• Dust control

• Construction road stabilizing

• Protection of catch basins

• Sediment traps and barriers

• Any non-stormwater discharges

107-15.01(D) Method of Measurement.

There shall be no separate measurement for providing ‘good housekeeping’ practices, the cost being considered as included in the price of the other items.

107-15.01(E) Basis of Payment.

No measurement or direct payment will be made for the contractor’s Best Management Practices to protect stormwater quality.

107-21 CONTRACTOR’S RESONSIBILITY FOR UTILITY PROPERTY AND

SERVICES of the Standard Specifications is modified to add:

The following utility companies have facilities in the project area but are not anticipated to be in conflict:

Utility Agency Contact Phone

AT&T

Joseph Forkert

Tanya Hernandez

(714) 963-7964

(619) 200-7896

CenturyLink/Lumen

Kevin Wagner

Andre Hatcher Mike Thompson

(815) 245-9640

(602) 430-9388

(928) 211-4133

City Of Tucson Dept of Transp. - Traffic Eng Armando Bracamonte (520) 837-6802

Cogent Communications (Sprint Communications) David Jeter (422) 202-5262

Cox Communications

Jacob Horsman

Luke Moschgat

(623) 328-2202

(520) 909-3108

Crown Castle Solutions Jose Madrigal (480) 529-2231

First Digital Ryan Layton (520) 262-5667

Pima County Wastewater Reclamation Thomas Porter (520) 724-6719

Southwest Gas

Fernando Soto

Aridai Rosas

(520) 262-6551

(520) 794-6165

Tucson Electric Power Eduardo Leon (520) 833-4995

Tucson Water

Ali Fermawi

Kevin Miller Stephanie Winick

(520) 460-6489

(520) 837-2131

(520) 349-2150

The contractor shall follow the Arizona 811 Laws to locate and coordinate prior to start of any construction activities at each location.

The utility requirements for each utility agency are listed as follows:

CenturyLink/Lumen

AT&T has no active facilites (transcontinential fiber optic lines) within the vicintity of this project.

CenturyLink/Lumen

Protect in place and maintain a minimum of 12 inches of vertical and horizontal separation from existing underground and aerial CenturyLink/Lumen facilities at all times.

Additionally, CenturyLink/Lumen request to be notified of upcoming coordination milestones or

Preconstruction Meetings, to review updated plans before advertising, and to ensure state-law requirements are followed for blue staking, facility protection, and minimum separation during construction. ROW acquisition is the municipality’s responsibility and that any necessary facility relocations may be at the sponsoring agency’s expense, with contractors required to contact

CenturyLink/Lumen if unknown facilities are encountered.

Cogent Communications

Protect in place and maintain a minimum of 12 inches of vertical and horizontal separation from existing underground Cogent Communication facilities at all times.

Cox Communications

Protect in place and maintain a minimum of 12 inches of vertical and horizontal separation from existing underground and aerial Cox Communications facilities at all times.

The contractor is responsible for complying with all utility-locate laws and verifying the location of all nearby utilities, including Cox Communication Facilities, and must ensure they remain supported and protected throughout construction activities. If work occurs near Cox

Communication Facilities, the contractor is required to perform potholing and take all necessary measures to prevent disturbance or damage.

Crown Castle Solutions

Protect in place and maintain a minimum of 12 inches of vertical and horizontal separation from existing aerial Crown Castle facilities at all times.

First Digital

Protect in place and maintain a minimum of 12 inches of vertical and horizontal separation from existing underground and aerial Crown Castle facilities at all times.

Pima County Wastewater Reclamation

Protect in place all Pima County Wastewater Reclamation facilities.

Southwest Gas

Protect in place and maintain a minimum of 12 inches of separation from existing underground

Southwest Gas facilities at all times.

If structures are to be install above/underneath existing Southwest Gas facilites, the contractors responsibility is to support and protect them in place during construction. Southwest Gas has valves within the project area that may need to be protected and adjusted to final grade. The contractor must contact SWG at least two weeks before the start of construction to schedule valve adjustments by calling Melina Lazo at 520-279-3840.

Tucson Electric Power

Protect in place and maintain a minimum of 10 feet of radial clearance from existing overhead

Tucson Electric Power facilities at all times.

Contractors must proactively assess each site for required overhead and underground protection around TEP facilities, maintain drivable access to all TEP equipment, and follow TEP’s seasonal restrictions on facility relocations. They are also responsible for contacting Blue Stake, coordinating protection needs with TEP at least 10 working days in advance, and covering all costs for required overhead/excavation protection or repairs if any TEP facilities are damaged. For more information, refer to the following:

https://www.tep.com/Customer/Construction/ESR/ https://www.tep.com/Resources/Safety/Overhead/ https://www.tep.com/Customer/Construction/ESR/ https://www.tep.com/Resources/Safety/Overhead/

Tucson Water

Protect in place and maintain two feet of vertical separation from the outside diameter of all existing Tucson Water facilities and five feet of horizontal separation from the outside diameter of all existing Tucson Water facilities at all times.

The following utility companies have aerial facilities within close proximity of the proposed construction and anticipate certain possible safety requirements to work near them:

Company Conflict(s) Conflict Resolution

CenturyLink/Lumen Potential conflict between aerial facilities and proposed traffic signal improvements.

Protect in place and maintain a minimum of 12 inches of vertical and horizontal separation from existing aerial CenturyLink/Lumen facilities at all times.

Cox Communications Potential conflict between aerial facilities and proposed traffic signal improvements.

Protect in place and maintain a minimum of 12 inches of vertical and horizontal separation from existing aerial Cox Communication facilities at all times.

Crown Castle Solutions Potential conflict between aerial facilities and proposed traffic signal improvements.

Protect in place and maintain a minimum of 12 inches of vertical and horizontal separation from existing aerial Crown Castle Solutions facilities at all times.

First Digital Potential conflict between aerial facilities and proposed traffic signal improvements.

Protect in place and maintain a minimum of 12 inches of vertical and horizontal separation from existing aerial First Digital facilities at all times.

Tucson Electric Power Potential conflict between aerial facilities and proposed traffic signal improvements.

Protect in place and maintain a minimum of 10 feet of radial clearance from existing aerial Tucson

Electric Power facilities at all times.

The project has a network of underground and overhead power lines. All work at or within close proximity to said lines shall be performed in accordance with all Federal, State, and local laws and regulations, including but not limited to:

(1) Arizona law regarding “Underground Facilities” (A.R.S. 40-360.21, .22, .24, .26 and

.28).

(2) Arizona law regarding “High Voltage…